Kensington Corp. v. Department of State Highways

253 N.W.2d 781, 74 Mich. App. 417, 1977 Mich. App. LEXIS 740
CourtMichigan Court of Appeals
DecidedMarch 29, 1977
DocketDocket 26382
StatusPublished
Cited by10 cases

This text of 253 N.W.2d 781 (Kensington Corp. v. Department of State Highways) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kensington Corp. v. Department of State Highways, 253 N.W.2d 781, 74 Mich. App. 417, 1977 Mich. App. LEXIS 740 (Mich. Ct. App. 1977).

Opinion

*419 D. E. Holbrook, P. J.

On July 8, 1974, the Court of Claims found no cause of action on three counts of a four-count complaint involving the alleged misrepresentation of the State Highway Department regarding the type of soil present at a bridge reconstruction site. 1 Judgment was entered on December 12, 1974, and rehearing was denied. Plaintiff Kensington appeals as of right.

On April 7, 1971, plaintiff Kensington, as low bidder, was awarded a prime contract for reconstruction of a bridge over 1-94 in Dearborn, Michigan. The contract specified that Kensington, acting individually and through its subcontractors, was required to build a reinforced concrete wing wall at one end of the bridge. The defendant prepared and submitted certain plans and specifications which indicated that the soil in the wing wall area was soft blue clay, which has a transverse sheering resistance of 100 to 300 pounds per square foot. Kensington sublet the bridge construction work to Korneffel Company, a state-approved subcontractor. Construction proceeded until the cofferdam of the wing wall collapsed. Upon independent analysis of the soil, it became apparent that the soil was in fact very soft blue clay, which has a transverse sheering resistance of less than 100 pounds per square foot, and not soft blue clay. The cofferdam was successfully rebuilt using very soft blue clay methods. Kensington and its subcontractors 2 then attempted to recover approximately $55,000, the added expense incurred by the requirement of the use of very soft blue clay building methods, from the highway department. On July 17, 1972, the Central Office Adjustment Board denied the vari *420 ous claims in the final administrative step of the claim review process. The plaintiffs then filed the instant action in the Court of Claims.

The trial court found that Kensington could not maintain this action to recover damages caused by this incident. The court held that there was never a joint venture between Kensington and the subcontractors and that therefore as a matter of law, the prime contractor could not maintain this action on behalf of the subcontractors.

Both parties apparently agreed that the trial court misdirected its inquiry towards the existence of a joint venture. On appeal both parties engage in a thorough review of similar claims by contractors against the Federal government. We also agree that a review of Federal court experience, where a substantial amount of litigation in this area has occurred, is helpful. Both parties cite the same case as support for their respective positions, JL Simmons Co, Inc v United States, 304 F2d 886 (Ct Cl, 1962). We also agree that this, and subsequent cases following this case, control and that the rule is that the contractor may maintain a suit on behalf of the subcontractors when the prime contractor has reimbursed its subcontractors for the damages or remains liable for such reimbursement in the future (known as the Severin Doctrine, Severin v United States, 99 Ct Cl 435 [1943], cert den 322 US 733; 64 S Ct 1045; 88 L Ed 1567 [1944]), J L Simmons Co, supra, Hegeman-Harris & Co, Inc v United States, 440 F2d 1009 (Ct Cl, 1971), Keydata Corp v United States, 504 F2d 1115 (Ct Cl, 1974). 3 Apparently Kensington has not reim *421 bursed the subcontractors and, therefore, this dispute really concerns whether Kensington remains liable for such reimbursement in the future. The key to this dispute, therefore, lies in interpretation of the subcontract itself, which the trial court avoided herein by improperly ruling that the contractor could not maintain this action because Kensington and the subcontractors herein were not engaged in a joint venture. Unfortunately, this case does not fit neatly within the Simmons rule, and the subcontract language does not clearly require a particular result. The liability of the prime contractor to the subcontractor depends on proper interpretation of this subcontract. See, Blount Brothers Construction Co v United States, 346 F2d 962 (Ct Cl, 1965).

This subcontract was not interpreted by the trial court although there was testimony presented concerning the meaning of the subcontract. The subcontract herein provides in pertinent part as follows:

"3. Prime contractor to remit payment for completed work when received and evidenced by estimates prepared by the Michigan State Highway Department.
* * *
"9. The Party of the Second Part agrees to accept as complete and final, amounts and quantities as determined by the Michigan State Highway Department and the Party of the Second Part shall have no further claim against the Party of the First Part whatsoever. Payment will be made to the Second Party as the Michigan State Highway Department pays the Party of the First Part.”

These sections when read with the rest of the subcontract, do not absolve plaintiff Kensington of all responsibility or liability to the subcontractors, *422 but rather serve to create an implied obligation on the part of the prime contractor to proceed against the government in administrative and judicial proceedings should the state fail to pay without good cause. Keydata Corp, supra, at 1121. Federal courts have clearly announced that: "To come under the 'Severin’ doctrine the defendant must show, through some contractual term or a release, that the plaintiif-prime is not liable to the subcontractor”. Blount Brothers Construction Co, supra, at 965. In the absence of clear, express exculpatory language, suit by the prime contractor in behalf of a subcontractor against the government will generally be permitted. Southern Construction Co, Inc v United States, 364 F2d 439, 447 (Ct Cl, 1966). We rule that the burden is properly on the defendant to show that the prime contractor is absolved from liability, particularly when, as here, there is no question but that recovery will properly go to the injured subcontractor. 4 Defendant has not carried its burden of proof.

Furthermore, we think this is the just result. Contrary to the court below, as explained further by us in the next issue, we feel the prime contractor and subcontractor herein properly relied on defendant’s misrepresentations as to the soil quality, which caused the collapse of the cofferdam. To deny recovery on the basis that the subcontractor did not directly deal with the state when the state voluntarily and knowingly provided the incorrect and material information to the subcontractor would be unfair. This is particularly so when the subcontractor has not given up his rights against *423 the prime contractor, nor signed a release, and when the contract supports a finding of an obligation on the part of the prime contractor to protect the subcontractor from wrongful action by the state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Alamo Community College District v. Browning Construction Co.
131 S.W.3d 146 (Court of Appeals of Texas, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Lumley v. U of M Bd of Regents
544 N.W.2d 692 (Michigan Court of Appeals, 1996)
Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
Frank Coluccio Construction Co. v. City of Springfield
779 S.W.2d 550 (Supreme Court of Missouri, 1989)
Midwest Bridge Co. v. Department of Transportation
350 N.W.2d 913 (Michigan Court of Appeals, 1984)
Solomon v. Department of State Highways & Transportation
345 N.W.2d 717 (Michigan Court of Appeals, 1984)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
253 N.W.2d 781, 74 Mich. App. 417, 1977 Mich. App. LEXIS 740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kensington-corp-v-department-of-state-highways-michctapp-1977.