N. S. Stavrou, Inc. v. Beacon Supply Co.

240 A.2d 278, 249 Md. 451, 1968 Md. LEXIS 623
CourtCourt of Appeals of Maryland
DecidedApril 4, 1968
Docket[No. 166, September Term, 1967.]
StatusPublished
Cited by6 cases

This text of 240 A.2d 278 (N. S. Stavrou, Inc. v. Beacon Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N. S. Stavrou, Inc. v. Beacon Supply Co., 240 A.2d 278, 249 Md. 451, 1968 Md. LEXIS 623 (Md. 1968).

Opinion

Finan, J.,

delivered the opinion of the Court.

A general contractor (N. S. Stavrou, Inc.) and its surety (Reliance Insurance Company) have appealed from judgments 'in three consolidated cases aggregating $14,059.25 plus inter•est, entered in favor of a supplier of materials, Beacon Electric Supply Co., Inc. In the court below there was another party •defendant, a subcontractor, Densco, Inc., who did not appeal a judgment entered against it on a cross claim by the contractor, whose actions directly affected this litigation.

Early in 1964, Stavrou was awarded prime contracts by the Board of Education of Prince George’s County to construct three schools: Tanglewood, Greendale and Taney. Stavrou subcontracted the electrical work to Densco, which procured its materials from Beacon. Beacon was unwilling to directly extend ■credit to Densco for job materials because it believed Densco to be over-extended, and therefore it requested Stavrou to guarantee payment in advance. As a result of a meeting between •officers of Beacon and Stavrou, a written agreement was executed. This agreement, the basis for the litigation, is an undated instrument, executed by Stavrou and signed by Densco, but directed toward Beacon:

*453 “We agree to make payment to the joint order of Densco Inc. and Beacon Electric Supply Corp. monthly for all material supplied by you to Densco Inc. for the Tanglewood Elementary School — $13,000, Greendale Elementary School — $3,000 & Roger B. Taney Jr. High School — $4,000, jobs, total amount not to exceed $20,000.00.”

After receipt of this instrument Beacon commenced deliveries of material and between May 13 and August 14, 1964, Stavrou issued 12 checks totalling $19,851, payable jointly to Densco and Beacon. The evidence shows that Stavrou stamped each joint check with the name and address of one of the three schools which were under construction. As a result, according to the job designation on the checks, payments were made as follows:

Greendale: $ 2,990
Tanglewood: 13,215
Taney: 3,646
$19,851

The dispute focuses upon the manner in which Beacon applied the payments which it received from Stavrou. Stavrou argues that the job designation marked on each check was merely for internal bookkeeping purposes, and that Beacon should have applied the checks to the payment for materials delivered to any or all of the three jobs at the time checks were received, with any surplus to be held to apply to the future cost of materials. In support of this contention, Stavrou points to the language in the undated agreement that payment would be “for all material.” Stavrou further contends that Beacon must bear the loss for its failure to apply the proceeds of the checks in payment for materials which it supplied since it had it within its power and control to do so.

On the other hand Beacon alleges that it could only legally withhold from the proceeds of the checks that amount due and owing for materials delivered by it to a particular job as of the date covered by the requisition for which the check was issued, and that the checks included payment, not only for materials which it had supplied Densco, but also reimbursement *454 for Densco’s labor expenses. Beacon argues that it could not rightfully withhold any part of the proceeds of the checks which represented Densco’s labor cost.

The evidence showed that, as is the custom of the industry, Beacon billed Densco each month for materials supplied from the 25th of the previous month to the 25th of the current month, for each of the three separate school construction accounts. Densco would then submit requisitions to Stavrou, indicating costs for both labor and materials. Beacon’s office manager testified, over objection, that the checks issued by Stavrou tied in to these requisitions of Densco’s, which included both material and labor charges. As a result, when Beacon received a check for $846 on June 15, 1964, for example, it would note that the check was marked “Roger Taney Jr. High School,” would apply the check to the amount due Beacon for materials supplied on the Taney contract as of the last requisition date, and would then turn over any cash balance on the check to Densco so the latter could pay its employees. Following this procedure Beacon contends that of the $19,851 paid to it by checks from Stavrou, only $4,818.46 was for materials covered by the requisitions submitted to it. Since the cost of materials for the completed jobs totaled $18,877.62, Beacon argues that $14,059.16 is still due.

This Court is of the opinion that the checks were issued for payment only on the designated jobs, and that both labor and materials were included in the requisitions covered by the checks. Clearly, both Stavrou and Beacon understood Densco’s credit to be questionable, and this fact prompted the written agreement. Although the terms of the writing impose upon Stavrou the duty to make payment for materials not to exceed $20,000, Stavrou’s conduct had the effect of exceeding the obligation undertaken by the writing.

On July 9, for example, Stavrou issued three joint checks, one •designated “Taney,” one “Greendale” and the third “Tangle-wood.” Certainly, if appellant Stavrou expected the checks to be applied indiscriminately to materials owed on all three jobs, there would be no reason to draw three checks on the same day. Similarly, Stavrou issued two checks on June 15, one designated “Greendale” and the other, “Taney.” We must conclude *455 that Stavrou paid on individual requisitions which included both labor and materials expenses separately listed.

This conclusion is not necessarily inconsistent with the terms of the undated “agreement.” It should be noted that the instrument lists the material cost per job based on Beacon’s prior price quotations, with the total of $20,000 which Stavrou set as the upper limit of its agreement regarding materials. Since no mention was made of labor costs, it can be argued that when Stavrou received the monthly requisitions covering both material and labor, it combined both payments in the joint check rather than write one to Beacon for materials and another to Densco for labor. In other words, the fact that the agreement remained silent on the subject of labor expenses does not demand the conclusion that Stavrou intended the check to be in satisfaction of materials alone. As further support for this conclusion we note first, that each joint check satisfied the previous requisition which included material and labor, and second, that during the period of these payments Stavrou made no direct payments to Densco for the latter’s labor expenses.

In evaluating Stavrou’s contentions we cannot overlook the fact that Stavrou was acutely aware of Densco’s precarious financial condition and that the company was struggling to maintain solvency.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mehul's Investment Corp. v. ABC Advisors, Inc.
130 F. Supp. 2d 700 (D. Maryland, 2001)
Greens at Hilton Run I Ltd. Partnership v. Rollin Building Supply Co.
589 A.2d 536 (Court of Special Appeals of Maryland, 1991)
Allied Building Products Corp. v. United Pacific Insurance
549 A.2d 1163 (Court of Special Appeals of Maryland, 1988)
Porter v. General Boiler Casing Co.
396 A.2d 1090 (Court of Appeals of Maryland, 1979)
Snider Bros., Inc. v. Heft
317 A.2d 848 (Court of Appeals of Maryland, 1974)
Whalen v. Devlin Lumber & Supply Corp.
246 A.2d 247 (Court of Appeals of Maryland, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
240 A.2d 278, 249 Md. 451, 1968 Md. LEXIS 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/n-s-stavrou-inc-v-beacon-supply-co-md-1968.