Tsp Services Inc v. National-Standard LLC

CourtMichigan Court of Appeals
DecidedMay 12, 2022
Docket356729
StatusUnpublished

This text of Tsp Services Inc v. National-Standard LLC (Tsp Services Inc v. National-Standard LLC) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tsp Services Inc v. National-Standard LLC, (Mich. Ct. App. 2022).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

TSP SERVICES, INC., doing business as TSP UNPUBLISHED ENVIRONMENTAL, May 12, 2022

Plaintiff/Counterdefendant-Appellant,

v No. 356729 Berrien Circuit Court NATIONAL-STANDARD, LLC, DW-NATIONAL LC No. 16-000018-CB STANDARD-NILES, LLC, doing business as NATIONAL-STANDARD LLC,

Defendants/Cross-Defendants- Appellees, and

NATIONAL-STANDARD COMPANY,

Defendant/Cross-Defendant,

and

ENVIRONMENTAL DEMOLITION GROUP, LLC,

Defendant/Counterplaintiff/Cross- Plaintiff.

Before: GLEICHER, C.J., and RONAYNE KRAUSE and BOONSTRA, JJ.

PER CURIAM.

Plaintiff, TSP Services, Inc. (TSP) appeals by right the trial court’s order granting summary disposition in favor of defendant DW-National Standard-Niles, LLC (DW-National Standard), and denying TSP’s request to clarify the judgment entered after arbitration. We affirm.

-1- I. PERTINENT FACTS AND PROCEDURAL HISTORY

A. THE ENTITIES AT ISSUE

TSP is a Michigan corporation that provides demolition, reclamation, and remediation services for owners of real property, specializing in the remediation of environmental impacts, including asbestos remediation. DW-National Standard is a Delaware limited liability company, as is defendant National-Standard, LLC (National-Standard). Both defendants are owned by the same parent, The HEICO Companies (HEICO). Jeremy Steele testified at the arbitration hearing that he was a vice president and general counsel with the HEICO group of companies. Steele stated that DW-National Standard was part of the “Wire Group division” of HEICO. DW-National Standard began conducting business in Michigan in March 2010. It owned and operated a plant in Niles, Michigan—known as City Center Complex (the Niles Complex). Steele testified that National-Standard was a legacy entity that did not operate any businesses. National-Standard existed only to hold certain real property assets, including the real property at issue in this case. Steele testified specifically that the Niles Complex was owned by National-Standard, not by DW- National Standard.

On August 6, 2013, National-Standard applied to the Michigan Department of Licensing and Regulatory Affairs (LARA) for a certificate of withdrawal, stating that it no longer conducted business in Michigan. On the same day, DW-National Standard filed a certificate of assumed name stating that it would conduct business in Michigan under the name National-Standard, LLC.

B. THE DEMOLITION PROJECT

Ronald Swan of TSP testified that the Niles Complex was roughly 10 acres in size and had 500,000 square feet of buildings. The buildings on the property ranged from an office building to heavy-duty industrial buildings. The heavy-duty industrial buildings had substantial amounts of steel in their construction.

Steele testified that after the last tenant vacated the Niles Complex, National-Standard decided to demolish the complex and provide a recreational easement to the city for a park. He indicated that National-Standard was interested in doing so because the buildings had fallen into disrepair and the demolition would reduce the company’s exposure to liability.

Thomas Moran testified that he was the former director of operations for National-Standard in Michigan. In that position, he was responsible for the management of the properties owned by National-Standard in Michigan. He began managing the Niles Complex in 2005. Moran testified that in 2012, a company named Regal Recycling (Regal) approached National-Standard suggesting that it could demolish the Niles Complex at no cost to National-Standard; Moran assumed that Regal intended to profit from selling the steel reclaimed from the demolition project. Although the initial proposal was that the remediation and demolition would be done at no cost, the additional cost of services required by the city of Niles resulted in a quote from Regal of $478,000. Moran testified that when his contact person at Regal moved to TSP, National-Standard began negotiating remediation with TSP instead of Regal.

In August 2013, TSP submitted a proposal for asbestos remediation and demolition of all structures at the Niles Complex. The proposal also included grading, backfilling, and seeding the

-2- land. TSP’s quoted amount was $414,950. The first page of the proposal reflected that it was directed to “National Standard, L.L.C.” The ninth (and last) page of the proposal included a section entitled “Acceptance.” The Acceptance of the proposal was signed on August 30, 2013 (the remediation agreement); the signature lines of the Acceptance (which were part of TSP’s proposal) identified the contracting parties as TSP and “National Standard Co.” Moran testified that the parties did not discuss the issue of steel reclamation during the negotiations relating to the proposal, but he understood from previous negotiations that the steel to be reclaimed would have significant value. In January 2014, DW-National Standard began paying TSP the installment payments due under the remediation agreement.

Steele testified that in 2014, disputes arose about the project after several months of delays. Specifically, TSP complained that steel prices had declined during the period of the delays. TSP proposed an adjustment to the contract price to cover additional unanticipated remediation costs and to reflect the drop in the price of steel. The requested adjustment was declined. Thereafter, TSP stated that it would only complete the project under protest and with the expectation that it would get the adjustment. That was not acceptable to Steele, and he suspended the project in March 2015.

C. THE CONTRACT DISPUTE

In January 2016, TSP sued “National-Standard, LLC, a Delaware limited liability company,” “DW-National Standard-Niles, LLC, d/b/a National-Standard, LLC, a Delaware limited liability company,” “National-Standard Company, Inc.”1 (collectively, the National- Standard entities), and a subcontractor with which TSP had contracted to perform certain work.2 TSP separately and specifically identified each of these National-Standard entities, while contending that they were all related entities or the same entity. TSP asserted a claim for breach of contract on the unpaid balance on the original proposal, which was $141,083, and asserted that it was entitled to the value of the steel that it would have reclaimed, as consequential damages. It also asserted claims relating to its construction lien, and claims of unjust enrichment and promissory estoppel.

In February 2016, TSP entered into an arbitration agreement with “National-Standard, LLC, a Michigan limited liability company.”3 In February 2017, the arbitrator issued an award. The arbitrator captioned the award to reflect that the litigation was between TSP and “National- Standard, LLC, a Delaware limited liability company.” The arbitrator awarded TSP $141,083 for the unpaid balance on the contract, $391,809 for the lost value of the steel that would have been

1 The trial court dismissed National-Standard Company from the complaint after the parties stipulated that it no longer existed. 2 In May 2016, the subcontractor countersued TSP and cross-sued the National-Standard entities. The trial court later dismissed the subcontractor from the litigation after it settled with TSP and assigned all its rights in its lawsuit and its lien to TSP. It is not a party to this appeal. 3 This description misidentified the relevant contracting entity, inasmuch as there is no Michigan limited liability company that is named or doing business as “National-Standard, LLC.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Driver v. Naini
802 N.W.2d 311 (Michigan Supreme Court, 2011)
Walters v. Nadell
751 N.W.2d 431 (Michigan Supreme Court, 2008)
Miller v. Chapman Contracting
730 N.W.2d 462 (Michigan Supreme Court, 2007)
Long Manufacturing Co. v. Wright-Way Farm Service, Inc.
214 N.W.2d 816 (Michigan Supreme Court, 1974)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Hertz Corp. v. Volvo Truck Corp.
533 N.W.2d 15 (Michigan Court of Appeals, 1995)
Barnard Manufacturing Co. v. Gates Performance Engineering, Inc.
775 N.W.2d 618 (Michigan Court of Appeals, 2009)
Konal v. Forlini
596 N.W.2d 630 (Michigan Court of Appeals, 1999)
Gordon Sel-Way, Inc. v. Spence Bros.
475 N.W.2d 704 (Michigan Supreme Court, 1991)
Mitcham v. City of Detroit
94 N.W.2d 388 (Michigan Supreme Court, 1959)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)
Conlin v. Upton
881 N.W.2d 511 (Michigan Court of Appeals, 2015)
Mossman v. Millenbach Motor Sales
280 N.W. 50 (Michigan Supreme Court, 1938)
Saums v. Parfet
258 N.W. 235 (Michigan Supreme Court, 1935)
Timmerman v. Bultman
220 N.W. 754 (Michigan Supreme Court, 1928)
Landyskowski v. Lark
66 N.W. 371 (Michigan Supreme Court, 1896)
Ewald v. Ewald
810 N.W.2d 396 (Michigan Court of Appeals, 2011)
Brecht v. Hendry
825 N.W.2d 110 (Michigan Court of Appeals, 2012)
Maple BPA, Inc. v. Bloomfield Charter Township
838 N.W.2d 915 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Tsp Services Inc v. National-Standard LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tsp-services-inc-v-national-standard-llc-michctapp-2022.