JONES EXCAVAT. CONTRACTOR v. Firemen's Ins.
This text of 920 S.W.2d 483 (JONES EXCAVAT. CONTRACTOR v. Firemen's Ins.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
R.J. "BOB" JONES EXCAVATING CONTRACTOR, INC., Appellant,
v.
FIREMEN'S INSURANCE COMPANY OF NEWARK, NEW JERSEY, Appellee.
Supreme Court of Arkansas.
*484 Stanley D. Rauls, Little Rock, for appellant.
Clark Mason, Little Rock, Michelle I. Rieger and Elmer A. Johnston, Dallas, Texas, for appellee.
CORBIN, Justice.
Appellant, R.J. "Bob" Jones Excavating Contractor, Inc., (hereinafter "Jones") appeals the order of the Pulaski County Circuit Court granting summary judgment to appellee, Firemen's Insurance Company of Newark, New Jersey, (hereinafter "Firemen's") on appellant's complaint for nonpayment under a statutory payment bond pursuant to Ark.Code Ann. § 23-79-208 (Repl.1992) and for the tort of bad faith. This case requires statutory interpretation and presents a question about the law of torts; jurisdiction is properly in this court pursuant to Ark.Sup. Ct.R. 1-2(a)(3) and (16). Jones raises two points for reversal of the summary judgment. We find no merit and affirm.
PROCEDURAL HISTORY WITH BACKGROUND FACTS
Jones filed this suit against Firemen's seeking to recover on a payment bond issued by Firemen's as surety to Lawrence Brothers *485 Incorporated, (hereinafter "Lawrence Brothers") as principal and general contractor on Arkansas Highway Department Project No. 60447. Lawrence Brothers was to construct several bridges and appurtenances along Highways 46 and 222 in Grant County, Arkansas. Jones subcontracted with Lawrence Brothers to do the excavation work on the project.
A dispute arose between Lawrence Brothers and Jones over Jones's completion of the subcontract and Lawrence Brothers declared Jones in default. Jones sued Lawrence Brothers for breach of contract and Lawrence Brothers counterclaimed for breach as well. A jury found both appellant and Lawrence Brothers in breach, but awarded damages only to appellant. Appellant won damages in the amount of $110,115.50 plus $46,891.97 in costs. This court dismissed Lawrence Brothers's appeal of the jury verdict for lack of jurisdiction due to an untimely notice of appeal. Lawrence Bros., Inc. v. R.J. "Bob" Jones Excavating Contractor, Inc., 318 Ark. 328, 884 S.W.2d 620 (1994). Lawrence Brothers satisfied the judgment two days after we dismissed its appeal. Firemen's was not a party to the suit between Lawrence Brothers and Jones.
Jones demanded payment under the bond from Firemen's both prior to and after filing this suit against Lawrence Brothers and again after judgment was entered in that suit. Two days before Lawrence Brothers satisfied the judgment, Jones amended its complaint against Firemen's in this case to include a claim for the tort of bad faith.
The trial court granted Firemen's motion for summary judgment in an order without explanation. At the hearing on the motion, however, the trial court stated that Firemen's was entitled to judgment on both claims because Jones did not recover twenty percent of the amount demanded or sought in the suit as required by section 23-79-208(d) and because the tort of bad faith did not apply to a surety and had not been shown in this case.
STANDARD OF REVIEW
The standard for appellate review of a summary judgment is whether the evidentiary items presented by the moving party in support of the motion left a question of material fact unanswered and, if not, whether the moving party is entitled to judgment as a matter of law. Baker v. Milam, 321 Ark. 234, 900 S.W.2d 209 (1995). This court views all proof in the light most favorable to the party opposing the motion, resolving all doubts and inferences against the moving party. Id. However, when the movant makes a prima facie showing of entitlement to summary judgment, the respondent must meet that proof with proof showing a genuine issue as to a material fact. Id.
CLAIM FOR PAYMENT UNDER THE BOND
Jones's first point for reversal relates to the claim for payment under the bond. Jones makes two arguments under this point. First, Jones contends the trial court erred in ruling that Lawrence Brothers's payment of the underlying debt after Jones's appeal was dismissed against Lawrence Brothers extinguished Jones's cause of action under section 23-79-208. We need not address whether such a ruling was in error because there was no such ruling by the trial court in this case. The order entered in this case grants summary judgment to appellee without explanation. Although Firemen's pleaded Lawrence Brothers's payment as an affirmative defense in its answer, the record of the hearing on the motion for summary judgment does not reveal that the effect of the principal's payment of the underlying debt on the surety's liability was ever discussed or served as a basis for the trial court's ruling. This court does not review matters that were not ruled upon below. Technical Servs. of Arkansas, Inc. v. Pledger, 320 Ark. 333, 896 S.W.2d 433 (1995).
Second, Jones contends that Firemen's admitted all essential elements to establish appellant's recovery of the statutory penalty, interest, and attorneys' fees under section 23-79-208, thus the trial court erred in granting summary judgment to Firemen's. Specifically, Jones argues the trial court erred in ruling that recovery under section 23-79-208 was not allowed because Jones did not recover within twenty percent of the *486 amount demanded as required by section 23-79-208(d). Subsection (d) was added to section 23-79-208 in 1991 and provides as follows:
XX-XX-XXX. Damages and attorney's fees on loss claims.
(a) In all cases where loss occurs and the ... surety ... liable therefor shall fail to pay the losses within the time specified in the policy, after demand made therefor, the person, firm, corporation, or association shall be liable to pay the holder of the policy or his assigns, in addition to the amount of the loss, twelve percent (12%) damages upon the amount of the loss, together with all reasonable attorneys' fees for the prosecution and collection of the loss.
. . . .
(d) Recovery of less than the amount demanded by the person entitled to recover under the policy shall not defeat the right to the twelve percent (12%) damages and attorneys' fees provided for in this section if the amount recovered for the loss is within twenty percent (20%) of the amount demanded or which is sought in the suit. [Emphasis ours.]
Firemen's contends that Jones was required to recover within twenty percent of the amount demanded of Firemen's or the amount sought in the suit against Lawrence Brothers. This contention arises as a result of the peculiar facts of this casespecifically, that Jones did not join Firemen's as a party defendant in the suit against Lawrence Brothers and that Jones made four demands for payment from Firemen's, the amounts of which decreased chronologically as follows: $368,118.21, $311,808.51, $280,000.00, and $110,115.50. Firemen's points out that the only demand that would satisfy the requirements of XX-XX-XXX(d) is the final one, which represents the amount of the judgment against Lawrence Brothers. Jones cites Armco Steel Corp. v. Ford Constr. Co., 237 Ark. 272, 372 S.W.2d 630
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
920 S.W.2d 483, 324 Ark. 282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-excavat-contractor-v-firemens-ins-ark-1996.