Robert E. Lee & Co. v. Commission of Public Works

149 S.E.2d 59, 248 S.C. 92, 1966 S.C. LEXIS 160
CourtSupreme Court of South Carolina
DecidedJune 16, 1966
Docket18524
StatusPublished
Cited by15 cases

This text of 149 S.E.2d 59 (Robert E. Lee & Co. v. Commission of Public Works) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert E. Lee & Co. v. Commission of Public Works, 149 S.E.2d 59, 248 S.C. 92, 1966 S.C. LEXIS 160 (S.C. 1966).

Opinion

Moss, Chief Justice.

It appears from the record that on April 28, 1959, the appellants entered into a contract for the installation of a water pipeline from the respondent's No,rth Saluda Dam to Travelers Rest, South Carolina. The completion date fixed in said contract was June 21, 1960, and it was provided that as against the amount due under said contract the respondent would be entitled to a reduction and offset for any delay in the completion of said contract at the rate of $100.00 per day.

There was included in the complaint here two causes of action. Under the first cause of action the appellants sought to recover the sum of $65,693.29, being the balance due under the contract for the installation of the water pipeline. The second cause of action was one wherein the appellants sought damages occasioned by the breach of an implied warranty in the failure of the respondent to reveal on its plans submitted to the bidding contractors the true subsoil *95 condition and water level as shown by auger borings made by the respondent thro,ugh their duly constituted engineers.

The respondent, by its answer to the first cause of action, admitted the making of the contract hereinbefore referred to and that the appellants have partially performed such on their part, but denies the full performance thereof or that any sum was due the appellants at the time of the commencement of this action, for the reason that they have failed to furnish the respondent proof in documentary form prescribed by the contract, showing that all claims, liens, or other obligations incurred by them and all of their subcontractors have been properly paid and settled, or that the respondent has ever accepted or approved the work according to the provisions of said contract. The respondent further alleged that the appellants failed to complete the contract in accordance with the time limit therein prescribed and it was entitled to a reduction and offset against any amount due under the said contract by way of liquidated damages in the sum of $16,217.50, representing 162.175 days delay.

It was provided in the contract between the parties hereto that on completion of the work, “but prior to the acceptance thereof by the owner”, the contractor was to furnish proof in documentary form that all claims, liens, or other obligations incurred by him and all of his subcontractors in connection with the performance of the work have been properly paid and settled. It was further agreed that after official approval and acceptance of the work by the respondent, the engineers would be authorized to prepare a final estimate of the work done under the contract and the value thereof. Such final estimate was to be submitted to the respondent within ten days after its preparation had been authorized as aforesaid; and the respondent shall, within thirty days after said final estimate is made and certified, pay the entire sum so found to be due thereunder. It was further agreed that all estimates when approved by the respondent should be conclusive evidence of the work done and materials furnished.

*96 A final estimate of the work done, under the aforesaid contract, was made up by the engineers for the respondent on January 19, 1961, and such was mailed by the respondent to the appellants on January 23, 1961. This final estimate showed the completion of the contract and that the amount due the contractor was $65,067.01. On this final estimate liquidated damages for delay in the performance of the contract by the appellants were calculated to be $16,217.50, leaving an amount due “after all the'terms of the contract had been complied with of $48,849.51.”

The general manager of the respondent in his testimony said that according to the final estimate made up by the engineers for the respondent, that the appellants were due the sum of $65,067.01 “before the liquidated damages were offset”, the amount of such being $16,217.50, leaving the net amount due the appellants of $48,849.51.

It is implicit in this record that there was never any dispute as to the overall amount due by the respondent to the appellants under the terms of the aforesaid contract. There was a dispute concerning the proper number of days delay and occasions therefor for which the respondent was entitled to an offset as liquidated damages under the contract.

This action was tried before The Honorable Louis Rosen, Presiding Judge, and a jury, at the 1964 February term of the Court of Common Pleas for Greenville County and resulted in a verdict for the appellants on the first cause of action in the sum of $54,363.00. A verdict was rendered fo.r the respondent on the second cause of action and a separate appeal is now pending in this Court as to such second cause of action. There was no appeal by the parties to this action from the verdict of the jury in the first cause of action. We are here concerned only with an appeal from the rulings of the trial judge with reference to the first cause of action.

The question of whether the appellants were entitled to interest upon the amount of the verdict upon the first cause of action was, by agreement of counsel, left for determination by the trial judge. It is the position of the appellants that they were entitled to interest upon the amount due them un *97 der the first cause of action from December 10, 1960, which was the date the construction work was declared completed by the engineers for the respondent, to the date of the verdict of the jury on February 7, 1964. Interest was denied by the trial judge and this appeal is from his order of denial.

The trial judge held as a matter of law that the appellants were entitled to a verdict against the respondent on the first cause of action in said complaint for a sum of not less than $48,849.51, and not more than $65,693.29. In his charge he said: “The reason I say you must find for the plaintiffs, the defendants admit they owe him $48,849.51 and consents, so to speak, to a verdict in that amount but for nothing more.” He also held that the evidence is undisputed that the appellants completed the construction provided for in the contract on December 10, 1960, and that the respondent claims the right to deduct from the amount due the appellants the sum of $16,217.50 as liquidated damages, computing the same in the manner described in the contract at the rate of $100.00 per day for each day of delay in the completion of the contract. He charged the jury that the respondent would be entitled to make this deduction unless the delay of the completion of the contract was caused by the respondent, by the breach of its warranty, or by its failure to furnish pipe for the job, or by its failure to make necessary rights of way .available. It thus appears that the trial judge submitted to the jury for its determination the total number of days of delay in the completion of the contract chargeable to the appellants, and directed the jury to. deduct from the amount due the appellants by the respondent the sum of $100.00' per day for each day of delay. He charged the jury that such constituted liquidated damages for failure to complete the construction work according to the time schedule provided for in the contract. It is implicit in the verdict of the jury that it did not find that the appellants had delayed completion of the contract for the number of days asserted by the respondent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fast Formliners Company v. Construction Resource Group, Inc.
Court of Appeals of South Carolina, 2025
Julia Sibley-Jones v. Decide4Action, Inc. (2)
Court of Appeals of South Carolina, 2024
Dixie Bell, Inc. v. Redd
656 S.E.2d 765 (Court of Appeals of South Carolina, 2007)
Wilder Corp. v. Wilke
479 S.E.2d 510 (Court of Appeals of South Carolina, 1996)
Tiger, Inc. Ex Rel. Green Apple Partnership v. Fisher Agro, Inc.
391 S.E.2d 538 (Supreme Court of South Carolina, 1989)
Wayne Smith Construction Co. v. Wolman, Duberstein, & Thompson
363 S.E.2d 115 (Court of Appeals of South Carolina, 1987)
Southern Welding Works, Inc. v. K & S Construction Co.
332 S.E.2d 102 (Court of Appeals of South Carolina, 1985)
Kerr v. State Farm Fire & Casualty Co.
731 F.2d 219 (Fourth Circuit, 1984)
Llewelyn Ex Rel. Estate of Dillard v. Dobson Bros.
262 S.E.2d 726 (Supreme Court of South Carolina, 1980)
E & S INVESTMENT CORP. v. Richland Bowl, Inc.
216 S.E.2d 522 (Supreme Court of South Carolina, 1975)
Lewis v. Carnaggio
183 S.E.2d 899 (Supreme Court of South Carolina, 1971)
Burger v. Wood
446 S.W.2d 436 (Missouri Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
149 S.E.2d 59, 248 S.C. 92, 1966 S.C. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-e-lee-co-v-commission-of-public-works-sc-1966.