J. F. Johnson Lumber Co. v. Magruder

147 A.2d 208, 218 Md. 440
CourtCourt of Appeals of Maryland
DecidedSeptember 1, 1980
Docket[No. 80, September Term, 1958.]
StatusPublished
Cited by26 cases

This text of 147 A.2d 208 (J. F. Johnson Lumber Co. v. Magruder) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. F. Johnson Lumber Co. v. Magruder, 147 A.2d 208, 218 Md. 440 (Md. 1980).

Opinion

Prescott, J.,

delivered the opinion of the Court.

This is an appeal from a decree of the Circuit Court for Prince George’s County declaring a mechanics’ lien filed by *442 appellant invalid and expunging the same from the records of said Court, dismissing the cross-bill of the appellant, and directing the appellee to pay the appellant the sum of $1,115.33 which the appellee owed to the contractor, Theodore J. Johnson.

On or about September 26, 1956, the appellee, M. Hampton Magruder, a well known and highly respected member of the Maryland Bar of many years standing, entered into a contract with one Theodore J. Johnson whereby Johnson agreed, for the price of $27,111, to construct a one-story brick building on a certain parcel of ground owned by the appellee in Prince George’s County. Within a few days, the contractor commenced construction and the house was finished in August of 1957.

During the period from October 1, 1956, to July 25, 1957, the appellant, hereinafter sometimes referred to as the “Lumber Company,” furnished lumber and other building materials to Johnson under one continuous contract for the construction of the house in question at prices conceded to be reasonable and proper. The total price of the materials supplied by the appellant was $9,569.86. Toward this amount, Johnson paid the Lumber Company $1,446.35 on November 16, 1956, and $500 some time after August 22, 1957, leaving a balance due of $7,623.51.

The appellant gave due notice of its claim to the appellee on August 19, 1957, and filed its mechanics’ lien on August 22, 1957. There is no dispute as to any of the foregoing facts.

It appears that prior to September of 1956 Mr. Magruder decided to build a dwelling house for his daughter-in-law and grandchildren. He retained the services of an architect. Friends of Mr. Magruder in Anne Arundel County told him of a man named Theodore J. Johnson, who lived in Anne Arundel County and had done some work for them, and they recommended him. Mr. Magruder testified that after conferring with Johnson he placed a telephone call to Mr. Carroll Lee, manager of the Annapolis yard of the appellant. There was a serious dispute as to whether this telephone call *443 was placed before or after Mr. Magruder signed the construction contract with Johnson. The Court found that the telephone call was made before the contract was signed—as claimed by Mr. Magruder—and that the conversation was substantially as related by him. Appellant concedes that it cannot say that this finding of fact was clearly wrong.

This conversation, as given by Mr. Magruder, was, in part, as follows:

“ ‘Well,’ I said, ‘Carroll, I am about to build a home over on Wilson Lane in Upper Marlboro, and I have been talking to a Theodore Johnson who has been recommended to me by Page Bowie and his wife as a good builder and I want to know what you know about him.’
“And he said, ‘Well, Mr. Mac, I have known him for thirty years. What do you want to know about him?’
“ ‘Well,’ I said, ‘I want to be perfectly certain that if I were to sign a contract with him I want to take all the precautions necessary that I would be safe in not exacting from Johnson a completion bond.’
* * *
“He said, ‘Mr. Mac, we have been doing business with Theodore Johnson for 20 years. We have got a high regard for him and in my judgment I don’t think you need worry about that. And so far as we are concerned, we will give him all the credit he needs.’ ”

Mr. Magruder further testified that because of this statement he “was lulled into security” and therefore did not require Johnson to furnish a completion bond.

The construction contract between Mr. Magruder and Johnson, however, provided that the contract price was to be paid to the contractor in four equal installments as the work progressed, and:

“That within one week subsequent to the payment *444 of any quarterly payment called for in this Contract shall have been made the said Contractor shall present to the said Owner receipts, or evidence of payment, showing all labor done on said building and all materials furnished for said building have been paid in full.”

The contract was prepared by Mr. Magruder and the clause quoted above was inserted at his suggestion; the contract being on a printed form with the clause quoted above typed in.

Mr. Magruder made his first quarterly payment in the amount of $6,775 to the contractor on November 13, 1956. This payment was due upon completion of the foundation and a few days later Johnson delivered to Mr. Magruder a release of liens, with one signature on it, the appellant’s.

It will be noted that this release fell far short of what was required under the contract. Within one week after a payment Johnson was duty bound to produce, and Mr. Magruder was entitled to demand, receipts or other evidence showing that all charges for labor and material incurred up to that time had been paid. The release which Johnson delivered to Mr. Magruder and which Mr. Magruder accepted, indicated only that one charge—in an unstated amount—had been paid.

Mr. Magruder testified that when he received this release he did not know and he did not inquire how much had been paid to the Lumber Company; and that he did not know and he did not ask Johnson whether there were other bills which had been paid, or whether there were any charges which were not paid. He knew that work and material, other than that supplied by appellant, had gone into the building, but he made no request for receipts or other evidence showing that the cost of such work and material had been paid.

Mr. Magruder made another payment to Johnson on December 13, 1956, and soon thereafter Johnson delivered another release of liens to him. Again, Mr. Magruder did not know and he did not ask how much Johnson had paid out; he did not ask Johnson for vouchers or other evidences of *445 payment; he did not inquire whether there were any bills which had not been paid. He had “no idea” at that time how much Johnson had paid out.

In February, 1957, Mr. Magruder made two more payments to Johnson, thereby completing the payments due under the second draw; soon thereafter Johnson delivered another release of liens.

After two or three questions directed to Mr. Magruder to ascertain whether he took any steps at this time to require Johnson to comply with the provisions of the contract, Mr. Magruder’s counsel objected and the Court sustained the objection, stating, “Whether or not Mr. Magruder policed the prime contractor is entirely beside the point.” Later in the trial, counsel for the appellant tried to resume this line of questioning, but upon objection the Court again ruled that any such testimony was irrelevant.

The testimony that was admitted showed that Mr. Magruder paid little or no attention as to whether Johnson was paying the bills for labor and material until construction of the house came to a standstill. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montgomery County v. Managed Care Innovations, LLC
261 F. Supp. 3d 567 (D. Maryland, 2017)
Olde Severna Park Improvement Ass'n v. Barry
982 A.2d 905 (Court of Special Appeals of Maryland, 2009)
Alternatives Unlimited, Inc. v. New Baltimore City Board of School Commissioners
843 A.2d 252 (Court of Special Appeals of Maryland, 2004)
Bessette v. Weitz
811 A.2d 812 (Court of Special Appeals of Maryland, 2002)
Friedman & Fuller, P.C. v. Funkhouser
666 A.2d 1298 (Court of Special Appeals of Maryland, 1995)
Peruzzi Brothers, Inc. v. Contee
527 A.2d 821 (Court of Special Appeals of Maryland, 1987)
King v. Bankerd
465 A.2d 1181 (Court of Special Appeals of Maryland, 1983)
Matter of Urban Development Co. & Associates
452 F. Supp. 902 (D. Maryland, 1978)
Dixon v. Process Corp.
382 A.2d 893 (Court of Special Appeals of Maryland, 1978)
Everdell v. Carroll
336 A.2d 145 (Court of Special Appeals of Maryland, 1975)
Zimmerman v. Summers
330 A.2d 722 (Court of Special Appeals of Maryland, 1975)
Douglass v. First National Realty Corporation
351 F. Supp. 1142 (District of Columbia, 1972)
MacPhail v. Sagner
293 A.2d 257 (Court of Appeals of Maryland, 1972)
United States v. 222.0 Acres of Land
306 F. Supp. 138 (D. Maryland, 1969)
Pumphrey v. Pelton
245 A.2d 301 (Court of Appeals of Maryland, 1968)
Chesapeake Homes, Inc. v. McGrath
240 A.2d 245 (Court of Appeals of Maryland, 1968)
N. S. Stavrou, Inc. v. Beacon Supply Co.
240 A.2d 278 (Court of Appeals of Maryland, 1968)
Travelers Indemnity Company v. Nationwide Construction Corporation
224 A.2d 285 (Court of Appeals of Maryland, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
147 A.2d 208, 218 Md. 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-f-johnson-lumber-co-v-magruder-md-1980.