Glencoe Education Foundation, Inc. v. Clerk of Court & Recorder of Mortgages for the Parish of St. Mary

65 So. 3d 225, 2010 La.App. 1 Cir. 1872, 2011 La. App. LEXIS 626, 2011 WL 1878788
CourtLouisiana Court of Appeal
DecidedMay 6, 2011
DocketNo. 2010 CA 1872
StatusPublished
Cited by7 cases

This text of 65 So. 3d 225 (Glencoe Education Foundation, Inc. v. Clerk of Court & Recorder of Mortgages for the Parish of St. Mary) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glencoe Education Foundation, Inc. v. Clerk of Court & Recorder of Mortgages for the Parish of St. Mary, 65 So. 3d 225, 2010 La.App. 1 Cir. 1872, 2011 La. App. LEXIS 626, 2011 WL 1878788 (La. Ct. App. 2011).

Opinion

WELCH, J.

13Appellants, Lamar Contractors, Inc. (Lamar) and Hartford Casualty Insurance Company (Hartford), appeal a judgment [227]*227entered against Hartford awarding subcontractors Mayeux’s Air Conditioning & Heating, Inc. (Mayeux’s) and Brown Drywall and Coating, Inc. (Brown) the principal amounts of their claims and attorney fees, as well as the assessment of all costs of the concursus proceeding to Hartford. We affirm in all respects.

BACKGROUND

The facts forming the basis for this lawsuit are essentially undisputed. On January 29, 2007, Glencoe Education Foundation, Inc. d/b/a Virgil Brown Glencoe Charter School (Glencoe) entered into a contract with Lamar for the construction of a new building at its charter school in Franklin, Louisiana (sometimes referred to as “the project”). The construction contract was recorded with the clerk of court for St. Mary Parish on March 9, 2007. Hartford issued two bonds on the project to Lamar, a performance bond securing Lamar’s performance, and a payment bond, securing payment to all persons, firms, and corporations furnishing labor or materials on the construction project. Each of the bonds was issued in the amount of $3,178,000.00.

On February 2, 2007, Lamar entered into a written subcontract with Brown to furnish all materials and labor to install a complete painting system on the project for the lump sum price of $124,420.00. Lamar entered into a written subcontract with Mayeux’s to provide all materials and labor to install a complete HVAC system for the lump sum price of $214,827.00.

Brown’s and Mayeux’s satisfactory performance of their contractual duties on the construction project is not disputed. During the course of the project, however, disputes between Glencoe and Lamar arose over the work. Glencoe withheld payment of the remaining balance owed to Lamar and on July 23, 2008, |.¡Glencoe filed and recorded a notice of termination of the contract. In response, on September 16, 2008, Lamar filed a lien and statement of claim against Glencoe in the mortgage records for the sum of $380,850.19, representing the balance claimed to be due for general contract services and labor provided. Various subcontractors on the project also filed statements of claim and privilege into the mortgage records. On August 20, 2008, Brown filed a statement of claim or privilege against Lamar, Glencoe, and Hartford in the amount of $52,339.73, the balance it claimed was due for materials and services. On September 8, 2008, May-eux’s filed a statement of claim against Lamar, Glencoe, and Hartford for the sum of $30,420.00, representing the balance due for finished work on the project. The Sherwin-Williams Company, which provided materials to Brown on the project, also filed a statement of claim or privilege against Brown, Glencoe, Lamar, and Hartford in the amount of $4,937.46, the balance claimed for materials and services furnished on the project.

On October 1, 2008, Lamar filed a lawsuit seeking damages for breach of contract against Glencoe in the 16th Judicial Court. On October 3, 2008, Glencoe filed this concursus proceeding in that same court against Lamar, Brown, Mayeux’s, Sherwin-Williams, and two other subcontractors, Chuckleberry’s Commercial Floors, Inc. and Premier Steel Fabrication & Construction, LLC, seeking cancellation of their recorded claims from the mortgage records on the basis that there was a payment bond in effect for the project. Glencoe requested that all defendants be ordered to appear and reserve their claims to the payment bond, that it be deemed to be relieved of all liability to all claimants, and that the clerk of court be ordered to cancel all recorded claims.

[228]*228In the concursus proceeding, in October of 2008, Brown filed a claim against the payment bond, alleging that amicable demand for payment had been made on the principal and surety without payment being made, and that pursuant to [Sits properly recorded claim and La. R.S. 38:2246, it is entitled to an award of ten percent attorney fees on the amount recovered. It also filed a reconventional demand against Glencoe and a third party demand against Lamar and Hartford, seeking to recover the unpaid balance of $52,339.73 for furnishing labor and materials on the construction project, as reflected in its recorded claim, as well as interest and court costs. Mayeux’s filed a claim against Lamar and Hartford in the concursus proceeding, asserting that more than 30 days had lapsed since amicable demand without a payment being made. It sought to recover the full amount of its recorded claim as well as ten percent attorney fees on the amounts recovered. Both subcontractors submitted evidence in connection with their claims.

A threshold procedural dispute arose regarding whether the Public Works Act or Private Works Act governed the concursus proceeding. Lamar asserted that Glencoe is not a “public entity” and the work was not a “public work” as defined by the Public Works Act, and the trial court agreed, holding that the Private Works Act applied to the proceeding. This court reversed that ruling, holding that Glencoe may proceed under the Public Works Act. Glencoe Education Foundation, Inc. v. Clerk of Court and Recorder of Mortgages for the Parish of St. Mary, Louisiana, 2008-2404 (La.App. 1st Cir.12/9/08) (unpublished). The supreme court declined to review that ruling. Glencoe Education Foundation, Inc. v. Clerk of Court and Recorder of Mortgages for the Parish of St. Mary, Louisiana, 2008-2892 (La.12/12/08), 996 So.2d 1122.

On January 5, 2009, the trial court entered judgment dismissing, with prejudice, all claims and causes of action against Glencoe, relieved Glencoe for personal liability on the claims asserted by Lamar, the subcontractors, and Sherwin-Williams, and directed the clerk of court to cancel all claims filed against Glencoe in the public records. In so doing, the court noted that it reviewed the certificate of no objection to the bond filed by the clerk of court. Lamar filed a ^motion for a new trial, which was granted in part by the trial court to preserve Lamar’s claims against Glencoe that were pending in the breach of contract lawsuit filed in another division of the court.

Thereafter, on March 1, 2010, Brown filed a motion to set the summary hearing and trial of all issues and claims pending in the concursus proceeding. In opposition to that motion, Lamar and Hartford asserted that neither Brown, nor any of the other claimants in the concursus proceeding, is entitled to recover any amount from them under the payment provisions of the Lamar subcontracts. Specifically, they relied on the “pay if paid” clauses found in the Lamar subcontracts, which makes payment by Glencoe to Lamar a “suspensive condition” or condition precedent to the obligation of Lamar to pay its subcontractors. Paragraph 18(c) of the Lamar subcontracts provides as follows:

Payment by Owner to General Contractor shall be a suspensive condition (condition precedent) to the obligation of the General Contractor to pay the Subcontractor. The Contractor shall not be obligated to make any payment to Subcontractor under this contract unless and until General Contractor from the Owner receives payments.

Lamar argued that it could not be held liable to the claimants because Glencoe [229]*229failed to remit the balance due on the general contract to Lamar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodrow Wilson Constr., LLC v. Amtek of La., Inc.
256 So. 3d 305 (Louisiana Court of Appeal, 2018)
Bear Indus., Inc. v. Hanover Ins. Co.
241 So. 3d 1159 (Louisiana Court of Appeal, 2018)
Gillio v. Hanover American Insurance Co.
212 So. 3d 588 (Louisiana Court of Appeal, 2017)
Gootee Construction, Inc. v. Atkins
178 So. 3d 629 (Louisiana Court of Appeal, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
65 So. 3d 225, 2010 La.App. 1 Cir. 1872, 2011 La. App. LEXIS 626, 2011 WL 1878788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glencoe-education-foundation-inc-v-clerk-of-court-recorder-of-lactapp-2011.