Woodrow Wilson Constr., LLC v. Amtek of La., Inc.
Opinion
WELCH, J.
A materialman for a parish public works project filed suit against the general contractor, the surety that issued the performance bonds, and the subcontractor for the full amount of its statement of claim. The subcontractor filed a cross-claim against the general contractor and the surety for the full amount of its claim of lien or privilege and sought indemnification from the materialman. Following a bench trial limited in scope to the materialman's claims, the trial court rendered judgment in favor of the materialman and against the subcontractor for the full amount of the materialman's statement of claim. The judgment dismissed the materialman's claims against the general contractor and its surety, with prejudice. The materialman and the subcontractor have appealed. For the reasons that follow, we reverse in part, affirm in part, and remand.
FACTS AND PROCEDURAL HISTORY
The Orleans Parish School Board ("OPSB"), the owner, contracted with Woodrow Wilson Construction, LLC ("Woodrow Wilson"), a general contractor, for the construction of an elementary school ("project").1 The contract was recorded on September 14, 2012.2 Western *309Surety Company ("Western Surety") provided the statutory performance and payment bonds to Woodrow Wilson for the project.
Woodrow Wilson subcontracted with Amtek of Louisiana, Inc. ("Amtek") for site work on the project.3 Amtek then subcontracted with Baton Rouge Winwater Works Co. ("BR Winwater"), a materialman, to supply PVC storm drainage pipe, in-line drains, and pipe for installation into the project. Woodrow Wilson, Amtek, and BR Win water executed a joint check agreement, whereby Woodrow Wilson agreed to pay Amtek and BR Winwater by joint check for all services rendered in connection with the project. Although executed by Woodrow Wilson in October 2012, the joint check agreement was not fully executed by all the parties and received by Woodrow Wilson until October 30, 2014.
BR Winwater made ten deliveries of materials to Amtek, from March 25, 2014 to June 11, 2014. It is undisputed that BR Winwater's materials were delivered, received in "good condition" by Amtek, and installed into the project. It is further undisputed that Amtek billed Woodrow Wilson for BR Winwater's materials; Woodrow Wilson billed OPSB for all materials furnished by BR Winwater; and, OPSB fully paid Woodrow Wilson for the materials supplied by BR Winwater.
At some point during the project, a dispute arose between Woodrow Wilson and Amtek. After sending notices of default to Amtek on March 14, 2014 and June 10, 2014, Woodrow Wilson terminated Amtek's subcontract on June 20, 2014. On August 14, 2014, Amtek filed a claim of lien or privilege on the project in the amount of $280,272.15, which included unpaid amounts owed to BR Winwater, as well as unpaid amounts owed to other subcontractors of Amtek.4
It is undisputed that Woodrow Wilson, Western Surety, and Amtek have made no payments to BR Winwater for the materials it supplied for the project. Accordingly, BR Winwater transmitted notice of nonpayment to Woodrow Wilson via certified mail on October 29, 2014. BR Winwater transmitted a second notice of nonpayment to Woodrow Wilson via facsimile on November 24, 2014.
A certificate of substantial completion for the project was recorded on December 2, 2014.5
BR Winwater filed a statement of claim on January 5, 2015, alleging it was owed $79,240.00 for the materials it supplied to Amtek on the project, plus the cost of filing the statement of claim.6 Also on January 5, 2015, BR Winwater transmitted notices of filing its statement of claim as well as demand letters to OPSB, Woodrow *310Wilson, and Western Surety via certified mail. On January 27, 2015, BR Winwater transmitted a second demand letter to Western Surety, via certified mail.
On April 1, 2015, Woodrow Wilson filed a petition for damages and breach of contract against Amtek.7 Amtek answered Woodrow Wilson's suit and filed a reconventional demand against Woodrow Wilson and Western Surety, alleging that it had not been paid by Woodrow Wilson for the work it performed on the project.
On October 1, 2015, BR Winwater filed a petition for damages against Woodrow Wilson, Amtek, and Western Surety.8 Amtek answered BR Winwater's suit and filed a cross claim against Woodrow Wilson and Western Surety for amounts due and for indemnification from BR Winwater's claim.
The Woodrow Wilson Suit and the BR Winwater Suit were ultimately consolidated and transferred to Division "D" of the 19th Judicial District Court ("JDC"), pursuant to a judgment signed on October 5, 2016. Prior to trial, Woodrow Wilson and Amtek stipulated in camera that the claims between Woodrow Wilson and Amtek (the subject of the Woodrow Wilson Suit and Amtek's cross claim in the BR Winwater Suit) would be reserved pending the resolution of a separate, related lawsuit in Civil District Court in Orleans Parish (the "Beverly Suit").9
Following a bench trial held on January 31, 2017, solely on BR Winwater's claims against Woodrow Wilson, Western Surety, and Amtek, the trial court rendered judgment on March 9, 2017, stating in pertinent part:
The court finds that no notice was given to Woodrow Wilson by BR Winwater that Amtek had defaulted on its payment obligations until after a lapse of time for issuing a notice of non payment. Therefore, Woodrow Wilson and its surety Western have no obligations to pay Amtek?s [sic ] debt to Winwater. Nonetheless, Winwater would have rights over and against Amtek for the amount of unpaid invoices. Judgment to be signed accordingly.
The trial court signed a judgment in accordance with its ruling on May 2, 2017, in favor of BR Winwater and against Amtek, in the amount of $79,240.90, plus interest and costs. The judgment dismissed BR Winwater's claims against Woodrow Wilson and Western Surety, with prejudice. BR Winwater and Amtek now appeal the May 2, 2017 judgment of the trial court.
ASSIGNMENTS OF ERROR
In its sole assignment of error, BR Winwater contends the trial court erred in dismissing its claims against Woodrow Wilson and Western Surety under La. R.S. 38:2242(B) and La. R.S. 38:2247.
Amtek assigns three errors to the trial court's judgment:
1. The Trial Court erred in dismissing BR Winwater's claim against [Woodrow] Wilson, general contractor, and Western [Surety], as [Woodrow] Wilson's surety, under La. R.S. 38:2242(B) and 2247.
Free access — add to your briefcase to read the full text and ask questions with AI
WELCH, J.
A materialman for a parish public works project filed suit against the general contractor, the surety that issued the performance bonds, and the subcontractor for the full amount of its statement of claim. The subcontractor filed a cross-claim against the general contractor and the surety for the full amount of its claim of lien or privilege and sought indemnification from the materialman. Following a bench trial limited in scope to the materialman's claims, the trial court rendered judgment in favor of the materialman and against the subcontractor for the full amount of the materialman's statement of claim. The judgment dismissed the materialman's claims against the general contractor and its surety, with prejudice. The materialman and the subcontractor have appealed. For the reasons that follow, we reverse in part, affirm in part, and remand.
FACTS AND PROCEDURAL HISTORY
The Orleans Parish School Board ("OPSB"), the owner, contracted with Woodrow Wilson Construction, LLC ("Woodrow Wilson"), a general contractor, for the construction of an elementary school ("project").1 The contract was recorded on September 14, 2012.2 Western *309Surety Company ("Western Surety") provided the statutory performance and payment bonds to Woodrow Wilson for the project.
Woodrow Wilson subcontracted with Amtek of Louisiana, Inc. ("Amtek") for site work on the project.3 Amtek then subcontracted with Baton Rouge Winwater Works Co. ("BR Winwater"), a materialman, to supply PVC storm drainage pipe, in-line drains, and pipe for installation into the project. Woodrow Wilson, Amtek, and BR Win water executed a joint check agreement, whereby Woodrow Wilson agreed to pay Amtek and BR Winwater by joint check for all services rendered in connection with the project. Although executed by Woodrow Wilson in October 2012, the joint check agreement was not fully executed by all the parties and received by Woodrow Wilson until October 30, 2014.
BR Winwater made ten deliveries of materials to Amtek, from March 25, 2014 to June 11, 2014. It is undisputed that BR Winwater's materials were delivered, received in "good condition" by Amtek, and installed into the project. It is further undisputed that Amtek billed Woodrow Wilson for BR Winwater's materials; Woodrow Wilson billed OPSB for all materials furnished by BR Winwater; and, OPSB fully paid Woodrow Wilson for the materials supplied by BR Winwater.
At some point during the project, a dispute arose between Woodrow Wilson and Amtek. After sending notices of default to Amtek on March 14, 2014 and June 10, 2014, Woodrow Wilson terminated Amtek's subcontract on June 20, 2014. On August 14, 2014, Amtek filed a claim of lien or privilege on the project in the amount of $280,272.15, which included unpaid amounts owed to BR Winwater, as well as unpaid amounts owed to other subcontractors of Amtek.4
It is undisputed that Woodrow Wilson, Western Surety, and Amtek have made no payments to BR Winwater for the materials it supplied for the project. Accordingly, BR Winwater transmitted notice of nonpayment to Woodrow Wilson via certified mail on October 29, 2014. BR Winwater transmitted a second notice of nonpayment to Woodrow Wilson via facsimile on November 24, 2014.
A certificate of substantial completion for the project was recorded on December 2, 2014.5
BR Winwater filed a statement of claim on January 5, 2015, alleging it was owed $79,240.00 for the materials it supplied to Amtek on the project, plus the cost of filing the statement of claim.6 Also on January 5, 2015, BR Winwater transmitted notices of filing its statement of claim as well as demand letters to OPSB, Woodrow *310Wilson, and Western Surety via certified mail. On January 27, 2015, BR Winwater transmitted a second demand letter to Western Surety, via certified mail.
On April 1, 2015, Woodrow Wilson filed a petition for damages and breach of contract against Amtek.7 Amtek answered Woodrow Wilson's suit and filed a reconventional demand against Woodrow Wilson and Western Surety, alleging that it had not been paid by Woodrow Wilson for the work it performed on the project.
On October 1, 2015, BR Winwater filed a petition for damages against Woodrow Wilson, Amtek, and Western Surety.8 Amtek answered BR Winwater's suit and filed a cross claim against Woodrow Wilson and Western Surety for amounts due and for indemnification from BR Winwater's claim.
The Woodrow Wilson Suit and the BR Winwater Suit were ultimately consolidated and transferred to Division "D" of the 19th Judicial District Court ("JDC"), pursuant to a judgment signed on October 5, 2016. Prior to trial, Woodrow Wilson and Amtek stipulated in camera that the claims between Woodrow Wilson and Amtek (the subject of the Woodrow Wilson Suit and Amtek's cross claim in the BR Winwater Suit) would be reserved pending the resolution of a separate, related lawsuit in Civil District Court in Orleans Parish (the "Beverly Suit").9
Following a bench trial held on January 31, 2017, solely on BR Winwater's claims against Woodrow Wilson, Western Surety, and Amtek, the trial court rendered judgment on March 9, 2017, stating in pertinent part:
The court finds that no notice was given to Woodrow Wilson by BR Winwater that Amtek had defaulted on its payment obligations until after a lapse of time for issuing a notice of non payment. Therefore, Woodrow Wilson and its surety Western have no obligations to pay Amtek?s [sic ] debt to Winwater. Nonetheless, Winwater would have rights over and against Amtek for the amount of unpaid invoices. Judgment to be signed accordingly.
The trial court signed a judgment in accordance with its ruling on May 2, 2017, in favor of BR Winwater and against Amtek, in the amount of $79,240.90, plus interest and costs. The judgment dismissed BR Winwater's claims against Woodrow Wilson and Western Surety, with prejudice. BR Winwater and Amtek now appeal the May 2, 2017 judgment of the trial court.
ASSIGNMENTS OF ERROR
In its sole assignment of error, BR Winwater contends the trial court erred in dismissing its claims against Woodrow Wilson and Western Surety under La. R.S. 38:2242(B) and La. R.S. 38:2247.
Amtek assigns three errors to the trial court's judgment:
1. The Trial Court erred in dismissing BR Winwater's claim against [Woodrow] Wilson, general contractor, and Western [Surety], as [Woodrow] Wilson's surety, under La. R.S. 38:2242(B) and 2247.
2. The Trial Court erred in granting judgment against Amtek on BR Winwater's *311claims when the evidence showed that [Woodrow] Wilson was paid by the OPSB for the materials, but never paid Amtek for the materials supplied by BR Winwater. [Woodrow] Wilson violated La. R.S. 9:2784 by failing to pay BR Winwater and/or Amtek after it was paid by the owner.
3. The Trial Court erred in failing to grant judgment against [Woodrow] Wilson and Western [Surety] in favor of BR Winwater because [Woodrow] Wilson was fully paid by the [OPSB] and violated La. RS. 9:2784 and the Joint Check Agreement when it failed to pay BR Winwater after [Woodrow] Wilson received full payment for BR Winwater's materials.
LAW & DISCUSSION
Materialman Claimant's Right of Action on Bond
Relevant Law
Public construction contracts are governed by the Louisiana Public Works Act ("LPWA"), La. R.S. 38:2241, et seq. , which provides the exclusive remedies to parties in litigation arising out of a public work. State Through Div. of Admin . v. Mc I nnis Bros. Const., 97-0742 (La. 10/21/97),
The LPWA accomplishes its purpose of protecting laborers and suppliers of materials on public works by mandating that when a public entity enters into a contract for the construction, alteration, or repair of a public work in excess of $25,000.00, the contractor is required to post a bond "in a sum of not less than fifty percent of the contract price for the payment by the contractor or subcontractor to claimants as defined in R.S. 38:2242." La. R.S. 38:2241(A)(2) ; Pierce Foundations, Inc.,
The category of "claimants" who are entitled to recovery under the LPWA includes any person to whom money is due pursuant to a contract with the owner, contractor, or subcontractor for doing work, performing labor, or furnishing material or supplies for the construction of *312any public work. La. R.S. 38:2242(A). One method for claimants to assert claims under the LPWA is set forth in La. R.S. 38:2242(B), which provides:
Any claimant may after the maturity of his claim and within forty-five days after the recordation of acceptance of the work by the governing authority or of notice of default of the contractor or subcontractor, file a sworn statement of the amount due him with the governing authority having the work done and record it in the office of the recorder of mortgages for the parish in which the work is done.
Unlike laborers and suppliers involved in private building projects, similarly situated workers and suppliers engaged by public entities on building projects cannot protect themselves with liens against public property because liens are not enforceable against publicly-owned property. Mc I nnis Bros. Const.,
Under the LPWA, a claimant also has one year from the registry of acceptance of the work (or of notice of default of the contractor) to bring an action on the bond against the surety, contractor, or both. This process is set forth in La. R.S. 38:2247, which provides:
Nothing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part, provided that said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work or of notice of default of the contractor; except that before any claimant having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall in addition to the notice and recordation required in R.S. 38:2242(B) give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work or notice by the owner of default, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor or service was done or performed. Such notice shall be served by mailing the same by registered or certified mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office in the state of Louisiana. [Emphasis added.]
See also Bd. of Sup'rs of Louisiana State Univ. v. Louisiana Agr. Fin. Auth., 2007-0107 (La. App. 1st Cir. 2/8/08),
In Pierce Foundations, Inc.,
In this case, the trial court concluded that BR Winwater failed to give the appropriate materialman claimant's notice of nonpayment to the general contractor Woodrow Wilson that the subcontractor Amtek had defaulted on its payment obligations for materials supplied by BR Winwater, as set forth in La. R.S. 38:2242(F). Louisiana Revised Statutes 38:2242(F) provides:
In addition to the other provisions of [ La. R.S. 38:2242 ], if the materialman has not been paid by the subcontractor and has not sent notice of nonpayment to the general contractor and the owner, then the materialman shall lose his right to file a privilege or lien on the immovable property. The return receipt indicating that certified mail was properly addressed to the last known address of the general contractor and the owner and deposited in the U.S. mail on or before seventy-five days from the last day of the month in which the material was delivered, regardless of whether the certified mail was actually delivered, refused, or unclaimed satisfies the notice provision hereof or no later than the statutory lien period, whichever comes first. The provisions of this Subsection shall apply only to disputes arising out of recorded contracts. [Emphasis added.]
To plainly state La. R.S. 38:2242(F), prior to filing a lien or privilege, a materialman must give written notice of nonpayment via certified mail to the general contractor and owner within 75 days from the last day of the month in which the materials were delivered.
On appeal, BR Winwater and Amtek contend the trial court erred in dismissing BR Winwater's claim against Woodrow Wilson and Western Surety under La. R.S. 38:2242(B) and La. R.S. 38:2247, arguing that BR Winwater has a right to recover against Woodrow Wilson and Western Surety in accordance with La. R.S. 38:2247, because BR Winwater timely filed its statement of claim pursuant to *314La. R.S. 38:2242(B) and further complied with the filing and notice requirements of La. R.S. 38:2247. Furthermore, BR Winwater and Amtek contend that Woodrow Wilson was fully paid by the owner, OPSB, for the materials supplied by BR Winwater.11
Woodrow Wilson and Western Surety argue, however, that prior to filing its statement of claim in accordance with La. R.S. 38:2242(B), the LPWA required BR Winwater, as a materialman supplying materials on the project, to comply with the materialman's notice of nonpayment requirement set forth in La. R.S. 38:2242(F). Thus, Woodrow Wilson and Western Surety argue that compliance with La. R.S. 38:2242(B)and La. R.S. 38:2242(F) is required before a materialman claimant may pursue a right of action on the statutory bond under La. R.S. 38:2247. It is undisputed that BR Winwater did not transmit notice of nonpayment via certified mail to the general contractor Woodrow Wilson and the owner OPSB within 75 days from the last day of the month in which the materials were delivered, in accordance with La. R.S. 38:2242(F).12
This case involves the interpretation of three provisions of the LPWA: La. R.S. 38:2242(B), La. R.S. 38:2242(F), and La. R.S. 38:2247. The issue before this court is whether the LPWA requires a materialman to comply with La. R.S. 38:2242(B)and La. R.S. 38:2242(F) in order to file an action against the general contractor and/or surety on the bond, as set forth in La. R.S. 38:2247. Questions of law, such as the proper interpretation of a statute, are reviewed by this court under the de novo standard of review. Louisiana Mun. Ass'n v. State, 2004-0227 (La. 1/19/05),
Analysis
Legislation is the solemn expression of legislative will and, thus, the interpretation of legislation is primarily the search for the legislative intent. Red Stick Studio Dev., L.L.C. v. State ex rel. Dep't of Econ. Dev., 2010-0193 (La. 1/19/11),
If however, the language of the law is susceptible of different meanings, it must be interpreted as having the meaning that best conforms to the purpose of the law. La. C.C. art. 10 ; M.J. Farms, Ltd. v. Exxon Mobil Corp., 2007-2371 (La. 7/1/08),
It is also well established that the Legislature is presumed to enact each *315statute with deliberation and with full knowledge of all existing laws on the same subject. State v. Campbell, 2003-3035 (La. 7/6/04),
At the outset, we distinguish between La. R.S. 38:2242 -setting forth a claimant's right to file a statement of claim that grants him a privilege against the unexpended funds in the hands of the public entity-and La. R.S. 38:2247 -setting forth a claimant's right to file suit on the bond against the contractor and/or surety.
Louisiana Revised Statutes 38:2242 sets forth the process for a claimant to file a sworn statement of the amount due him. Louisiana Revised Statutes 38:2242(B) provides that a claimant "may" file a sworn statement. Like the supreme court noted in Pierce Foundations, Inc., the word "may" is permissive.
In contrast, La. R.S. 38:2242(F) provides that "[i]n addition to the other provisions of this Section,"-i.e. , the other provisions of La. R.S. 38:2242, including subsection (B)-if a materialman has not been paid by the subcontractor, the materialman must send notice of nonpayment to the general contractor and owner within 75 days from the last day of the month in which the materials were delivered, otherwise the materialman shall lose his right to file a privilege or lien.13
Based upon a plain reading of La. R.S. 38:2242(B) and La. R.S. 38:2242(F), a materialman's failure to provide the 75-day notice of nonpayment to *316the general contractor and owner results only in the materialman's loss of the right to file a privilege against the unexpended funds in the hands of the public entity.
The inclusion of the phrase, "[i]n addition to the other provisions of this Section", found in La. R.S. 38:2242(F), conflicts with the language of La. R.S. 38:2242(B) by rendering the permissive "may" in La. R.S. 38:2242(B) mandatory by requiring a materialman claimant to file a sworn statement and give the 75-day notice of nonpayment to the general contractor and the owner, otherwise, the materialman claimant loses his right to file a privilege against the unexpended funds in the hands of the public entity.
Unlike La. R.S. 38:2242, La. R.S. 38:2247 sets forth the requirements for a claimant to file suit on the bond against the contractor and/or surety. Therein, La. R.S. 38:2247 refers to the recordation "requirements" of La. R.S. 38:2242(B), providing that "[n]othing in this Part"-i.e. , Part III of Chapter 10 of Title 38 of the Revised Statutes, which is La. R.S. 38:2241 -2249-"shall be construed to deprive any claimant ... who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part." If the claimant does not have a direct contractual relationship with the general contractor, La. R.S. 38:2247 further requires that said claimant give written notice to the contractor within 45 days from the recordation of the acceptance. Aside from the mention of La. R.S. 38:2242(B), La. R.S. 38:2247 contains no mention of La. R.S. 38:2242(F)'s materialman claimant 75-day notice of nonpayment requirement. Furthermore, La. R.S. 38:2247 states that "[n]othing in this Part"-including La. R.S. 38:2242(F) -"shall be construed to deprive any claimant ... of his right of action on the bond." If the Legislature had intended to require materialman claimants to provide the 75-day notice of nonpayment to the general contractor and owner, or be deprived of his right of action on the statutory bond, the Legislature would have included such language in La. R.S. 38:2247 ; however, it did not.
Furthermore, in Pierce Foundations, Inc.,
In the matter before us, not only did BR Winwater comply with La. R.S. 38:2242(B), BR Winwater also provided the additional 45-day notice to Woodrow Wilson due to its lack of privity of contract. La. R.S. 38:2247. The last month that BR Winwater supplied materials on the project was June 2014.14 The acceptance of work was recorded on December 2, 2014.15 BR Winwater *317filed a statement of claim on January 5, 2015, within 45 days of the recordation of acceptance of work, in accordance with La. R.S. 38:2242(B). BR Winwater filed suit on October 1, 2015, against the general contractor, Woodrow Wilson, its surety, Western Surety, and the subcontractor, Amtek, within one year from the registry of the acceptance of work, as set forth in La. R.S. 38:2247. Additionally, since BR Winwater was not in contractual privity with Woodrow Wilson, BR Winwater gave written notice via certified mail to Woodrow Wilson within 45 days from the recordation of the acceptance of work, in accordance with La. R.S. 38:2247. Therefore, we conclude that Woodrow Wilson and Western Surety were sufficiently notified of the claim for purposes of filing suit on the bond pursuant to La. R.S. 38:2247.
Our interpretation best comports with the purpose of the LPWA, which again, is to "protect those performing labor and furnishing materials for public works." Pierce Foundations, Inc.,
It is undisputed that BR Winwater complied with the requirements of La. R.S. 38:2242(B) and La. R.S. 38:2247. It is also undisputed that BR Winwater did not comply with La. R.S. 38:2242(F). Applying the LPWA as written, BR Winwater has only lost its right to file a privilege against the unexpended funds in the possession of the OPSB. While BR Winwater has lost its right to a privilege against those funds, BR Winwater is not precluded from filing suit on the bond against the general contractor, Woodrow Wilson, and its surety, Western Surety. BR Winwater is not seeking to enforce a lien or privilege on the public work; it is seeking to enforce its *318right of action on the bond against the general contractor and the surety under La. R.S. 38:2247 as a claimant. There is no language in the LPWA prohibiting BR Winwater from recovering on the bond against Woodrow Wilson and Western Surety, even if it failed to comply with La. R.S. 38:2242(F).
On appeal, Woodrow Wilson and Western Surety contend that this court established that compliance with both La. R.S. 38:2242(B)and La. R.S. 38:2242(F) is required by the LPWA before a materialman claimant may preserve a right of action on the bond under La. R.S. 38:2247 in J. Reed Constructors, Inc. v. Roofing Supply Grp., L.L.C., 2012-2136 (La. App. 1st Cir. 11/1/13),
J. Reed Constructors is factually distinguishable from the case before us for several reasons. First, in J. Reed Constructors, the materialman did not file a statement of claim in accordance with La. R.S. 38:2242(B) ; the materialman had merely transmitted one notice of nonpayment pursuant to La. R.S. 38:2242(F) to the general contractor and owner. In the instant matter, BR Winwater filed a statement of claim within 45 days of the recordation of acceptance of work in accordance with La. R.S. 38:2242(B). Additionally, since BR Winwater was not in contractual privity with Woodrow Wilson, BR Winwater gave written notice via certified mail to Woodrow Wilson within 45 days from the recordation of the acceptance of work, pursuant to La. R.S. 38:2247. Second, the J. Reed Constructors court's conclusion that a "materialman claimant must first comply with the notice and recordation requirements of La. R.S. 38:2242(B) and (F) in order to preserve the right to file a privilege or lien" does not apply to the case before us. BR Winwater is not attempting to enforce a privilege on the funds held by the OPSB. BR Winwater is seeking to enforce its right of action on the bond against Woodrow Wilson and Western Surety. Finally, the issue of a materialman claimant preserving a right of action on the statutory bond as set forth in La. R.S. 38:2247 was not before the court in J. Reed Constructors. In the instant matter, a materialman claimant's right of action on the bond as set forth in La. R.S. 38:2247 court, and whether compliance with both La. R.S. 38:2242(B) and *319La. R.S. 38:2242(F) is necessary before pursing said action, is the issue squarely before this court in the instant case.16
The second and third circuits have held that La. R.S. 38:2242(F) requires notice of nonpayment be given to the general contractor and owner before a materialman claimant files a lien or privilege in accordance with La. R.S. 38:2242(B). However, those circuits distinguish between the 75-day notice of nonpayment set forth in La. R.S. 38:2242(F) and the 45-day notice referenced in La. R.S. 38:2247.17 The 75-day notice of nonpayment set forth in La. R.S. 38:2242(F) is to be given by the materialman claimant to the general contractor and owner to preserve the materialman claimant's right to file a statement of claim as set forth in La. R.S. 38:2242(B). In contrast, the notice referenced in La. R.S. 38:2247 is to be given by a claimant who is not in privity of contract with the general contractor to the general contractor to preserve the claimant's right of action on the bond against the contractor or the surety or both. In addition, the 75-day notice requirement La. R.S. 38:2242(F) would be untimely if it were given before a claim was filed, but after 75 days had elapsed since the last day of the month in which material was delivered. It would be immaterial in that case if the 45-day statutory lien period had not elapsed. The notice requirement found in La. R.S. 38:2247 references only the 45-day statutory lien period provided in La. R.S. 38:2242(B). See Elec. Supply Co. v. Great Am. Ins. Co., 42,727 (La. App. 2nd Cir. 12/12/07),
*320Conclusion
Giving full effect to the language of La. R.S. 38:2247, which states in relevant part, "[n]othing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part," BR Winwater only lost its right to a privilege against the unexpended funds in the possession of the OPSB for its failure to comply with La. R.S. 38:2242(F). Had the Legislature intended to require materialman claimants to comply with La. R.S. 38:2242(F) prior to proceeding against the contractor and the surety on the statutory bond, they would have amended La. R.S. 38:2247 to do so. They did not. Thus, we hold that BR Winwater has preserved its right of action on the bond against Woodrow Wilson and Western Surety. Accordingly, we hold that the trial court erred in dismissing BR Winwater's claims against Woodrow Wilson and Western Surety.
Louisiana's Prompt Pay Statute, La. R.S. 9:2784 ; Joint Check Agreement
In its second assignment of error, Amtek argues that Woodrow Wilson violated Louisiana's Prompt Pay Statute, La. R.S. 9:2784, by failing to pay Amtek for the materials supplied by BR Winwater after it was paid by the owner, OPSB, for the materials. Similarly, in its third and final assignment of error, Amtek contends that the trial court erred in failing to grant judgment against Woodrow Wilson and Western Surety, in favor of BR Winwater, arguing that Woodrow Wilson violated La. R.S. 9:2784 and the parties' joint check agreement when it failed to issue joint checks payable to Amtek and BR Winwater after it was fully paid by the owner, OPSB.
Louisiana's Prompt Pay Statute, La. R.S. 9:2784, provides, in relevant part:
A. When a contractor receives any payment from the owner for improvements to an immovable after the issuance of a certificate of payment by the architect or engineer, or when a contractor receives any payment from the owner for improvements to an immovable when no architect or engineer is on the job, the contractor shall promptly pay such monies received to each subcontractor and supplier in proportion to the percentage of work completed prior to the issuance of the certificate of payment by such subcontractor and *321supplier, or by the owner if no architect or engineer is on the job. Further, whenever a subcontractor receives payment from the contractor, the subcontractor shall promptly pay such monies received to each sub-subcontractor and supplier in proportion to the work completed.
* * *
C. If the contractor or subcontractor without reasonable cause fails to make any payment to his subcontractors and suppliers within fourteen consecutive days of the receipt of payment from the owner for improvements to an immovable, the contractor or subcontractor shall pay to the subcontractors and suppliers, in addition to the payment, a penalty in the amount of one-half of one percent of the amount due, per day, from the expiration of the period allowed herein for payment after the receipt of payment from the owner. The total penalty shall not exceed fifteen percent of the outstanding balance due. In addition, the contractor or subcontractor shall be liable for reasonable attorney fees for the collection of the payments due the subcontractors and suppliers. However, any claim which the court finds to be without merit shall subject the claimant to all reasonable costs and attorney fees for the defense against such claim. [Emphasis added.]
Statutes providing for punitive penalties are rare, and as such, when a statute does authorize the imposition of a penalty, it is to be strictly construed. Int'l Harvester Credit Corp. v. Seale,
The Prompt Pay Statute is not a part of the LPWA. The statute is found in Title 9 of the Revised Statutes, the "Civil Code Ancillaries," to Book III, Title IV, "Conventional Obligations or Contracts." While a statute's heading is not the law, it provides some guidance as to what the Legislature intended the statute to cover. See Anderson v. Ochsner Health Sys., 2013-2970 (La. 7/1/14),
Joint check agreements-where a check is issued jointly to two or more parties (e.g. , to a subcontractor and a materials supplier)-are widely used in the construction industry. General contractors often use joint checks to ensure their subcontractors properly disburse the proceeds of progress payment checks to their sub-subcontractors and suppliers. See 1 Construction Contracts Deskbook § 21:1 (Nick J. Vizy, ed., 2017), available on WESTLAW . A joint check agreement is a conventional obligation that constitutes the law between the parties. Courts are obligated to give legal effect to such contracts according to the true intent of the parties. See La. C.C. arts. 2045 - 2047.
The evidence established at trial indicated the joint check agreement was prepared by Woodrow Wilson on behalf of Amtek and BR Winwater. The joint check agreement, dated October 11, 2012, provides:
As an accommodation to our subcontractor, Amtek of La., Inc. and to assist it in the obtainment of materials to be consumed and/or incorporated in the above-referenced project this will evidence our agreement to make checks jointly payable to Amtek of La., Inc. and Baton Rouge Winwater Works Co. for payment of materials ordered by Amtek of La., Inc. in an amount not to exceed *322$50,000.00 [handwritten notation in margin increased the amount to "$60,000.00"] and delivered to the above-referenced project site, which materials are actually consumed in and/or incorporated in the above-referenced construction site. Such payments shall be made as and when provided in the subcontract agreement between WOODROW WILSON CONSTRUCTION COMPANY, INC. and Amtek of La., Inc. upon presentation to WOODROW WILSON CONSTRUCTION COMPANY, INC. of (1) an invoice evidencing the purchase of such materials, and (2) proof acceptable to WOODROW WILSON CONSTRUCTION COMPANY, INC. of delivery of such materials to the project site.
This agreement is not, and nothing herein stated shall be construed to create, a contract or agreement between WOODROW WILSON CONSTRUCTION COMPANY, INC. and Baton Rouge Winwater Works Co. an agreement or guaranty or surety, or an assignment of all or any part of the subcontract agreement between WOODROW WILSON CONSTRUCTION COMPANY, INC. and Amtek of La., Inc.
Woodrow Wilson signed the joint check agreement on October 11, 2012. Amtek signed the joint check agreement on October 15, 2012. BR Winwater then signed the joint check agreement on March 14, 2014, nearly two years after Woodrow Wilson had issued and signed the joint check agreement. Woodrow Wilson received a copy of the final, executed joint check agreement on October 30, 2014.19
When Woodrow Wilson received the final, executed version of the joint check agreement, Amtek's subcontract had been terminated for approximately four months (since June 20, 2014). The last payment Woodrow Wilson tendered to Amtek is dated May 23, 2014, which is approximately five months prior to Woodrow Wilson receiving the fully executed joint check agreement. Since the joint check agreement was not in effect at the time Woodrow Wilson issued its last payment to Amtek prior to terminating Amtek's subcontract, Woodrow Wilson had no obligation to issue checks jointly to Amtek and BR Winwater; therefore, Woodrow Wilson did not breach the joint check agreement.
The joint check agreement did not obligate Woodrow Wilson to make any payments to BR Winwater, but only gave Woodrow Wilson the contractual right to do so out of any payments Woodrow Wilson made to Amtek, and only for materials Amtek purchased from BR Winwater. The joint check agreement prevented Amtek from refusing to authorize Woodrow Wilson to make payments to BR Winwater since Woodrow Wilson did not have a contract with BR Winwater, Amtek's materialman.
*323Absent from La. R.S. 9:2784 is any requirement that a general contractor such as Woodrow Wilson must promptly pay a materialman with whom he does not stand in contractual privity.
Furthermore, we cannot read the terms of the joint check agreement into the statutory bond provided by Western Surety. The LPWA is sui generis and must be strictly construed and applied. Mc I nnis Bros. Const.,
While Amtek may assert a cause of action against Woodrow Wilson under La. R.S. 9:2784, Amtek must pursue that cause of action in the separate proceeding pending in Orleans Parish in the Beverly Suit, since the parties stipulated that the only claims at issue before the trial court in this matter were BR Winwater's claims. Thus, Woodrow Wilson's suit against Amtek, and Amtek's reconventional demand and cross claim against Woodrow Wilson and Western Surety regarding its claim of lien or privilege, are reserved for the Beverly Suit.
Accordingly, Amtek's second and third assignments of error are without merit.
DECREE
For the foregoing reasons, we reverse the portion of the trial court's May 2, 2017 judgment dismissing Baton Rouge Winwater Works Co.'s claims against Woodrow Wilson Construction, LLC and Western Surety Company, with prejudice. The judgment is affirmed in all other respects. We remand this matter for further proceedings consistent with this opinion. All costs of this appeal are assessed equally against Woodrow Wilson Construction, LLC, Western Surety Company, and Amtek of Louisiana, Inc.
JUDGMENT REVERSED IN PART, AFFIRMED IN ALL OTHER RESPECTS; REMANDED.
Footnotes
256 So. 3d 305 (Woodrow Wilson Constr., LLC v. Amtek of La., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.