Mrozik Construction, Inc. v. Lovering Associates, Inc.

461 N.W.2d 49, 1990 Minn. App. LEXIS 948, 1990 WL 140943
CourtCourt of Appeals of Minnesota
DecidedOctober 2, 1990
DocketC8-90-961
StatusPublished
Cited by17 cases

This text of 461 N.W.2d 49 (Mrozik Construction, Inc. v. Lovering Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mrozik Construction, Inc. v. Lovering Associates, Inc., 461 N.W.2d 49, 1990 Minn. App. LEXIS 948, 1990 WL 140943 (Mich. Ct. App. 1990).

Opinion

OPINION

KALITOWSKI, Judge.

Appellant Lovering Associates, Inc. challenges the trial court’s grant of summary judgment for respondent Mrozik Construction, Inc., arguing that payment by the owner to the general contractor was a condition precedent to payment by the general contractor to the subcontractor.

FACTS

Appellant Lovering Associates, Inc. (Lov-ering) is a general contractor of commercial buildings. In 1986, Stratford Investments, Ltd. contracted with Lovering to construct two office buildings in a professional office development in Falcon Heights, Minnesota. Lovering executed several subcontract agreements to perform the construction work, including a subcontract with respondent Mrozik Construction, Inc. (Mrozik) executed on September 10, 1986. According to the parties’ subcontract, Mrozik was to perform concrete and masonry work for payment in the amount of $144,207, increased to $177,928 after changes and extras.

By August 1987, the owner, Stratford Investments, Ltd., had unpaid amounts due to Lovering of $71,486 for work completed on building no. 1 and $58,990 on building no. 2. These amounts were never paid due to the owner’s insolvency.

As a result of the owner’s failure to pay Lovering, Lovering did not pay the final unpaid balance of $20,843.20 due on the subcontract with Mrozik. Lovering does not dispute that Mrozik completely and satisfactorily performed the work as required by the subcontract. Rather, Lovering contends that language in the subcontract establishes payment by the owner to the general contractor as a condition precedent to payment to the subcontractor, thus excusing its failure to pay Mrozik. Lovering also argues that based on the subcontract language, the architect’s failure to certify the completed work for payment further justifies nonpayment to Mrozik. The language in the subcontract relied on by Lov-ering states:

THE CONTRACTOR AGREES AS FOLLOWS:
D. Final payment including all retention becomes due and payable within 30. days after Architects’ certification of final payment. At all times the Subcontractor shall be paid to the extent that the Contractor has been paid on the Subcontractor’s account.

(Emphasis added.)

The parties’ subcontract document is published by the Associated General Contractors of Minnesota and is titled “Standard Subcontract Agreement.” Lovering selected the document to be used and prepared the form by providing information in the appropriate blanks.

Mrozik filed a complaint to recover the amount due plus interest from Lovering. The trial court granted summary judgment for Mrozik on March 7, 1990, ruling as a matter of law that the developer’s payment to the general contractor Lovering was not a condition precedent in the subcontract to the general contractor’s payment to the subcontractor Mrozik. Lovering Associates, Inc. appeals from the judgment entered pursuant to the trial court’s order granting summary judgment for respondent Mrozik Construction, Inc.

ISSUE

Does a subcontract providing for payment by the general contractor to the subcontractor to the extent the general contractor has been paid by the developer establish the developer’s payment as a condition precedent to payment of the subcontractor?

ANALYSIS

In a review of summary judgment, this court must determine whether there are any issues of material fact and whether the *51 trial court erred in its application of the law. Offerdahl v. University of Minn. Hosps. & Clinics, 426 N.W.2d 425, 427 (Minn.1988). The question of whether the terms of a contract are ambiguous is a question of law. Boe v. Christlieb, 399 N.W.2d 131, 133 (Minn.App.1987). The appellate court need not defer to the trial court in reviewing questions of law. A.J. Chromy Constr. Co. v. Commercial Mechanical Servs., Inc., 260 N.W.2d 579, 582 (Minn.1977).

The question presented in this case is the effect of a provision in a subcontract providing that the general contractor shall pay the subcontractor to the extent the general contractor has been paid. The general contractor Lovering Associates, Inc. contends that the provision makes the owner’s payment a condition precedent to payment of the subcontractor, so that the owner’s insolvency excuses nonpayment to the subcontractor.

Although Minnesota courts have not addressed this issue, the law is well settled in other jurisdictions. Both the Restatement (Second) of Contracts, and state and federal courts have taken the position that a subcontract will not be construed as having payment to the general contractor as a condition precedent to the general contractor’s payment to the subcontractor, unless the parties express such intent in plain, unequivocal, and unambiguous language in the subcontract.

The Restatement (Second) of Contracts, section 227, Standards of Preference with Regard to Conditions, states:

(1) In resolving doubts as to whether an event is made a condition of an obligor’s duty, and as to the nature of such an event, an interpretation is preferred that will reduce the obligee’s risk of forfeiture, unless the event is within the obli-gee’s control or the circumstances indicate that he has assumed the risk.

Comments to the above section indicate that forfeiture refers to the denial of payment to the obligee. Restatement (Second) of Contracts § 227 comment b (1981). The Restatement illustrates the rule of law with an example specifically pertaining to a general and subcontractor and a provision in a subcontract agreement similar to the one presented in this case. The illustration addresses the following provision in a subcontract: “[N]o part of [payment to the subcontractor] shall be due until five days after Owner shall have paid Contractor therefor.” The Restatement states that this language should not be construed to establish the owner’s payment as a condition precedent to payment on the subcontract. Instead, the Restatement instructs that upon the owner’s insolvency, the provision would require the general contractor to pay the subcontractor within a reasonable period of time. Restatement (Second) of Contracts § 227 comment b, illustration 1 (1981).

Numerous state and federal courts that have addressed the issue have adopted the Restatement rule of law. Darrell T. Stuart Contractor v. J.A. Bridges & Rust-Proofing, Inc., 2 Ariz.App. 63, 406 P.2d 413 (1965); Peacock Constr. Co. v. Modern Air Conditioning, Inc., 353 So.2d 840 (Fla.1977); A.J. Wolfe Co. v. Baltimore Contractors, Inc., 355 Mass. 361, 244 N.E.2d 717 (1969); Howard-Green Elec. Co. v. Chaney & James Constr. Co., 12 N.C.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Design Basics, LLC v. Chelsea Lumber Co.
977 F. Supp. 2d 714 (E.D. Michigan, 2013)
Marine Credit Union v. Detlefson-Delano
813 N.W.2d 429 (Court of Appeals of Minnesota, 2012)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Calabrese Foundation, Inc. v. Investment Advisors, Inc.
831 F. Supp. 1507 (D. Colorado, 1993)
Norwest Bank Minnesota, N.A. v. Midwestern MacHinery Co.
481 N.W.2d 875 (Court of Appeals of Minnesota, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
461 N.W.2d 49, 1990 Minn. App. LEXIS 948, 1990 WL 140943, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mrozik-construction-inc-v-lovering-associates-inc-minnctapp-1990.