Beal Bank Nevada v. NorthShore Center THC, LLC

2016 IL App (1st) 151697, 64 N.E.3d 201
CourtAppellate Court of Illinois
DecidedSeptember 30, 2016
Docket1-15-1697
StatusUnpublished
Cited by1 cases

This text of 2016 IL App (1st) 151697 (Beal Bank Nevada v. NorthShore Center THC, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beal Bank Nevada v. NorthShore Center THC, LLC, 2016 IL App (1st) 151697, 64 N.E.3d 201 (Ill. Ct. App. 2016).

Opinion

2016 IL App (1st) 151697

FIFTH DIVISION September 30, 2016

No. 1-15-1697

) BEAL BANK NEVADA, ) ) Appeal from the Plaintiff, ) Circuit Court of ) Cook County v. ) ) NORTHSHORE CENTER THC, LLC, et al., ) ) Defendants. ) ) No. 08 CH 39446 ) LAKE COUNTY GRADING COMPANY, LLC, ) ) Counterplaintiff-Appellant, ) ) v. ) Honorable ) Anthony C. Kyriakopoulos, FCL INVESTORS, INC., formerly known as ) Judge Presiding. FCL BUILDERS, INC., ) ) Counterdefendant-Appellee. )

JUSTICE REYES delivered the judgment of the court, with opinion. Presiding Justice Gordon and Justice Lampkin concurred in the judgment and opinion.

OPINION

¶1 This appeal addresses the issue of whether a contractor is liable for amounts due to a

subcontractor if the property owner fails to make payment to the contractor for the

subcontractor's work. The circuit court of Cook County granted summary judgment in favor of

contractor FCL Investors, Inc., formerly known as FCL Builders, Inc. (Contractor), and against 1-15-1697

subcontractor Lake County Grading Company, LLC (Subcontractor) on the Subcontractor's

breach of contract claim. Applying A.A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp., 132

Ill. App. 3d 325 (1985) (Conte), the circuit court found that the provisions of the parties'

subcontract "clearly make the receipt of payment from the [property owner] to [the Contractor],

the condition precedent to [the Subcontractor's] payment." The circuit court concluded that the

condition precedent has not been satisfied because the Contractor has not received payment from

the property owner. As discussed below, we reverse the judgment of the circuit court.

¶2 BACKGROUND

¶3 As the circuit court proceedings were lengthy and complex, we provide only the facts

necessary for the disposition of this appeal. In 2006, Northshore Center THC, LLC (Owner)

borrowed funds from BankFirst, secured by notes and a mortgage, to develop real estate in

Northbrook, Illinois. The Owner and the Contractor entered into a contract (contract), for the

Contractor to perform certain construction work at the Northbrook site. The Contractor and

Subcontractor entered into a subcontract (subcontract), for the Subcontractor to provide

excavation, sewer line installation and other construction services.

¶4 After performing a portion of its work under the subcontract, the Subcontractor issued an

invoice to the Contractor for $130,343.40; the said amount was tendered by the Owner. The

Subcontractor subsequently issued additional invoices and payment requests to the Contractor

for additional amounts totaling $775,872.60 for work performed under the subcontract.

Although the Contractor submitted the invoices for payment to the Owner, the requests were

refused and the Owner failed to pay. The Subcontractor recorded a subcontractor's claim for lien

against the Contractor and the Owner on February 4, 2008, in the amount of $775,872.60. The

Contractor recorded a contractor's claim for lien on November 26, 2008, claiming an outstanding

2 1-15-1697

balance of $943,494.53 – which included the amount due to the Subcontractor.

¶5 BankFirst filed a foreclosure complaint against the Owner in the circuit court of Cook

County in October 2008. The complaint also named various parties with interests in the

mortgaged real estate as defendants, including the Contractor and the Subcontractor. The

Subcontractor filed an answer and a counter-complaint, which included a breach of contract

claim against the Contractor. The affirmative defense asserted by the Contractor was basically

that the subcontract provides that payment by the Owner to the Subcontractor is a condition

precedent to any obligation by the Contractor to pay the Subcontractor. In response, the

Subcontractor argued that the Contractor's affirmative defense is prohibited by section 21(e) of

the Mechanics Lien Act (770 ILCS 60/21(e) (West 2008)), discussed below.

¶6 Beal Bank Nevada (bank) – substituted as plaintiff for BankFirst – filed a second

amended complaint in November 2009. In March 2011, the Subcontractor and the bank entered

into a settlement agreement wherein the Subcontractor agreed to release its mechanics lien in

exchange for $475,000. As a result of the settlement, the principal balance sought by the

Subcontractor was reduced to $300,872.60. The Contractor subsequently secured a judgment

against the Owner in the amount of $943,494.53. By that time, however, the Owner had ceased

its operations and had been involuntarily dissolved. Although the Contractor's counsel later

transmitted an "assignment" of its judgment against the Owner to the Subcontractor's counsel, a

stipulation in the record indicates that "[the Subcontractor] did not request and did not agree to

take assignment of [the Contractor's] judgment against the Owner."

¶7 In June 2011, the court entered a judgment of foreclosure and sale with respect to the

Northbrook property in favor of the bank. On the bank's motion, the court subsequently

amended the judgment to reflect that the Contractor's liens – recorded more than four months

3 1-15-1697

after the completion of work – were subordinate and inferior to the bank's mortgage.

¶8 In November 2013, the Contractor and the Subcontractor filed cross-motions for

summary judgment. The Subcontractor's motion acknowledged that the parties had filed prior

cross-motions for summary judgment, that the court previously found that certain questions of

fact precluded judgment on the sole remaining count – breach of contract (Count III) – of the

Subcontractor's counter-complaint, and that the parties had since engaged in substantial

discovery and entered into stipulations in an effort to eliminate any material question of fact.

¶9 The circuit court subsequently entered an order denying the Subcontractor's motion for

summary judgment and granting the Contractor's motion for summary judgment. The court

rejected the Subcontractor's contention that the Contractor was "barred from bringing the

condition precedent as a contractual defense due to the alleged representations and warranties

breached by [the Contractor]," i.e., an alleged statement from the Contractor's representative to

the Subcontractor's representative that funding had already been secured from the Owner. The

court determined that the Contractor's "failure to confirm [the Owner's] funds before allowing

[the Subcontractor] to begin performance" could not be considered a breach "as there is nothing

in the four corners of the contract making [the Contractor's] confirmation of funds a term or part

of performance."

¶ 10 After quoting portions of sections 5.1 and 5.2 of the subcontract, the court further found

that Conte "is controlling on the instant case," noting that the "payment provision in the

subcontract" in Conte was "nearly identical to the provision in the Subcontract at issue in the

case at bar." Sections 5.1 and 5.2 provide in part:

"[5.1] Provided Subcontractor's rate of progress and general performance

are satisfactory to the Contractor, and provided that the Subcontractor is in full

4 1-15-1697

compliance with each and every provision of the Subcontract Documents, the

Contractor will make partial payments to the Subcontractor in an amount equal to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Estate of Kramer
2026 IL App (2d) 250277-U (Appellate Court of Illinois, 2026)
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2016 IL App (1st) 151697, 64 N.E.3d 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beal-bank-nevada-v-northshore-center-thc-llc-illappct-2016.