Miller-Davis Co. v. Ahrens Construction, Inc.

848 N.W.2d 95, 495 Mich. 161
Michigan Supreme Court·Decided April 15, 2014·No. Docket 145052·Published·Cited by 326 cases

Opinion

KELLY, J.

After nearly a decade of litigation and alternative dispute resolution proceedings, the indemnification contract underlying the troubled natatorium roof in this case again wends its way to this Court. We previously held that the six-year period of limitations of MCL 600.5807(8) applies to the parties’ indemnification contract. We now hold that the indemnity clauses in the parties’ subcontract apply here, because the plain language of the indemnification clauses extends to Ahrens’s failure to undertake corrective work as obligated by the subcontract. We further hold that Sherman Lake YMCA made a “claim” upon Miller-Davis which triggered Ahrens’s liability under the indemnity clauses. Ahrens’s failure to indemnify therefore caused the damages Miller-Davis sustained in undertaking the corrective work itself. Finally, we hold that Miller-Davis’s claim was not barred by the six-year statute of limitations found in MCL 600.5807(8). Rather, Miller-Davis’s breach of contract claim for Ahrens’s failure to indemnify is distinct from its breach of contract claim based on Ahrens’s failure to install the roof according to *166 specifications, and Miller-Davis’s indemnity action necessarily accrued at a later point. We therefore reverse that portion of the Court of Appeals’ opinion discussing Miller-Davis’s indemnity claim, and remand this case to the Kalamazoo Circuit Court for entry of judgment in Miller-Davis’s favor and to determine whether Miller-Davis is entitled to attorney’s fees under the relevant indemnification clauses.

I. FACTS AND PROCEDURAL HISTORY

Miller-Davis Company was an “at risk” contractor 1 for the Sherman Lake YMCA’s natatorium project. 2 Miller-Davis hired defendant Ahrens Construction, Inc., as a subcontractor to install similar roof systems on three rooms, including the natatorium. The contract incorporated by reference the applicable project plans and specifications, the American Institute of Architects General Conditions (AIA A201), the project manual, and a written guarantee of Ahrens’s work. 3 AIA A201 required the subcontractor to “assume toward the Contractor all the obligations and responsibilities which the Contractor, by these Documents, assume[d] toward the Owner and Architect.” 4 It further obligated Ahrens to “bear costs of correcting such rejected Work, including additional testing and inspections and compensation for the Architect’s services and expenses made necessary *167 thereby,” 5 and to correct at its expense any work “found to be not in accordance with the Contract Documents” within one year of Substantial Completion. 6 Ahrens agreed to install all products in accordance with the manufacturer’s instructions and the requirements of the plans and specifications. Ahrens further agreed to indemnify Miller-Davis from and against any liabilities, claims, damages, losses, actions, and expenses arising out of the subcontract.

- Ahrens substantially completed the work on June 11, 1999, at which point its Written Guarantee commenced. The Guarantee provides in relevant part:

[Ahrens] hereby agree [s] that all work furnished to the project is guaranteed against deficiencies and defects in materials and/or workmanship for a period of one (1) year, as described in the Contract Documents.
We agree to satisfy such obligations, which appear within the guarantee period without cost to the Owner.
Nothing contained in this agreement shall be construed to establish a period of limitation with respect to any other obligation we may have under the Contract Documents or to alter any longer period of time as may be prescribed by law of the Contract Documents.

A certificate of substantial completion issued on June 25, 1999. During the winter season of 1999-2000, Sherman Lake YMCA experienced excessive condensation in the natatorium, which it termed the “natatorium moisture problem” (NMP). As a result of the accumulated conden *168 sation, it sometimes appeared to be raining within the natatorium. Miller-Davis notified Ahrens of the NMP on January 28, 2000, and Ahrens returned to the project to undertake remedial work not contemplated in the original design. Ahrens received its final payment on February 17, 2000, but the NMP persisted.

In February 2003, the project architects opened the roof and discovered significant deficiencies with Ahrens’s installation of the roof system, namely inch-wide gaps between the Styrofoam blocks and sub-T supports, and many gaps and tears in the vapor barrier. The architects determined that the installation was not in substantial compliance with the contract, and directed reinstallation of the roof system using salvageable materials to the extent possible. The corrective work contained three elements not contained in the original design: Procor, a waterproofing agent; expanding foam insulation; and butyl caulk sealant.

By letter dated April 2, 2003, Miller-Davis notified Ahrens that the roof system was not installed in accordance with the manufacturer’s requirements and the subcontract guidelines. Miller-Davis’s May 5, 2003 letter to Merchants Bonding Company, Ahrens’s surety, explicitly declared Ahrens in default and requested a conference within fifteen days. The parties met on June 27,2003, and Ahrens agreed to review the corrective work plans and provide a plan for performance within a week. Neither Ahrens nor its bonding company provided such a plan. On July 15, 2003, Miller-Davis gave Ahrens notice of default, terminated Ahrens’s right to perform the contract, and demanded the bonding company perform under the bond. In that letter, plaintiff noted that Sherman Lake YMCA was “considering declaring a Contractor Default....” The bonding company notified Miller-Davis that Ahrens had waived the surety’s right to perform under the bond.

*169 Miller-Davis and Sherman Lake YMCA entered into an Agreement for Corrective Work on August 27, 2003. Pursuant to the agreement and at the direction of the architects, Miller-Davis installed Procor, expanding foam insulation, and butyl caulk. On December 8, 2003, an independent contractor certified that Miller-Davis had completed the corrective work. Sherman Lake YMCA has not since experienced the NMR

Miller-Davis filed suit in the Kalamazoo Circuit Court against Ahrens and its bonding company in May 2005, alleging breach of contract and seeking indemnification and bond collection. 7 Following a bench trial, the circuit court found that Ahrens’s work was deficient and that it caused the NMR The court rejected Ahrens’s assertion that it had ceased involvement with the project before July 2003, noting that the parties had engaged in a series of meetings regarding corrective work from March to July 2003.

Free access — add to your briefcase to read the full text and ask questions with AI

Miller-Davis Co. v. Ahrens Construction, Inc., 848 N.W.2d 95, 495 Mich. 161 (Mich. 2014).

848 N.W.2d 95 (Miller-Davis Co. v. Ahrens Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tompor v. Comerica Bank
E.D. Michigan, 2025
20221229_C359523_31_359523.Opn.Pdf
Michigan Court of Appeals, 2022
Tsp Services Inc v. National-Standard LLC
Michigan Court of Appeals, 2022
Fraternal Enterprises Inc v. Marie a Lemieux
Michigan Court of Appeals, 2019
Strobl & Sharp Pc v. Michael P Rivait
Michigan Court of Appeals, 2019
Matthew T Thiel v. David L Goyings
Michigan Supreme Court, 2019
Global Products Inc v. Mayser Polymer USA Inc
Michigan Court of Appeals, 2019
in Re Rc Minor
Michigan Court of Appeals, 2019
Rudolph T Stonisch III v. Forthright IV LLC
Michigan Court of Appeals, 2018
Frank Wojcik v. Merchants Metals LLC
Michigan Court of Appeals, 2018
Bony Rochlani v. Sanford Aaron
Michigan Court of Appeals, 2018
Edward Castle Jr v. Marcia Shoham
Michigan Court of Appeals, 2018
Bruce Klaasen v. Dennis Jonker
Michigan Court of Appeals, 2018