Bear Indus., Inc. v. Hanover Ins. Co.

241 So. 3d 1159
CourtLouisiana Court of Appeal
DecidedJanuary 4, 2018
Docket2017 CA 0301
StatusPublished
Cited by3 cases

This text of 241 So. 3d 1159 (Bear Indus., Inc. v. Hanover Ins. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bear Indus., Inc. v. Hanover Ins. Co., 241 So. 3d 1159 (La. Ct. App. 2018).

Opinion

McCLENDON, J.

*1161In this matter, a contractor and its surety appeal a trial court judgment in favor of a supplier of materials used on a construction project. For the reasons that follow, we affirm.

FACTUAL AND PROCEDURAL HISTORY

Bear Industries, Inc. (Bear) supplied limestone and sand materials to Amtek of Louisiana, Inc. (Amtek), a subcontractor on the New Roads Wal-Mart Supercenter project. The contractor was Hudson Construction Company of Tennessee (Hudson). Hanover Insurance Company (Hanover), as surety for Hudson, furnished the payment bond for the project. Bear, Hudson, and Amtek executed a Joint Check Agreement, and all payments to Bear on the project were by joint check from Hudson.

Bear sold the materials to Amtek from May 21, 2012, to July 12, 2013. It is undisputed that the materials were delivered. However, at some point, a dispute arose between Amtek and Hudson, and Hudson stopped making payments.1 Bear filed a Statement of Claim and Privilege on September 16, 2013, alleging it was owed a total of $259,148.00 for the materials furnished and installed on the project. Payment was still not made, and on March 6, 2014, Bear filed suit against Amtek and Hanover under the Private Works Act. In response, Amtek filed a cross-claim against Hanover and Hudson, claiming an unpaid amount of $701,296.52. Hudson filed a peremptory exception raising the objection of prematurity, claiming that under its subcontract with Amtek all disputes had to be arbitrated. On July 9, 2014, the trial court granted the exception as to Hudson and ordered that Hudson and Amtek arbitrate their disputes.

The arbitration was conducted in April of 2016, and a Ruling was rendered on June 1, 2016.2 Thereafter, Hudson and Hanover filed a Motion to Confirm the Arbitration Award, and Amtek filed a motion to confirm as well. Following a hearing on August 8, 2016, the trial court rendered judgment, and on August 24, 2016, the trial court signed its judgment, confirming the arbitration award.

Thereafter, on August 29, 2016, the trial court held a bench trial on Bear's claims. On October 20, 2016, the trial court read its reasons for judgment into the record, and on October 31, 2016, the trial court signed a judgment in favor of Bear and against Hanover and Amtek in the full sum of $259,914.80. The trial court also found Hanover obligated to Bear in the amount of $25,914.80 for attorney fees and found Amtek obligated to Bear in the amount of $40,000.00 for attorney fees. Lastly, the trial court found Amtek obligated to Hudson in the amount of *1162$40,000.00 for attorney fees expended in defense of Bear's claim. Hudson and Hanover then filed a suspensive appeal, asserting several assignments of error, essentially arguing that Bear's lien did not comply with the Private Works Act and therefore was invalid. Hudson and Hanover additionally assert that the trial court erred in limiting Hudson's recovery for attorney fees from Amtek to $40,000.00.

DISCUSSION

The Louisiana Private Works Act, LSA-R.S. 9:4801, et seq. , was enacted to facilitate the construction of improvements on immovable property; it serves this purpose by granting certain rights to enumerated persons to facilitate recovery of the costs of their work from an owner with whom they lack privity of contract. Wholesale Electric Supply Company v. Honeywell International, Inc. , 16-1180 (La.App. 1 Cir. 5/11/17), 221 So.3d 98, 101. The Private Works Act is in derogation of general contract law; therefore, it must be strictly construed. In interpreting the Private Works Act, care must be taken not to overlook the legislative intent and fundamental aim of this act, which is to protect materialmen, laborers, and subcontractors who engage in construction and repair projects. Bernard Lumber Co., Inc. v. Lake Forest Const. Co., Inc. , 572 So.2d 178, 181 (La.App. 1 Cir. 1990).

Louisiana Revised Statutes 9:4802 clearly defines those persons granted a claim or privilege pursuant to the Act and provides, in pertinent part:

A. The following persons have a claim against the owner and a claim against the contractor to secure payment of the following obligations arising out of the performance of work under the contract:
* * *
(3) Sellers, for the price of movables sold to the contractor or a subcontractor that become component parts of the immovable, or are consumed at the site of the immovable, or are consumed in machinery or equipment used at the site of the immovable.
* * *
B. The claims against the owner shall be secured by a privilege on the immovable on which the work is performed.
C. The owner is relieved of the claims against him and the privileges securing them when the claims arise from the performance of a contract by a general contractor for whom a bond is given and maintained as required by R.S. 9:4812 and when notice of the contract with the bond attached is properly and timely filed as required by R.S. 9:4811.

In their first assignment of error, Hudson and Hanover assert that the trial court erred in interpreting LSA-R.S. 9:4811. Specifically, they assert that the Notice of Commencement filed by Wal-Mart in the public records of Pointe Coupee Parish on May 31, 2012, did not contain the statutory requirements of a notice of contract under LSA-R.S. 9:4811. Therefore, according to Hudson and Hanover, the trial court erred in finding that the Notice of Commencement qualified as a notice of contract so that Bear's lien was untimely filed and Bear lost its privilege. To the contrary, Bear asserts that the trial court correctly interpreted LSA-R.S. 9:4811 and found that a timely notice of contract was properly filed.

Louisiana Revised Statutes 9:4811 provides, in relevant part:

A. Written notice of a contract between a general contractor and an owner shall be filed as provided in R.S. 9:4831 before the contractor begins work, as defined by R.S. 9:4820, on the immovable. The notice:
(1) Shall be signed by the owner and contractor.
*1163(2) Shall contain the legal property description of the immovable upon which the work is to be performed and the name of the project.
(3) Shall identify the parties and give their mailing addresses.
(4) Shall state the price of the work or, if no price is fixed, describe the method by which the price is to be calculated and give an estimate of it.
(5) Shall state when payment of the price is to be made.
(6) Shall describe in general terms the work to be done.
B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
241 So. 3d 1159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bear-indus-inc-v-hanover-ins-co-lactapp-2018.