Lamb Plumbing & Heating Co. v. Kraus-Anderson of Minneapolis, Inc.

296 N.W.2d 859, 1980 Minn. LEXIS 1571
CourtSupreme Court of Minnesota
DecidedAugust 29, 1980
Docket50411
StatusPublished
Cited by36 cases

This text of 296 N.W.2d 859 (Lamb Plumbing & Heating Co. v. Kraus-Anderson of Minneapolis, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamb Plumbing & Heating Co. v. Kraus-Anderson of Minneapolis, Inc., 296 N.W.2d 859, 1980 Minn. LEXIS 1571 (Mich. 1980).

Opinion

SCOTT, Justice.

Plaintiff Lamb Plumbing & Heating Co. (Lamb) brought this action against Kraus-Anderson of Minneapolis, Inc. (Kraus-An-derson) to recover the value of certain work done on a wastewater treatment construction project. The matter was tried in Hen-nepin County District Court without a jury. The trial court ordered judgment for plaintiff. Defendant appeals from the trial court’s order denying its motion for a new trial or for amended findings. We affirm.

In June, 1974, the Metropolitan Sewer Board began advertising for competitive bids on a public contract to construct a wastewater pretreatment facility at its Pig’s Eye site (the facility is designated as Project 71-06). The contract documents were prepared by Toltz, King, Duvall, Anderson and Associates, Inc. These documents include a specifications book, general conditions, plans, drawings, and schedules. The contract was to be awarded to a single prime contractor. Contract bids were due on August 13, 1974.

Defendant Kraus-Anderson decided that it would present a bid as prime contractor for the project, doing 40% of the construction itself and subcontracting the rest. Kraus-Anderson obtained plans and specifications for the project three or four weeks prior to the bid date. At approximately the same time, plaintiff Lamb also obtained the plans and decided to bid for a subcontract for mechanical work, set out in Division 15 of the contract. Lamb submitted bids for the mechanical work to various potential prime contractors, and Kraus-Anderson in turn solicited bids from subcontractors for various portions of the project, including the mechanical work. Several witnesses testified that the submission and acceptance of subcontracting bids for a large project such as this one is a last-minute, hectic affair, as the contractors compete for the best price. Lamb bid for the mechanical work with Kraus-Anderson shortly before Kraus-Anderson’s general bid was due, on August 13. Kraus-Anderson accepted Lamb’s bid, and was awarded the prime contract for $13,048,989. Within a few months, this dispute arose between Lamb and Kraus-Anderson as to whether certain valves and wall pipes or fittings were to be provided by the mechanical subcontractor or the force main subcontractor. Neither party wished to delay the project because of *861 the dispute, and therefore plaintiff and defendant executed a subcontract for performance of the mechanical work, including the disputed items, and agreed that the dispute would be resolved later: The parties stipulated that the value of the disputed work was $96,401.84.

Project 71-06 was designed to provide additional sewage treatment capacity at the Pig’s Eye facility in St. Paul. The sewage was to be partially treated at a South St. Paul plant, and then transferred to Pig’s Eye by means of a 48-inch diameter force main pipe. At the Pig’s Eye site, the force main pipe was to take the sewage through a concrete wall into a meter vault located underground (used to measure the volume of sewage), out of the vault through a concrete wall, and then through a third wall into a valve pit. The valve pit, also located underground, was to contain two 48-inch gate valves. These gate valves could be used to direct the flow of sewage into a large main facility (constructed as part of the same project) or into an adjacent facility.

' The mechanical subcontract for Project 71-06 required plaintiff to do work inside the various structures. The force main subcontractor, J. & T. Contractors, was responsible for the construction of the force main pipe. The dispute in this case between plaintiff and Kraus-Anderson involves the question of whether the mechanical subcontractor (plaintiff) or the force main subcontractor was required by the contract to provide the two 48-inch gate valves located within the valve pit and the five wall pipes or wall fittings needed to carry the force main pipe in and out of the meter vault and the valve pit. Plaintiff contends that these items are included under Division 2 of the contract specifications and not under Division 15, the mechanical division for which it bid. The problem arises because the valves and wall fittings are referred to in both divisions of the contract and drawings, and their locations and functions are such that they could logically be included under either subcontract.

The trial court concluded that Kraus-An-derson, but not plaintiff, was aware of the potential conflict in subcontracts prior to the time that it accepted plaintiff’s bid for the mechanical work. The trial court found that Mr. Simpkins, the project manager for Kraus-Anderson, had a conversation with Mr. Frost of J. & T. Contractors (the force main subcontractor) one day before the prime bid was due, during which Frost told Simpkins that he was confused about who should provide the valves and wall fittings. Frost advised Simpkins that he was excluding them from his bid because someone at the engineering office told him that the disputed items were under the mechanical section. The mechanical bidders on Simp-kins’ list of specification holders were told that they should include the disputed items in their bid, but plaintiff was not on this list. The trial court found that plaintiff was not told about this decision and was not aware of any ambiguity in the contract as to the disputed items. According to plaintiff’s interpretation of the contract, the disputed items were to be supplied by the force main subcontractor; therefore, plaintiff did not include these items in its bid calculations. Kraus-Anderson did not mention the disputed items to plaintiff when it accepted plaintiff’s bid.

The trial court concluded that the contract was not ambiguous as to which subcontractor should supply the 48-inch gate valves, and that the force main subcontractor was responsible for them. The trial court held that the contract was ambiguous as to who was to provide the five wall fittings. Without resolving the ambiguity, the court found that plaintiff did not believe that there was an ambiguity, that plaintiff’s analysis of the contract was reasonable, and that Kraus-Anderson was aware of the potential conflict. The trial court therefore concluded that because Kraus-Anderson failed to clear up a known potential conflict plaintiff should not be held responsible for providing the wall fittings.

1. Defendant Kraus-Anderson challenged several aspects of the trial court’s *862 decision. Defendant contends that the contract provisions are not ambiguous as to either the gate valves or the wall fittings, and that the contract clearly requires the mechanical subcontractor to provide all of them. Defendant argues in the alternative that if the contract is ambiguous, a new trial is required to properly weigh all the factors which should be considered in resolving an ambiguity.

A contract is ambiguous if it is susceptible to more than one interpretation based on its language alone. See, Metro Office Parks Co. v. Control Data Corp., 295 Minn. 348, 205 N.W.2d 121 (1973); Telex Corp. v. Data Products Corp., 271 Minn. 288, 135 N.W.2d 681 (1965).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Ashman
608 N.W.2d 853 (Supreme Court of Minnesota, 2000)
Backus v. Kauffman
605 N.W.2d 690 (Michigan Court of Appeals, 1999)
First Security Bank of Utah, N.A. v. Northwest Airlines, Inc.
43 F. Supp. 2d 136 (D. Massachusetts, 1999)
Art Goebel, Inc. v. North Suburban Agencies, Inc.
567 N.W.2d 511 (Supreme Court of Minnesota, 1997)
Hurlburt v. Northern States Power Co.
549 N.W.2d 919 (Supreme Court of Minnesota, 1996)
Barry v. Barry
78 F.3d 375 (Eighth Circuit, 1996)
Sandra Barry v. Charles L. Barry
78 F.3d 375 (Eighth Circuit, 1996)
Satterlund v. Murphy Bros', Inc.
895 F. Supp. 240 (D. Minnesota, 1995)
Current Technology Concepts, Inc. v. Irie Enterprises, Inc.
530 N.W.2d 539 (Supreme Court of Minnesota, 1995)
Finke v. State
521 N.W.2d 371 (Court of Appeals of Minnesota, 1994)
Williams v. Harris
518 N.W.2d 864 (Court of Appeals of Minnesota, 1994)
Matter of Zahradka
472 N.W.2d 153 (Court of Appeals of Minnesota, 1991)
Metropolitan Sports Facilities Commission v. General Mills, Inc.
470 N.W.2d 118 (Supreme Court of Minnesota, 1991)
Fredrich v. Independent School District No. 720
465 N.W.2d 692 (Court of Appeals of Minnesota, 1991)
Metropolitan Sports Facilities Commission v. General Mills, Inc.
460 N.W.2d 625 (Court of Appeals of Minnesota, 1990)
Mutsch v. Rigi
430 N.W.2d 201 (Court of Appeals of Minnesota, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
296 N.W.2d 859, 1980 Minn. LEXIS 1571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamb-plumbing-heating-co-v-kraus-anderson-of-minneapolis-inc-minn-1980.