Same Day Surgery Centers, L.L.C., Plaintiff-Appellant/cross v. Montana Regional Orthopedics, L.L.C., Defendant-Appellee/cross

433 F.3d 570, 2005 U.S. App. LEXIS 28990
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 30, 2005
Docket04-3908, 04-3909
StatusPublished

This text of 433 F.3d 570 (Same Day Surgery Centers, L.L.C., Plaintiff-Appellant/cross v. Montana Regional Orthopedics, L.L.C., Defendant-Appellee/cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Same Day Surgery Centers, L.L.C., Plaintiff-Appellant/cross v. Montana Regional Orthopedics, L.L.C., Defendant-Appellee/cross, 433 F.3d 570, 2005 U.S. App. LEXIS 28990 (8th Cir. 2005).

Opinion

LOKEN, Chief Judge.

Montana Regional Orthopedics (MRO), an orthopedic physician group practicing in Missoula, Montana, hired Minnesota-based Same Day Surgery (SDS) to construct, equip, and manage an ambulatory surgical center in Missoula. After SDS substantially completed the facility in June 2001, MRO denied demands for final payments. SDS commenced this diversity action for breach of two contracts, and MRO asserted breach of contract counterclaims. After a bench trial, applying Minnesota law, the district court 1 rejected SDS’s primary claim for reimbursement of expenses invoiced by third party vendors, finding that SDS failed to prove that the amounts it paid vendors exceeded MRO’s contract payments to SDS for this purpose. The court upheld two of SDS’s lesser contract claims, rejected MRO’s counterclaims, and entered judgment for SDS in the amount of $23,840.44, plus statutory prejudgment interest and contract-based attorneys fees. SDS appeals the rejection of its main claim. MRO cross-appeals the rejection of one counterclaim. We affirm.

I.

The parties’ relationship was reflected in a Development Agreement signed June 1, 2000, and a Management Agreement signed July 1, 2000. Only the Development Agreement is at issue on appeal. Under that Agreement, SDS agreed to purchase real estate, design and construct the surgical center, purchase and install necessary equipment, supervise selection of the nursing staff, and obtain certifications and licenses. MRO agreed to reimburse SDS for costs and expenses incurred and to pay SDS a “Development Fee” of $457,500. The Agreement provided that the total Project costs including the Development Fee “will not exceed $2,042,603.”

Construction of the surgical center began in late October 2000. MRO physicians saw their first patient at the facility in early March 2001. The surgical center received provisional accreditation as an approved Medicare facility efféctive June 18, 2001, which the parties agree was the Substantial Completion date under the Agreement. During these phases of the Project, MRO made four progress payments of $430,000 each, not always in response to SDS invoices. MRO paid SDS a total of $1,857,006 under the Development Agreement. On January 30, 2002, SDS sent MRO a final invoice of $246,007.62, an amount that exceeded the contract cap by *572 some $60,411. MRO refused to pay any part of that invoice. This lawsuit followed.

At trial, SDS conceded that MRO had paid the entire $457,500 Development Fee but claimed that invoices received from third party vendors put the total Project costs in excess of the $2,042,603 cap. Therefore, SDS argued, MRO owed an additional $185,597 for unreimbursed vendor expenses. SDS calculated its claim by subtracting the $1,857,006 paid by MRO from the contract cap. In support of the claim, SDS introduced vendor invoices (which it did not include in the record on appeal); Exhibit 4, a summary exhibit showing $1,561,820.59 in vendor invoices received by SDS; Exhibit 6, a summary exhibit showing a total of $1,185,904.94 paid by SDS to vendors; and testimony by Margaret Olin, a partner in SDS, explaining which entries on Exhibit 4 and Exhibit 6 were included in the $185,597 claim.

There was also trial testimony that SDS experienced financial difficulty during and after completion of the surgical center Project. Olin testified that she negotiated invoice reductions with some vendors and paid some vendor obligations with personal checks, and that one or two vendors had sued SDS and obtained money judgments. MRO’s chief executive, Ronald Peterson, testified that MRO paid some vendors directly to maintain needed relationships. Despite this episodic testimony, neither party introduced probative evidence as to the status of vendor claims, nor did SDS represent that monies it collected on its claim would be paid to vendors.

II.

On appeal, SDS argues that MRO received the full benefit of its bargain, SDS presented evidence that it has incurred liabilities which exceed the contract cap, and therefore SDS was entitled to payment of the full $2,042,603 cap. In response, MRO argues that the trial evidence proved that SDS’s payments to vendors plus its Development Fee were substantially less than the $1,857,006 paid by MRO under the Agreement. Therefore, MRO does not owe SDS the claimed $185,597. Rather, SDS owes MRO for its “overpayment” of reimbursable vendor expenses. These competing contentions require a closer look at the payment provisions in the Development Agreement. The interpretation of these provisions is a question of law we review de novo. See Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minn., 664 N.W.2d 303, 311 (Minn.2003).

Section 2 of the Development Agreement is entitled “Development services to be provided by [SDS].” It contains two relevant provisions:

2.2.3 Construction____ [SDS] will enter into appropriate agreements with the general contractor and/or other parties for construction of the Project.... [MRO] shall pay when due or promptly reimburse [SDS] for all amounts payable under such construction contracts.
2.2.4 Equipment Selection and Purchasing. ... [SDS] will coordinate the purchase and arrange for delivery and installation of all capital equipment, instruments and supplies necessary for operation of the Project through national vendors selected by [SDS] .... [SDS] shall enter into appropriate agreements ... for the purchase of such equipment, instruments and supplies. [MRO] shall pay when due or promptly reimburse [SDS] for all amounts payable under such agreements.

Section 4 of the Agreement is entitled “[SDS’s] Fees and Expenses” and contains what the parties consider the most relevant provision:

*573 4.3 Direct Expenses. In addition to fees payable to [SDS], [MRO] shall reimburse [SDS] for certain direct expenses advanced by [SDS] ... except where such expenses are expressly stated to be the responsibility of [SDS]____ Direct expenses shall include out-of-pocket disbursements, including but not limited to ... fees or charges advanced to other parties.... [SDS] shall send invoices ... for its direct expenses on a monthly basis during the development of the Project and [MRO] shall pay such invoices within ten (10) days of receipt. Any amounts remaining unpaid ... shall be due and payable in full at Substantial Completion.

Finally, Section 5 of the Agreement is entitled “[MRO] Responsibilities” and contains the following provision:

5.4 Equity/Loan Funds; Payment Obligations .... [MRO] shall pay when due all amounts to be paid to any third party in connection with the development of the Project, regardless of whether [SDS] or [MRO] entered into the contract with such third party, unless the obligation to pay such amounts is expressly stated herein to be that of [SDS].

The critical issue, as framed by the parties, is whether these provisions, and particularly § 4.3 with its use of the word “advanced,” limit MRO’s reimbursement obligations to amounts SDS has in fact paid

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mrozik Construction, Inc. v. Lovering Associates, Inc.
461 N.W.2d 49 (Court of Appeals of Minnesota, 1990)
Noreen v. Park Construction Co.
96 N.W.2d 33 (Supreme Court of Minnesota, 1959)
Alpha Real Estate Co. of Rochester v. Delta Dental Plan of Minnesota
664 N.W.2d 303 (Supreme Court of Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
433 F.3d 570, 2005 U.S. App. LEXIS 28990, Counsel Stack Legal Research, https://law.counselstack.com/opinion/same-day-surgery-centers-llc-plaintiff-appellantcross-v-montana-ca8-2005.