Lemoine Co. of Alabama v. HLH Constructors, Inc.

62 So. 3d 1020, 2010 Ala. LEXIS 215, 2010 WL 4679478
CourtSupreme Court of Alabama
DecidedNovember 19, 2010
Docket1090847
StatusPublished
Cited by24 cases

This text of 62 So. 3d 1020 (Lemoine Co. of Alabama v. HLH Constructors, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lemoine Co. of Alabama v. HLH Constructors, Inc., 62 So. 3d 1020, 2010 Ala. LEXIS 215, 2010 WL 4679478 (Ala. 2010).

Opinion

WOODALL, Justice.

The Lemoine Company of Alabama, L.L.C. (“Lemoine”), subcontracted with HLH Constructors, Inc. (“HLH”), for HLH to perform plumbing work on a construction project. HLH subsequently sued Lemoine, alleging, among other things, that Lemoine had not paid HLH the balance due under the subcontract. The trial court entered a judgment in HLH’s favor, awarding damages, interest, and attorney fees. We reverse and remand.

Facts and Procedural History

Vista Bella, Inc., and Lemoine entered into a contract, by which Lemoine agreed to act as general contractor on a condominium-construction project in Baldwin County (“the project”). Lemoine subcontracted the plumbing work for the project to HLHÍ

During the course of construction, and pursuant to the terms of the general contract, Vista Bella withheld a 5% retainage 1 on the work performed. Each month, Lemoine sent Vista Bella an application for payment, in which Lemoine set forth details regarding, among other things, the value of the work completed during the month and the amount of the retainage withheld with respect to that work.

Also during the course of construction, and pursuant to the terms of its subcontract with HLH, 2 Lemoine withheld a 5% *1023 retainage with respect to HLH’s work on the project. HLH sent monthly applications for payment to Lemoine. These applications, like the applications sent by Lemoine to Vista Bella, indicated the value of the work HLH had performed during the month and the retainage withheld with respect to that work.

On July 3, 2007, a certificate of completion was issued for the project. On July 12, 2007, Lemoine billed Vista Bella for the retainage that had been withheld during construction. Vista Bella never paid the retainage. It appears that Vista Bella has paid Lemoine all amounts owed under the general contract, except for the retainage. Lemoine sued Vista Bella to recover the unpaid balance. Vista Bella failed to appear, and the trial court entered a default judgment in Lemoine’s favor, awarding Lemoine $1,438,066.35 in damages, plus interest and costs. Lemoine states that, as of the date of trial in this case, Lemoine had not collected from Vista Bella any portion of the default judgment.

After the completion of the project, HLH sent Lemoine an application for payment of the balance outstanding under the subcontract. 3 Lemoine did not pay that bill; instead, it tendered to HLH a check for $1,500. Lemoine argues that the check was intended as a payment on the monthly application, not as a final payment for the retainage under the subcontract. HLH refused the check and requested payment of the entire outstanding balance. Lem-oine has not made any further payment under the subcontract. Lemoine states that “[t]he parties do not dispute that Lemoine made all payments required by the subcontract to HLH except for the final retainage payment and payment for disputed extra work.” Lemoine’s brief, at 43. HLH makes no argument to the contrary.

In April 2008, HLH sued Lemoine and Vista Bella, alleging breach of contract and stating claims for “work and labor done and materials provided, open account, stated account, and under [§] 8-29-1, [Ala. Code 1975].” HLH’s brief, at 9. HLH also sought to enforce a materialman’s lien against Vista Bella.

Lemoine denied HLH’s allegations and moved the trial court to “transfer HLH’s materialman’s lien against Vista Bella to a bond in the amount of $117,827.62 pursuant to [Ala.Code 1975,] § 35-11 — 233(b). ... The trial court granted the motion.” Lemoine’s brief, at 2-3.

*1024 In December 2009, the case was tried without a jury. On HLH’s motion, the trial court entered a default judgment against Vista Bella. On February 5, 2010, the trial court entered a judgment against Lemoine, stating:

“This case came for trial on 12/16/09; and the court, having heard the testimony of the witnesses; having reviewed the evidence and having considered the briefs of the parties, hereby enters judgment for [HLH] and against [Lemoine and Vista Bella] for the sum of $138,283.36, including principal of $90,102.95, interest of $25,228.82, and attorneys fees of $22,951.59. [Lemoine and Vista Bella] are taxed with the costs of court.” 4

Lemoine now appeals that judgment.

Issues

On appeal, Lemoine raises three issues: (1) whether Vista Bella’s payment to Lem-oine of the balance owed under the general contract was a condition precedent to Lemoine’s obligation to pay HLH the balance owed under the subcontract; (2) whether the trial court erred in determining that the unpaid balance due from Lem-oine to HLH under the subcontract was $90,102.95; and (3) whether the trial court erred in awarding HLH attorney fees and 12% interest pursuant to § 8-29-1 et seq., Ala. Code 1975.

Standard of Review

“When evidence is taken ore ten-us and the trial judge makes no express findings of fact, this Court will assume that the trial judge made those findings necessary to support the judgment. Transamerica Commercial Fin. Corp. v. AmSouth Bank, N.A., 608 So.2d 375, 378 (Ala.1992) (citing Fitzner Pontiac-Buick-Cadillac, Inc. v. Perkins & As- *1025 socs. Inc., 578 So.2d 1061 (Ala.1991)). We will not disturb the findings of the trial court unless those findings are ‘clearly erroneous, without supporting evidence, manifestly unjust, or against the great weight of the evidence.’ Gaston v. Ames, 514 So.2d 877, 878 (Ala.1987) (citing Cougar Mining Co. v. Mineral Land & Mining Consultants, Inc., 392 So.2d 1177 (Ala.1981)). ...
“ ‘However, the ore tenus standard of review has no application to a trial court’s conclusions of law or its application of law to the facts; a trial court’s ruling on a question of law carries no presumption of correctness on appeal.’ Ex parte J.E., 1 So.3d [1002,] 1008 [ (Ala.2008) ].... This Court “‘review[s] the trial court’s conclusions of law and its application of law to the facts under the de novo standard of review.” ’ Id. (quoting Washington v. State, 922 So.2d 145, 158 (Ala.Crim.App.2005)).”

Espinoza v. Rudolph, 46 So.3d 403, 412 (Ala.2010).

Analysis

Lemoine first argues that, “[p]ursuant to paragraph 5 of the subcontract, Vista Bella’s payment to Lemoine of the unpaid balance due under the general contract was a condition precedent[ 5 ]to Lemoine’s obligation to pay HLH the unpaid balance under the subcontract.” Lemoine’s brief, at 25. “ ‘[I]t is well-established that condition precedents are not favored in contract law, and will not be upheld unless there is clear language to support them.’ ” Federal Ins. Co. v. I. Kruger, Inc., 829 So.2d 732, 740 (Ala.2002) (quoting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HC&D, LLC v. DCK Pacific Construction, LLC.
529 P.3d 691 (Hawaii Intermediate Court of Appeals, 2023)
Prince v. Hui Huliau
N.D. Alabama, 2022
Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)
Beal Bank Nevada v. NorthShore Center THC, LLC
2016 IL App (1st) 151697 (Appellate Court of Illinois, 2016)
Boyington v. Bryan
174 So. 3d 347 (Court of Civil Appeals of Alabama, 2014)
CAM Investments, LLC v. Totty
128 So. 3d 749 (Court of Civil Appeals of Alabama, 2013)
Stitt v. Citibank, N.A.
942 F. Supp. 2d 944 (N.D. California, 2013)
Nationwide Mutual Insurance Co. v. Wood
121 So. 3d 982 (Supreme Court of Alabama, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
62 So. 3d 1020, 2010 Ala. LEXIS 215, 2010 WL 4679478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lemoine-co-of-alabama-v-hlh-constructors-inc-ala-2010.