Greens at Hilton Run I Ltd. Partnership v. Rollin Building Supply Co.

589 A.2d 536, 87 Md. App. 220, 1991 Md. App. LEXIS 106
CourtCourt of Special Appeals of Maryland
DecidedMay 7, 1991
DocketNo. 948
StatusPublished

This text of 589 A.2d 536 (Greens at Hilton Run I Ltd. Partnership v. Rollin Building Supply Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greens at Hilton Run I Ltd. Partnership v. Rollin Building Supply Co., 589 A.2d 536, 87 Md. App. 220, 1991 Md. App. LEXIS 106 (Md. Ct. App. 1991).

Opinion

MOYLAN, Judge.

The Greens at Hilton Run I Limited Partnership (The Greens) has appealed from a mechanic’s lien established in favor of Rollin’ Building Supply Company, Inc. (Rollin’) in the amount of $17,776 by the Circuit Court for St. Mary’s County. The Greens raises the following issues:

1. Whether the lien releases executed by Rollin’ and the subcontractor released the builder or owner from the mechanic’s lien;
2. Whether Rollin’ could apply all payments by the contractor on a first in-first out basis to the subcontractor’s only account with Rollin’ for the three projects all parties were involved in; and
3. Whether Rollin’ was estopped from raising non-payment and claiming a lien when it had full control of funds sufficient to satisfy the subcontractor’s account.

Rollin’ cross appeals, contending that the court erred in finding that Rollin’ was not entitled to recover the full amount of its lien.

[223]*223 The Facts

The Greens at Hilton Run in St. Mary’s County is one of several separate limited partnerships established to build multifamily housing projects.1 Case Edwards Development, Inc. is a general partner in each of the limited partnerships. The contractor for the projects, Case Edwards Construction Company, Inc. (Case Edwards), subcontracted with Duane Lundberg T/A Bay Central Installation (Lundberg) to furnish and install the vinyl siding. Lundberg, in turn, solicited Rollin’ to provide the siding and related materials at $60 per square2 for the projects. Lundberg had only one account with Rollin’ and all purchases, regardless of the project, were charged to that account. Rollin’ credited all payments, made jointly to Lundberg and Rollin’ by Case Edwards, to the oldest outstanding invoices first.

At issue are the 773 squares of siding and materials delivered by Rollin’ to the Hilton Run project, also known as the Lexington Park project, between April 2 and June 15, 1988.3 On March 31,1988, Lundberg’s account of payments due by it to Rollin’ stood at $66,368.26 for deliveries to the other two projects. When Lundberg’s account totalled $95,-137.78 at the end of April, Rollin’ requested a meeting with Case Edwards to discuss Lundberg’s arrearage. No payments toward the Lexington Park project had been made prior to the meeting.

The May 2 meeting attended by Lundberg, Case Edwards and Rollin’4 revealed that Lundberg had misled the other [224]*224parties as to his labor costs. He had been receiving checks from Case Edwards for labor (which he allegedly overstated), as well as the joint checks for materials (which he allegedly understated). Rollin’ was not aware Lundberg had received compensation for his labor costs in a separate check. In order to insure that Rollin’ would receive the full balance due it, and to ensure that Lundberg would continue to provide labor to finish the projects as Case Edwards wished, Rollin’ proposed 1) that the joint checks for labor and materials issued by Case Edwards be given directly to Rollin’ rather than Lundberg, and 2) that Rollin’ would credit itself $60 per square of siding installed, plus $5 per square on the arrearage, and pay Lundberg his labor costs.

Although the parties agreed to implement the Rollin’ proposal, each had a different interpretation as to its application. According to Rollin’, it was to pay the third-party labor costs first as presented by Lundberg, and then to credit the rest to Lundberg’s account. According to The Greens, Rollin’ was to pay itself first, collect the additional $5/square, and then pay the third-party labor costs.

Six of the joint checks distributed to Rollin’ related to the Lexington Park project before Lundberg was terminated:

Date Check No. Amount
5/03/88 21198 8,164.80
5/12/88 21270 16,329.60
5/19/88 21423 10,108.80
5/27/88 21597 9,552.60
6/10/88 21849 6,403.60
6/15/88 22115 14,094.00
64,653.40

Another check, number 22722 dated 7/19/88, in the amount of $7,840.80 was issued to Rollin’ on July 19, 1988, bringing the total disbursed to Rollin’ to $72,494.20.

According to Mark Winkler, an officer of Rollin’, the joint checks were distributed by Richard Norton (Norton), then president of the corporation. Norton “would try to ascer[225]*225tain how many squares [Lundberg] had done the week before, and how many squares the draws were based on, and pay him.” Winkler further testified:

“Lundberg would come in requesting a certain amount of money. Rick would determine, or try to make a determination how many squares this particular check was based on his applying. And try to base what he gave [Lundberg] on the reasonableness of that figure. And try to get for us no less than sixty dollars a square.”

Norton’s uncontroverted testimony corroborated Winkler’s summary. Norton also testified that Rollin’ paid Lundberg’s labor before it paid itself from the first two checks. Handwritten notations on the check stubs of the next four checks indicate that the Rollin’ paid itself for a certain amount of squares and then gave the balance to Lundberg. The stub of the last check was not in evidence.

Five undated, unwitnessed form lien releases were signed by Norton and Lundberg. Norton’s name appeared on the line for “stairwork.” No signature appeared on the owner’s signature line. All the releases had handwritten notes in the margins indicating “Bay Central,” and two mentioned “Rollin’ Supply.” Three had check numbers written on them, and two releases indicated (according to Norton’s testimony) what had been released:

Release5 Date Check No. Released
1 5/19/88 21473
2 6/10/88
3 6/10/88 21849 Bldg # 7 33 sq Bldg # 10 30 sq
5/27/88 21597
5/27/88 Bldg # 2 16 sq Clubhs 25 sq

Norton testified that the purpose of his signature was merely to signify that Rollin’ had received a check. He also [226]*226testified that six buildings and a clubhouse had been completed by the time Lundberg was terminated.6

On December 12, 1988, Rollin’ petitioned to establish and enforce a mechanic’s lien in the amount of $39,516.74 against The Greens. The Greens did not contend that Rollin’ failed to comply fully with the statutory requirements under Md.Real Prop.Code Ann. § 9-104 et seq. (1974, 1988 Repl. Vol.), and the trial court proceeded as if the lien was perfected.

The parties stipulated that Rollin’ received $72,494.20 in joint checks subsequent to the May 2 arrangement. The trial judge determined Rollin’ paid Lundberg $36,694.80 from the joint checks for labor, although the amount is actually $1,000 higher.7 Of the amount allocated to labor, $28,604 was directly related to the Lexington Park project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark-King Constr. v. SALTER AND TAYLOR, TRUSTEES
307 A.2d 485 (Court of Appeals of Maryland, 1973)
T. Dan Kolker, Inc. v. Shure
121 A.2d 223 (Court of Appeals of Maryland, 1956)
Dickerson Lumber Co. v. Herson
187 A.2d 689 (Court of Appeals of Maryland, 1963)
Landover Associates Ltd. Partnership v. Fabricated Steel Products, Inc.
371 A.2d 1140 (Court of Special Appeals of Maryland, 1977)
N. S. Stavrou, Inc. v. Beacon Supply Co.
240 A.2d 278 (Court of Appeals of Maryland, 1968)
Bounds v. Nuttle
30 A.2d 263 (Court of Appeals of Maryland, 1943)
Maryland Brick Co. v. Dunkerly
36 A. 761 (Court of Appeals of Maryland, 1897)
Hill v. Parkway Industrial Center
435 A.2d 472 (Court of Special Appeals of Maryland, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
589 A.2d 536, 87 Md. App. 220, 1991 Md. App. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greens-at-hilton-run-i-ltd-partnership-v-rollin-building-supply-co-mdctspecapp-1991.