Woodrow Wilson Constr., LLC v. Amtek of La., Inc.

256 So. 3d 305
CourtLouisiana Court of Appeal
DecidedAugust 6, 2018
Docket2017 CA 1156, 2017 CA 1157
StatusPublished
Cited by3 cases

This text of 256 So. 3d 305 (Woodrow Wilson Constr., LLC v. Amtek of La., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodrow Wilson Constr., LLC v. Amtek of La., Inc., 256 So. 3d 305 (La. Ct. App. 2018).

Opinion

WELCH, J.

A materialman for a parish public works project filed suit against the general contractor, the surety that issued the performance bonds, and the subcontractor for the full amount of its statement of claim. The subcontractor filed a cross-claim against the general contractor and the surety for the full amount of its claim of lien or privilege and sought indemnification from the materialman. Following a bench trial limited in scope to the materialman's claims, the trial court rendered judgment in favor of the materialman and against the subcontractor for the full amount of the materialman's statement of claim. The judgment dismissed the materialman's claims against the general contractor and its surety, with prejudice. The materialman and the subcontractor have appealed. For the reasons that follow, we reverse in part, affirm in part, and remand.

FACTS AND PROCEDURAL HISTORY

The Orleans Parish School Board ("OPSB"), the owner, contracted with Woodrow Wilson Construction, LLC ("Woodrow Wilson"), a general contractor, for the construction of an elementary school ("project").1 The contract was recorded on September 14, 2012.2 Western *309Surety Company ("Western Surety") provided the statutory performance and payment bonds to Woodrow Wilson for the project.

Woodrow Wilson subcontracted with Amtek of Louisiana, Inc. ("Amtek") for site work on the project.3 Amtek then subcontracted with Baton Rouge Winwater Works Co. ("BR Winwater"), a materialman, to supply PVC storm drainage pipe, in-line drains, and pipe for installation into the project. Woodrow Wilson, Amtek, and BR Win water executed a joint check agreement, whereby Woodrow Wilson agreed to pay Amtek and BR Winwater by joint check for all services rendered in connection with the project. Although executed by Woodrow Wilson in October 2012, the joint check agreement was not fully executed by all the parties and received by Woodrow Wilson until October 30, 2014.

BR Winwater made ten deliveries of materials to Amtek, from March 25, 2014 to June 11, 2014. It is undisputed that BR Winwater's materials were delivered, received in "good condition" by Amtek, and installed into the project. It is further undisputed that Amtek billed Woodrow Wilson for BR Winwater's materials; Woodrow Wilson billed OPSB for all materials furnished by BR Winwater; and, OPSB fully paid Woodrow Wilson for the materials supplied by BR Winwater.

At some point during the project, a dispute arose between Woodrow Wilson and Amtek. After sending notices of default to Amtek on March 14, 2014 and June 10, 2014, Woodrow Wilson terminated Amtek's subcontract on June 20, 2014. On August 14, 2014, Amtek filed a claim of lien or privilege on the project in the amount of $280,272.15, which included unpaid amounts owed to BR Winwater, as well as unpaid amounts owed to other subcontractors of Amtek.4

It is undisputed that Woodrow Wilson, Western Surety, and Amtek have made no payments to BR Winwater for the materials it supplied for the project. Accordingly, BR Winwater transmitted notice of nonpayment to Woodrow Wilson via certified mail on October 29, 2014. BR Winwater transmitted a second notice of nonpayment to Woodrow Wilson via facsimile on November 24, 2014.

A certificate of substantial completion for the project was recorded on December 2, 2014.5

BR Winwater filed a statement of claim on January 5, 2015, alleging it was owed $79,240.00 for the materials it supplied to Amtek on the project, plus the cost of filing the statement of claim.6 Also on January 5, 2015, BR Winwater transmitted notices of filing its statement of claim as well as demand letters to OPSB, Woodrow *310Wilson, and Western Surety via certified mail. On January 27, 2015, BR Winwater transmitted a second demand letter to Western Surety, via certified mail.

On April 1, 2015, Woodrow Wilson filed a petition for damages and breach of contract against Amtek.7 Amtek answered Woodrow Wilson's suit and filed a reconventional demand against Woodrow Wilson and Western Surety, alleging that it had not been paid by Woodrow Wilson for the work it performed on the project.

On October 1, 2015, BR Winwater filed a petition for damages against Woodrow Wilson, Amtek, and Western Surety.8 Amtek answered BR Winwater's suit and filed a cross claim against Woodrow Wilson and Western Surety for amounts due and for indemnification from BR Winwater's claim.

The Woodrow Wilson Suit and the BR Winwater Suit were ultimately consolidated and transferred to Division "D" of the 19th Judicial District Court ("JDC"), pursuant to a judgment signed on October 5, 2016. Prior to trial, Woodrow Wilson and Amtek stipulated in camera that the claims between Woodrow Wilson and Amtek (the subject of the Woodrow Wilson Suit and Amtek's cross claim in the BR Winwater Suit) would be reserved pending the resolution of a separate, related lawsuit in Civil District Court in Orleans Parish (the "Beverly Suit").9

Following a bench trial held on January 31, 2017, solely on BR Winwater's claims against Woodrow Wilson, Western Surety, and Amtek, the trial court rendered judgment on March 9, 2017, stating in pertinent part:

The court finds that no notice was given to Woodrow Wilson by BR Winwater that Amtek had defaulted on its payment obligations until after a lapse of time for issuing a notice of non payment. Therefore, Woodrow Wilson and its surety Western have no obligations to pay Amtek?s [sic ] debt to Winwater. Nonetheless, Winwater would have rights over and against Amtek for the amount of unpaid invoices. Judgment to be signed accordingly.

The trial court signed a judgment in accordance with its ruling on May 2, 2017, in favor of BR Winwater and against Amtek, in the amount of $79,240.90, plus interest and costs. The judgment dismissed BR Winwater's claims against Woodrow Wilson and Western Surety, with prejudice. BR Winwater and Amtek now appeal the May 2, 2017 judgment of the trial court.

ASSIGNMENTS OF ERROR

In its sole assignment of error, BR Winwater contends the trial court erred in dismissing its claims against Woodrow Wilson and Western Surety under La. R.S. 38:2242(B) and La. R.S. 38:2247.

Amtek assigns three errors to the trial court's judgment:

1. The Trial Court erred in dismissing BR Winwater's claim against [Woodrow] Wilson, general contractor, and Western [Surety], as [Woodrow] Wilson's surety, under La. R.S. 38:2242(B) and 2247.
2. The Trial Court erred in granting judgment against Amtek on BR Winwater's *311claims when the evidence showed that [Woodrow] Wilson was paid by the OPSB for the materials, but never paid Amtek for the materials supplied by BR Winwater. [Woodrow] Wilson violated La. R.S. 9:2784 by failing to pay BR Winwater and/or Amtek after it was paid by the owner.
3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
256 So. 3d 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodrow-wilson-constr-llc-v-amtek-of-la-inc-lactapp-2018.