Noreen v. Park Construction Co.

96 N.W.2d 33, 255 Minn. 187, 1959 Minn. LEXIS 585
CourtSupreme Court of Minnesota
DecidedApril 10, 1959
Docket37,601
StatusPublished
Cited by22 cases

This text of 96 N.W.2d 33 (Noreen v. Park Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noreen v. Park Construction Co., 96 N.W.2d 33, 255 Minn. 187, 1959 Minn. LEXIS 585 (Mich. 1959).

Opinion

Knutson, Justice.

This is an appeal from an order denying defendant’s alternative motion for judgment notwithstanding the verdict in favor of plaintiff or for a new trial.

In the spring of 1956 the United States Corps of Army Engineers, hereinafter called the engineers, let a contract to Ashbach Construction Company for the construction of certain runways at the Williamson-Johnson Airport at Duluth. Ashbach sublet the work of furnishing and compacting the subgrade material to defendant, Park Construction Company for the construction of certain runways at the Williamson-method of compaction were controlled by specifications prepared by the engineers. The specifications required that all material must be approved by the engineers.

*189 During May 1956 negotiations were had between Park and one Joe Kolojeski for hauling the subgrade material. Pits controlled by Kolojeski had been approved by the engineers. No contract was entered into at that time, but Kolojeski was permitted to commence hauling on June 4, 1956.

On June 2, 1956, Kris Bonander, plaintiff’s general manager, called at the office of Park in Minneapolis and discussed the matter of hauling material for this job. As a result of such discussions, the parties executed an instrument, referred to in the record as exhibit 1, which reads as follows:

“Duluth, Minnesota
“June 2, 1956
“Park Construction Company
“51 37th Avenue North East
“Minneapolis 21, Minnesota
“Re: Williamson-Johnson Airport,
Duluth, Minnesota
Contract No. DA 21-018-eng.-1081
f‘Gentlemen:
“We propose to furnish and deliver select sub-grade material to the Williamson-Johnson Airport, Duluth, Minnesota — such material to be in accordance with plans and specifications and meet with approval of the Corps of Engineers — at the unit price of ninety-five cents ($ .95) per cubic yard measured in place.
“It is understood and agreed, however, that Park Construction Company is to do the placing and compacting of such select sub-grade material as is furnished and delivered by us.
“It is also understood and agreed that in the event such sub-grade material as we have does not meet with the approval of the Corps of Engineers this proposal is null and void.
“Respectfully submitted,
“Noreen Trucking and Contracting Co.
“By Kris Bonander (Signed)
“Accepted June 2, 1956.
“Park Construction Co.
“Bv W. E. Carlson (Signed) President”

*190 On June 14, 1956, after a considerable portion of the material had been hauled, Park and Kolojeski entered into a written contract under the terms of which Kolojeski agreed to furnish all labor, material, skill, and instrumentalities and to secure all field measurements necessary or required and perform all work necessary or incidentally required for hauling all the subgrade material covered by this contract.

Plaintiff was not permitted to haul any material for the project. After the completion of the work he brought this action to recover damages for breach of contract. The-jury returned a verdict in his favor. On this appeal, the questions for our determination are: (1) Did Park and plaintiff enter into an enforceable contract under which plaintiff had a right to furnish all or a part of the required subgrade material? (2) If such contract was entered into, has plaintiff established his ability to perform? (3) What, if any, damages should plaintiff be entitled to recover?

Plaintiff contends that exhibit 1 constitutes an enforceable contract under which he was entitled to furnish all the subgrade material required in the performance of this subcontract. Defendant contends that the alleged contract is so lacking in mutuality that it is unenforceable. The trial court determined as a matter of law that the exhibit constituted an entire contract and that plaintiff was entitled to recover if he was able to establish his ability to perform. It was the trial court’s opinion that whatever ambiguity existed in the instrument signed by the parties had been eliminated by admissions in the pleadings, stipulations in the record, and the construction placed on the instrument by the parties themselves. There seems to be no dispute between the parties as to the rules applicable to the construction of a contract.

In Leslie v. Minneapolis Teachers Retirement Fund Assn. 218 Minn. 369, 373, 16 N. W. (2d) 313, 315, we said:

“The rule is well established that ordinarily the construction of a writing which is unambiguous is for the court, particularly when the intention of the parties is to be gained wholly from the writing. However, if the language is ambiguous, resort may be had to extrinsic evidence, and construction then becomes a question of fact, unless such evidence is conclusive. * * * Ordinarily, the question whether the language of a contract is ambiguous is one of law for the court. *191 * * * The extrinsic facts which may be considered in aid of construction are ordinarily questions for the court. * * * It is also true that where parties to a contract have given it a practical construction by their conduct, as by acts in performance thereof, such construction may be considered by the court in determining its meaning and in ascertaining the mutual intent of the parties. * * * Where such extrinsic evidence is conclusive and undisputed and renders the meaning of the contract clear, its construction again becomes a question of law for the court.”

Here, the ¿vidence of plaintiff and defendant as to what they intended by the written instrument is in hopeless conflict. The problem of resolving such conflict rested with the jury.

At the outset, it is apparent that exhibit 1 is open to at least three interpretations: (a) That plaintiff agreed to furnish all material needed for completion of the job and that the contract was null and void if he could not procure approval of enough material to perform the contract in its entirety; (b) that plaintiff agreed to furnish and defendant agreed to accept so much material as plaintiff had for which he could procure approval; or (c) that plaintiff agreed to furnish as much material approved by the engineers as defendant would accept but that defendant could procure all or a part of such material from others.

The trial court took the position that the contract should be construed as a matter of law according to interpretation (a). The court instructed the jury:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staffing Specifix, Inc. v. Tempworks Mgmt. Servs., Inc.
913 N.W.2d 687 (Supreme Court of Minnesota, 2018)
Pillsbury Co., Inc. v. Wells Dairy, Inc.
752 N.W.2d 430 (Supreme Court of Iowa, 2008)
Stephenson v. Greenblatt (In Re MJK Clearing, Inc.)
408 F.3d 512 (Eighth Circuit, 2005)
First Security Bank of Utah, N.A. v. Northwest Airlines, Inc.
43 F. Supp. 2d 136 (D. Massachusetts, 1999)
State Ex Rel. Humphrey v. Delano Community Development Corp.
571 N.W.2d 233 (Supreme Court of Minnesota, 1997)
Sprangers v. Interactive Technologies, Inc.
394 N.W.2d 498 (Court of Appeals of Minnesota, 1986)
Blackburn, Nickels & Smith, Inc. v. Erickson
366 N.W.2d 640 (Court of Appeals of Minnesota, 1985)
Lamb Plumbing & Heating Co. v. Kraus-Anderson of Minneapolis, Inc.
296 N.W.2d 859 (Supreme Court of Minnesota, 1980)
Rooney v. Dayton-Hudson Corp.
246 N.W.2d 170 (Supreme Court of Minnesota, 1976)
Transport Indemnity Co. v. Dahlen Transport, Inc.
161 N.W.2d 546 (Supreme Court of Minnesota, 1968)
Donnay v. Boulware
144 N.W.2d 711 (Supreme Court of Minnesota, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
96 N.W.2d 33, 255 Minn. 187, 1959 Minn. LEXIS 585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noreen-v-park-construction-co-minn-1959.