Instrumentation Services, Inc. v. General Resource Corp.

283 N.W.2d 902, 1979 Minn. LEXIS 1658
CourtSupreme Court of Minnesota
DecidedAugust 17, 1979
Docket48552
StatusPublished
Cited by11 cases

This text of 283 N.W.2d 902 (Instrumentation Services, Inc. v. General Resource Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Instrumentation Services, Inc. v. General Resource Corp., 283 N.W.2d 902, 1979 Minn. LEXIS 1658 (Mich. 1979).

Opinion

PETERSON, Justice.

Plaintiff, Instrumentation Services, Inc. (ISI), sued defendant third-party plaintiff Fluidizer, Inc. 1 , to recover in full on a subcontract it had with Fluidizer to perform work on a pneumatic conveyor system that Fluidizer had agreed to build for Standard Dry Wall Products, Inc. Fluidizer counterclaimed and, in addition, asserted against third-party defendants Dynamic Air, Inc. (a Fluidizer competitor) and Durwood Schlee (a former Fluidizer employee employed by Dynamic Air) claims that illegal acts by ISI, Dynamic Air, and Schlee had deprived Fluidizer of its underlying contract with Standard and had enabled Dynamic Air to obtain the construction contract.

The court below, in a bench trial, in its initial order and memorandum dated November 8, 1977, held against Fluidizer and held that ISI was entitled to recover, on a quantum meruit basis, for the work it had performed. In its final order and memorandum, dated December 13, 1977, the trial court ruled that ISI was entitled to recover in full on the subcontract. Fluidizer appeals from judgment entered January 13, 1978, in favor of ISI, Dynamic Air, and Schlee. We affirm the trial court’s holding on Fluidizer’s counterclaim and amended third-party complaint. We reverse the trial court’s holding that ISI was entitled to recovery of the full price on the subcontract, since ISI only partially completed its performance; we remand with the direction that the trial court ascertain the amount of savings realized by ISI from nonperformance and deduct that amount from the contract price.

In January 1973, Donald Stearns, who resided in Florida and was under contract as Fluidizer’s sales representative, persuaded Standard, a corporation headquartered in Florida, to install a pneumatic conveyor at its proposed plant in Newark, California. Stearns sent Fluidizer a set of preliminary drawings that he had prepared for the conveyor system. 2 On March-27, 1973, Fluidizer transmitted to Stearns its formal proposal for the conveyor system in the sum of $258,077 for presentation to Standard. *905 Because the conveyor system required equipment and parts which had to be obtained by Pluidizer from others, inquiries were made to outside vendors, including ISI, for information and prices. ISI prepared a plan for the scaling and batching section of the conveyor system and presented its quotation to Fluidizer on March 23,1973. On June 5, Standard formally accepted the Pluidizer proposal with the understanding that Pluidizer, before it began manufacturing or installing the system, would submit engineering and design drawings to Standard for approval. Fluidizer issued its acknowledgment of acceptance to Standard on June 7. On July 24, 1973, Pluidizer issued a purchase order (subcontract) to ISI for engineering and design drawings of the electronic scaling and batching section of the conveyor system.

On or about July 1, 1973, Schlee was assigned as Fluidizer’s project engineer in connection with the Standard conveyor system. He was responsible for design, engineering, and cost evaluation of the system. Schlee completed approximately 90 percent of the engineering drawings for the proposed system. Effective November 2, 1973, Schlee discontinued his employment with Fluidizer and 3 days later became an employee of Dynamic Air.

Stearns telephoned Fluidizer on November 9, 1973, to express concern about the status of the conveyor system and to suggest ways to get the project moving. At about the same time, Fluidizer began to re-estimate the cost of the conveyor system. Fluidizer determined that it would have to obtain additional monies for its proposed system and that it would have to substantially increase the proposal price. In mid-November 1973, Fluidizer informed Stearns that it was re-evaluating its original proposal and that it expected to submit a new proposal at an elevated price. 3

Fluidizer prepared a new proposal, and a meeting was scheduled with Phil C. Donnelly, president of Standard. On December 17, 1973, Fluidizer submitted its new proposal to Standard and, according to Donnelly, stated that it was withdrawing its original March 27 proposal. Fluidizer’s counsel similarly admitted at oral argument that Fluid-izer had said it would not perform the contract for the amount originally proposed. The total amount of the December 17 proposal was $423,000 — $268,243 represented cost; $154,966 represented profit. This proposal covered more than Fluidizer’s increase in expenses since the March 1973 proposal (which limited price escalation to 3 percent) —it allowed Fluidizer a profit 58 percent greater than the profit figured in its original proposal. No one denies that Donnelly was upset by the increase.

Shortly after the meeting, Donnelly informed Stearns that he wanted another bid, and Dynamic Air was called upon to submit a bid. Earlier, sometime between mid-November and early December 1973, after learning of Fluidizer’s probable increase, Stearns had requested that Dynamic Air be prepared to submit a bid for the Standard conveyor system. Schlee participated with other employees of Dynamic Air in the preparation of a formal bid for Standard. In mid-December 1973, Dynamic Air asked ISI to prepare a plan as subcontractor for Dynamic Air’s proposal. While preparing its plan, ISI learned that Standard was the ultimate customer for both the Fluidizer and the Dynamic Air conveyor systems. ISI thereafter maintained separate and distinct files for each project. ISI submitted a quotation and plan to Dynamic Air on January 2, 1974. Dynamic Air submitted a proposal to Standard on January 5,1974, in the amount of $338,947. Standard accepted the proposal and issued a purchase order on January 18, 1974.

I. Fluidizer’s Counterclaim and Cross-Complaint

Fluidizer has presented several theories for its cause of action against ISI, *906 Dynamic Air, and Schlee. In its counterclaim and its amended third-party complaint, Fluidizer alleged that ISI was guilty of transferring confidential business information; that Dynamic Air and Schlee were guilty of conversion and of unfair competition by misuse of trade secrets; and that ISI, Dynamic Air, and Schlee were guilty of interference with a customer relationship. The trial court properly held against Fluid-izer on all of the theories. Findings of fact, made by the trial court and supported by the record, demonstrated that the information Schlee allegedly used in developing the Dynamic Air proposal was general information and did not constitute use of trade secrets; that Fluidizer failed to prove Schlee or Dynamic Air had material assistance other than their own training, skill, knowledge, and experience in developing the Dynamic Air proposal or that ISI had transferred confidential Fluidizer business information to Dynamic Air; and that Fluidizer’s loss of the contract for the Standard conveyor system resulted from unilateral repudiation of its original commitment. Fluidizer does not on this appeal contest the trial court’s rejection of these theories.

However, in post-trial memoranda, Fluid-izer presented still another theory: conspiracy in unfair competition among Schlee, Dynamic Air, Stearns, and presumably ISI.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.M. Silta, Inc. v. Cleveland Cliffs, Inc.
616 F.3d 872 (Eighth Circuit, 2010)
First Security Bank of Utah, N.A. v. Northwest Airlines, Inc.
43 F. Supp. 2d 136 (D. Massachusetts, 1999)
In Re Hennepin County 1986 Recycling Bond Litigation
540 N.W.2d 494 (Supreme Court of Minnesota, 1995)
Williams v. Harris
518 N.W.2d 864 (Court of Appeals of Minnesota, 1994)
Zobel & Dahl Construction v. Crotty
356 N.W.2d 42 (Supreme Court of Minnesota, 1984)
RJM Sales & Marketing, Inc. v. Banfi Products Corp.
546 F. Supp. 1368 (D. Minnesota, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
283 N.W.2d 902, 1979 Minn. LEXIS 1658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/instrumentation-services-inc-v-general-resource-corp-minn-1979.