Williams v. Harris

518 N.W.2d 864, 1994 Minn. App. LEXIS 618, 1994 WL 314764
CourtCourt of Appeals of Minnesota
DecidedJuly 5, 1994
DocketCX-94-288, CX-94-355
StatusPublished
Cited by6 cases

This text of 518 N.W.2d 864 (Williams v. Harris) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Harris, 518 N.W.2d 864, 1994 Minn. App. LEXIS 618, 1994 WL 314764 (Mich. Ct. App. 1994).

Opinion

OPINION

LANSING, Judge.

This appeal raises the issue of whether a road construction contractor and its subcontractor have a contractual or common law duty to motorists using a detour route designed and maintained by the State of Minnesota. We hold that neither the contract nor the common law imposes a duty on the contractor or the subcontractor to provide for the safety of a detour route that is a preexisting roadway outside the construction zone. Nor is a duty created by the subcontractor gratuitously inspecting the detour route to determine the effectiveness of traffic control devices when there is no reliance on the inspection.

FACTS

The claims at issue arise from a fatal accident during the extensive reconstruction of Trunk Highway 55 in Dakota County. The Minnesota Department of Transportation (MN/DOT) established a detour to route traffic off Highway 55 and assumed jurisdiction over county roads within the detour route. As part of the plan, MN/DOT specified the precise location of each traffic control device within the detour route.

Under a contract between the state and Shafer Contracting Co., the state delegated to Shafer the “furnishing, installing, maintaining, and removing” of traffic control devices as shown in MN/DOT’s traffic control plan. Shafer contracted with Warning Lites of Minnesota, Inc. to fulfill that part of the contract relating to traffic control devices.

The accident occurred at an intersection along the detour route, more than two miles from the construction zone. John Harris, driving a car in which Thomas W. Williams and Jimmy Don Williams, brothers, and Robert Joe Gillaspy were passengers, failed to stop at a stop sign at the intersection of County Roads 47 and 48, proceeded the wrong way down County Road 47, and collided head-on with another car driven by Bruce G. Lapean. The accident killed Thomas W. Williams and Robert Joe Gillaspy and seriously injured Jimmy Don Williams. Harris had driven through the intersection several times before the day of the accident.

County Roads 47 and 48 are preexisting roadways and the design of the intersection did not change when it became part of the detour route although it is undisputed that the Highway 55 detour caused an increase in traffic on County Road 48. Three markers (also preexisting) warned drivers on County Road 48 of the upcoming intersection with County Road 47: a stop sign, the words “STOP AHEAD” on the road itself, and a double yellow center line. Although the intersection had no new warning devices, Bruce Zeien, a Warning Lites driver, testified that he inspected the entire detour route to see that Warning Lites’ traffic control devices were in place. He stated that he also checked for the overall effectiveness of the detour route and motorists’ reactions.

The Williamses and Bishop brought this wrongful death and personal injury action against the State of Minnesota, Shafer, and Harris (the Williamses also sued Dakota County in their amended complaint). Shafer brought third-party claims against Warning Lites, and Warning Lites was later added as a direct defendant. The claimants essentially allege that the intersection was unreasonably dangerous due to negligent design and inadequate supervision of its safe operation. The district court entered summary judgment for Shafer and Warning Lites on these *867 claims, finding that their duty did not extend to inspecting or safely designing the detour route. The court, however, denied summary judgment on the additional claim that Warning Lites assumed a duty by voluntarily inspecting the detour route.

ISSUES

I. Did Shafer and Warning Lites have a contractual or common law duty to provide for the safety of an intersection on a detour route outside the construction zone?

II. Did the district court err in denying summary judgment on the voluntary assumption-of-duty claim?

ANALYSIS

I

The claimants in this litigation allege that Shafer, as the construction contractor, had a contractual duty, and a common law duty that arises in part from the contract, to provide for the safety of an intersection that is part of a detour route. Shafer and Warning Lites argue that summary judgment was properly entered because the unambiguous contract neither imposes such a duty nor provides a basis on which a common law duty can be claimed.

Whether a contract is ambiguous is a legal rather than a factual question. Lamb Plumbing & Heating v. Kraus-Anderson of Minneapolis, 296 N.W.2d 859, 862 (Minn.1980). A contract is ambiguous if its terms are susceptible of more than one meaning. Id. If the terms are unambiguous, the court must determine the parties’ intent solely from its written content. Metropolitan Sports Facilities Comm’n v. General Mills, 470 N.W.2d 118, 123 (Minn.1991).

The contract, in a standard specification, states that the contractor shall provide for the safety of the general public. This standard specification is limited, however, by other contract terms. One such limitation is a provision distinguishing between the construction zone and the detour route and providing that the state has responsibility to “maintain those detour roads which are established by the Commissioner” when the plan provides for closure to through traffic.

Another standard specification outlines MN/DOT’s responsibilities to “design, provide, install, maintain, and remove all necessary traffic control devices to control and guide traffic over detours provided for in the Contract.” This responsibility is consistent with a statutory reservation to the Commissioner of Transportation of exclusive authority for the placement and maintenance of traffic control devices on trunk highways. See Minn.Stat. § 169.06, subd. 2 (1992) (prohibiting placement or maintenance of traffic control devices on trunk highways unless permitted by the Commissioner). MN/DOT took jurisdiction over the county road when it established the detour route to take traffic off Trunk Highway 55.

The state delegated part of its authority to erect traffic control devices to Shafer, but specifically retained authority for the design of the detour route and specified the precise location of each traffic control device within the detour route. In a special provision, which the contract identifies as controlling over a standard specification, the contract delegates the “furnishing, installing, maintaining, and removing .the traffic control devices * * * as shown in the Traffic Control sheets of the Plans.” Shafer contracted with Warning Lites to fulfill these duties. This limited delegation of authority does not contractually reallocate the state’s authority and responsibility for the design of the detour route and the location of the traffic control devices.

Because the contract provisions retain the state’s authority to design the route, Shafer has no contractual duty to provide for the inspection and safe design of the detour route.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiley v. Fleet Farm LLC
D. Minnesota, 2025
Shank v. Carleton College
232 F. Supp. 3d 1100 (D. Minnesota, 2017)
Ironwood Springs Christian Ranch, Inc. v. Emmaus
801 N.W.2d 193 (Court of Appeals of Minnesota, 2011)
Nickelson v. Mall of America Co.
593 N.W.2d 723 (Court of Appeals of Minnesota, 1999)
Atkins v. GE Capital Mortgage Services, Inc.
993 F. Supp. 1406 (M.D. Alabama, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
518 N.W.2d 864, 1994 Minn. App. LEXIS 618, 1994 WL 314764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-harris-minnctapp-1994.