Armco Steel Corp. v. Ford Construction Co.

372 S.W.2d 630, 237 Ark. 272, 1963 Ark. LEXIS 530
CourtSupreme Court of Arkansas
DecidedNovember 26, 1963
Docket5-3125
StatusPublished
Cited by7 cases

This text of 372 S.W.2d 630 (Armco Steel Corp. v. Ford Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armco Steel Corp. v. Ford Construction Co., 372 S.W.2d 630, 237 Ark. 272, 1963 Ark. LEXIS 530 (Ark. 1963).

Opinion

Paul Ward, Associate Justice.

In August, 1960 the El Dorado Waterworks and Sewer Commission let a contract to the Ford Construction Company to construct a sanitary sewerage plant at a total cost of $204,468. Pursuant to Ark. Stat. Ann. § 14-604 (Repl. 1956) the construction company furnished a bond with United States Fidelity and Guaranty Company. Hereafter the latter will be referred to as U. S. F. & G. The construction company will be referred to as Ford, and the Commission will be referred to as El Dorado.

El Dorado employed Mas Mehlburger and Associates, engineers of Little Rock to prepare plans and specifications for the proposed sewerage plant. Said plans and specifications were completed prior to June 12,1960. On that date the Armco Steel Corporation (hereafter called Armco), domiciled in Ohio, purchased two sets of said plans and specifications preparatory to selling Ford certain piping and equipment to be used in constructing said sewerage plant. Later Ford and Armco entered into a contract (or purchase order) wherein the latter agreed to furnish certain definitely described articles for the price of $37,195.33. Included in these articles Avas a sizeable quantity of 21 inch metal piping. The 21 inch pipe Avas to be laid or buried in a levee betAveen tAvo lagoons. This litigation stems from disagreements in some Avay connected Avith a portion of this 21 inch piping.

Summarily stated, here is Iioav the disagreements arose. Work began on the project in the early part of 1961, and by mid-September 1961 some of the 21 inch pipe had been laid in the levee. In early October 1961 tests made by Ford revealed leaks had developed in about 25 joints. Later, inspections Avere made by different parties but no Avay Avas found to stop the leaks, and on December 30, 1961 Mehlburger and El Dorado ordered Ford to remove the pipe and replace it with other piping.

In an attempt to adjust matters between Ford and Armco, the latter offered to take back the rejected pipe and cancel the balance of $5,955.78 OAved by Ford. Upon Ford’s refusal to accept this offer of settlement, renewed efforts to reach a settlement AAdthout resorting to court action were made over a period of several months. Again, no settlement was reached and this litigation followed. Armco sued Ford (and U. S. F. & G) for the balance due on merchandise ordered and delivered, and Ford counter-claimed for alleged damages.

For clarity and convenience we, at this point, divide our discussion into two separate parts, based upon the above pleadings. One: Armco recovered a judgment against Ford and U. S. F. & Cl. for the balance due on merchandise. The trial court refused to allow Armco statutory penalty and attorney’s fee, and this is urged to be reversible error. Tioo: Ford recovered a judgment against Armco (on the cross complaint) for damages allegedly resulting from Armco’s breach of warranty.

One. Penalty ancl Attorney’s Fee. Armco alleged Ford owed a balance of $5,955.78 on account, Ford admitted signing the purchase order but denied the materials were delivered and accepted. Ford also claimed a credit of $1,778.19 for pipe returned and $230 for another item. Armco filed a reply, conceding the above named credits, leaving a balance of $3,947.59. Thereupon, when appellees offered to confess judgment for the above amount the court instructed the jury to return a verdict for Armco against Ford and IT. S. F. & G. for $3,947.59. Armco then moved the court to assess the statutory 12% penalty and attorney’s fee against U. S. F. & G. under the provisions of Ark. Stat. Ann. § 66-3238 (Supp. 1961). The motion was denied by the trial court. This action, by the trial court is here assigned as error. ■' : ..."

We do not agree with appellant. As pointed out above, as soon as Armco reduced its claim to. the correct amount Ford and U. S. F. & G. promptly confessed judgment for that amount. In the Great So. F. Ins. Co. v. Burns & Billington, 118 Ark. 22, 31, 175 S. W. 1161, the plaintiff amended its complaint to reduce its claim but the insurance company did not then confess judgment but went to trial. The judgment was for the amended amount, and we held the penalty attached. This Court,however, made the following announcement which is decisive against Armco:. <

‘ ‘ If the insurance company had desired to avoid the penalty and attorneys’ fee provided for by the statute, it should have offered to confess judgment for the amount sued for in the amended complaint. ’ ’

Although the above quote may be classified as dictum, yet it is a clear statement of the rule consistently followed by the court.- See: National Fire Insurance Company v. Kight, 185 Ark. 386, 47 S. W. 2d 576; Broadway v. The Home Insurance Co., 203 Ark. 126, 155 S. W. 2d 889. The first case construed C. & M. Digest § 6155 and the latter case construed Pope’s Digest § 7670, both sections being the same as Ark.- -Stat. Ann. § 66-3238 (Supp. 1961) the section relied on here by appellant.

We conclude, therefore, that the trial court correctly refused to assess the statutory 12% penalty and attorney’s fee.

. Two. Da/inages. In connection with appellee’s answer to Armco’s complaint, Ford alleged a counter-claim against Armco in the amount of $38,176.03. Ford’s claim was based on four counts: (1) breach of contract, (2) breach of warranty, (3) negligence, and (4) fraud. Generally speaking, all counts were based on the contention by Ford that the materials furnished by Armco failed to meet required specifications. After denying :>all four counts, Armco affirmatively pleaded the following provision in the purchase contract:

“There are no understandings, terms or conditions not fully expressed herein. There is no implied warranty or condition except an implied warranty of title to and freedom from encumbrance of the products sold hereunder and in respect of products bought by description that they are of merchantable quality. Seller’s liability hereunder shall be limited to the obligation to replace material proven to have been defective in quality of workmanship at the time of delivery, or allow credit therefor at its option. In no event shall Seller be liable for consequential damages or for claims for labor.”

On appeal, appellant urges three separate grounds for a reversal. A. The trial court erred in refusing, to direct a verdict. B. Error in giving a certain instruction on measure of damages. G. Error in refusing a certain instruction. After a lengthy trial, the jury returned a verdict in favor of Ford in the amount of $26,176.03 on the first three counts, the last count (on fraud) was abandoned by Ford.

A. Appellant’s contention that the trial court erred in refusing to direct a verdict in its favor at the close of all the testimony is based principally on a question of law which is ably and exhaustively argued in its brief. In this argument no stress is placed on the sufficiency or insufficiency of the evidence. In our discussion hereafter, and without expressing any opinion as to the merits of the other two counts, we consider only the second count which is based on an implied warranty. Referring back to section “6” of the purchase order copied above, it appears clear to us that it contains an implied warranty on the part of Armco. The pertinent language-is:

‘ ‘ There is no implied warranty . ..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JONES EXCAVAT. CONTRACTOR v. Firemen's Ins.
920 S.W.2d 483 (Supreme Court of Arkansas, 1996)
W. William Graham, Inc. v. City of Cave City
709 S.W.2d 94 (Supreme Court of Arkansas, 1986)
Miller's Mutual Insurance v. Keith Smith Co.
680 S.W.2d 102 (Supreme Court of Arkansas, 1984)
Smith v. Beall
451 S.W.2d 195 (Supreme Court of Arkansas, 1970)
United States ex rel. Peevy v. Pensacola Construction Co.
257 F. Supp. 131 (W.D. Arkansas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
372 S.W.2d 630, 237 Ark. 272, 1963 Ark. LEXIS 530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armco-steel-corp-v-ford-construction-co-ark-1963.