Bruce Construction Corporation v. United States of America for Use of Westinghouse Electric Supply Company

242 F.2d 873, 1957 U.S. App. LEXIS 4633
Court of Appeals for the Fifth Circuit·Decided April 12, 1957·No. 16374_1·Published·Cited by 130 cases

Opinion

JOHN R. BROWN, Circuit Judge.

The question is whether summary judgment ought to have been granted against a general contractor and its surety 1 in an action under the Miller Act, 40 U.S.C.A. §§ 270a-270d, for materials furnished to or for a subcontractor 2 for construction of a Veterans Hospital.

We have long recognized that no matter how enticing, in an era of congested dockets, is a device to dispose of cases without the delay and expense of traditional trials with their sometime cumbersome and time-consuming characteristics, summary judgment was not devised for, must not be used as, a substitute for trial. Its wholesome utility is, in advance of trial, to test, not as formerly on bare contentions found in the legal jargon of pleadings, but on the intrinsic merits, whether there is in actuality a real basis for relief or defense. Consequently, where the proceedings have indicated that a genuine issue existed, we have consistently rejected 3 appealing shortcuts and not the less so even though it was likely that on a trial, the trier would resolve the disputed issues as one of fact in the same manner as when thought to have been one of law alone.

But, equally vigorous in giving full range to this mechanism, we have just as consistently rejected any notions that pretense, or apparent formal controversy can thwart application of this rule or hamstring the court in de *875 termining whether it is a proper case for it. Consequently, when a movant makes out a convincing showing that genuine issues of fact are lacking, we require 4 that the adversary adequately demonstrate by receivable facts that a real, not formal, controversy exists, and, of course, he does not do that by mere denial or holding back evidence.

And yet, reflecting in spots a picayunishness out of step with the spirit of the Federal Rules, that is just what the General Contractor did and which the District Court found, as do we, inadequate.

It asserts, for example, that an issue of fact was revealed because the complaint alleged that the last material was supplied to the Subcontractor on January 14, 1955, while one affidavit said it was January 15, and two others fixed it at January 17. But this was just such trivia as the Federal Rules were designed to weed out. For the date was important only in fixing the time within which the 90-day written notice must be given, 40 U.S.C.A. § 270b, where services or supplies are furnished to a subcontractor. And, except for a like quibbling, there was really no question about this. By categorical affidavit, an authenticated copy of the letter dated January 24, 1955, from the Supplier to the General Contractor (with indicated copies to the Subcontractor and surety) giving plain notice that the unpaid balance of the Subcontractor’s account was $112,997.78 was shown to have been sent Registered-Return Receipt Requested that day and receipted for by a specified representative of the General Contractor on January 26, 1955. Because another somewhat similar letter was sent on May 23, 1955, beyond the 90-day period, and the copy of the one of January 24 was not somehow itself sworn or certified to, Fed.Rules Civ.Proc. rule 56(e), 28 U. S.C.A. (although the affidavit of the credit manager incorporated and attached it as an exhibit) and these minor discrepancies appeared, it is claimed that a court, with or without a jury, had to hear evidence on this matter even though it was conceded on argument, as it had to be that a notice specifying the balance as $112,997.78 was a statement “with substantial accuracy” for a claim asserted and allowed finally in the sum of $114,770.52, Coffee v. United States, 5 Cir., 157 F.2d 968; Houston Fire & Casualty Insurance Co. v. United States, 5 Cir., 217 F.2d 727.

Equally hypercritical is the struggle to contrive a dispute over the filing of the suit within one year after the date of final settlement between the Government and the contractor, 40 U. S.C.A. § 270b (b). As it was undisputed, we hold above, that the last material was supplied about January 15-17, 1955, the contract obviously was not then closed, and the suit, filed August 26,1955, while theoretically capable of being too early, could not possibly have been too late. Moreover, no one would have better knowledge of the exact time final settlement was made with the Government, or more ready means for obtaining the conclusive certificate of the Comptroller General, 40 U.S.C.A. 270c, than the General Contractor. It could not, in the good faith the Rules command, FRCP 8(b), 11, 56(g), construct a disputed issue by allegations in its answer that it was “without knowledge as to [those] * * * allegations of * * * said complaint.” And when this matter, after a year’s pretrial discovery, reached a hearing on the motion for summary judgment in which the Judge, FRCP 56(d), by examination of the papers and “interrogating counsel,” would have to determine to what extent genuine issues were lacking, it was for the General *876 Contractor then to demonstrate under oath what it did not attempt to do, because it could not. So the complaint again is that trial was denied of an issue in fact utterly out of the case, and on which no dispute could or did exist and which, of all people, the General Contractor so well knew.

Free access — add to your briefcase to read the full text and ask questions with AI

Bruce Construction Corporation v. United States of America for Use of Westinghouse Electric Supply Company, 242 F.2d 873, 1957 U.S. App. LEXIS 4633 (5th Cir. 1957).

242 F.2d 873 (Bruce Construction Corporation v. United States of America for Use of Westinghouse Electric Supply Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Paone v. Microsoft Corp.
881 F. Supp. 2d 386 (E.D. New York, 2012)
Evabank v. Baxter
278 B.R. 867 (N.D. Alabama, 2002)
Avirgan v. Hull
691 F. Supp. 1357 (S.D. Florida, 1988)
Marshall v. United Egg Products, Inc.
95 F.R.D. 179 (S.D. Georgia, 1982)
Garner v. Pearson
545 F. Supp. 549 (M.D. Florida, 1982)
Pioneer Valley Credit Union v. Wright (In Re Wright)
19 B.R. 271 (D. Massachusetts, 1982)
Donovan v. Nellis
528 F. Supp. 538 (N.D. Florida, 1981)
Glynn J. Pelotto v. L & N Towing Company
604 F.2d 396 (Fifth Circuit, 1979)
Golden Oil Company, Inc. v. Exxon Company, U.S.A.
543 F.2d 548 (Fifth Circuit, 1976)
John C. Reeves v. City of Jackson, Mississippi
532 F.2d 491 (Fifth Circuit, 1976)
Donnie R. McCormick v. Frances G. Ross
506 F.2d 1205 (Eighth Circuit, 1974)