United States Ex Rel. E. C. Ernst, Inc. v. Curtis T. Bedwell & Sons, Inc.

506 F. Supp. 1324, 28 Cont. Cas. Fed. 81,295, 1981 U.S. Dist. LEXIS 9395
CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 2, 1981
DocketCiv. A. 79-4624
StatusPublished
Cited by9 cases

This text of 506 F. Supp. 1324 (United States Ex Rel. E. C. Ernst, Inc. v. Curtis T. Bedwell & Sons, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. E. C. Ernst, Inc. v. Curtis T. Bedwell & Sons, Inc., 506 F. Supp. 1324, 28 Cont. Cas. Fed. 81,295, 1981 U.S. Dist. LEXIS 9395 (E.D. Pa. 1981).

Opinion

OPINION

I. Introduction

JOSEPH S. LORD, III, Chief Judge.

This is a Miller Act case. 40 U.S.C. § 270a et seq. Defendant Bedwell is the general contractor on a construction project. Plaintiff was its electrical subcontractor. In Count I of its complaint, plaintiff seeks $249,960.56 in damages which allegedly resulted from Bedwell’s refusal to pay for services and materials furnished to Bedwell. In Counts II and III of its complaint, plaintiff seeks to recover in excess of $50,000 in damages which allegedly were the natural consequence of Bedwell’s material breach of this subcontract. This sum includes loss of profits, the cost of demobilization, unbilled services, and other damages. Bedwell denies that it failed to pay plaintiff what plaintiff was entitled to receive under the contract. Furthermore, Bedwell avers that plaintiff materially breached the subcontract when it, inter alia, (a) failed to pay plaintiff’s bills of its suppliers and materialmen, (b) went insolvent, and (c) failed to furnish performance and payment bonds. Bedwell therefore argues that it lawfully terminated the subcontract.

Bedwell has counterclaimed for the damages it suffered as the result of plaintiff’s alleged material breach of the subcontract. Bedwell seeks damages in an amount in excess of $200,000 for this breach. Plaintiff’s defense to Bedwell’s counterclaim is that Bedwell’s earlier material breach of the contract—the breach that comprises the nucleus of its initial complaint—excused plaintiff from adhering to its contractual obligations. Plaintiff also asserts that Bed-well prevented it from performing its contractual obligations.

Each party has filed a motion for summary judgment. The defendants’ joint motion for summary judgment against plaintiff as to all counts of plaintiff’s complaint raises one issue: did Bedwell properly and lawfully terminate its subcontract *1326 with plaintiff? 1 For the reasons which follow, I have concluded that there is a material issue of fact as to whether Bedwell was in breach before it terminated the subcontract. I shall therefore deny defendants’ motion.

Plaintiff moves for partial summary judgment with regard to Count I of Bed-well’s counterclaim. It contends that Bed-well’s damages were strictly limited by the contract. I shall deny plaintiff’s motion.

II. Facts

On December 19, 1977, Bedwell contracted with the United States Department of the Navy, Naval Facilities Engineering Command, for the construction of a Propeller Facility at the Philadelphia Naval Shipyard. Bedwell then entered into a subcontract with plaintiff for the performance of the electrical work. This subcontract, dated January 3, 1978, provided that Bedwell could request payment and performance bonds from plaintiff. 2 Bedwell did not request a bond when the parties executed the subcontract; nor did it request one when plaintiff began performance in February, 1978. However, in the fall of 1978—after the project was substantially underway— Bedwell learned that plaintiff’s accounts with its suppliers and materialmen were in arrears. Affidavit of Curtis T. Bedwell. Consequently, 3 on October 24, 1978, it requested that plaintiff furnish the necessary bonds. The overall subcontract project was more than fifty percent complete at this point. Affidavit of Robert L. Shreves, ¶ 18. On November 22, 1978, plaintiff notified Bedwell that it was unable to obtain the bonds at that time from its bonding company. Bedwell orally repeated its request for bonds in December, 1978. Deposition of Gerald Benson at 22. 4 Again plaintiff failed to provide the requested bonds.

In early December, 1978, plaintiff filed a Petition for Arrangement pursuant to Chapter XI of the Bankruptcy Act, 11 U.S.C. § 701 et seq. By this time, plaintiff’s past due supplier and materialmen accounts totalled over $130,000. Finally, on December 27, 1978, Bedwell gave plaintiff forty-eight hours written notice of termination. 5 It was only at this point that plaintiff ceased construction on the project.

At the time Bedwell terminated its subcontract with plaintiff, it had paid plaintiff $351,661.96 out of the total subcontract cost of $853,000. After plaintiff ceased construction on the project, Bedwell retained sixteen other subcontractors to complete the electrical work covered by plaintiff’s subcontract. The subcontractors satisfactorily finished the work in November, 1979, charging Bedwell approximately $580,000.

III. Defendants’ Joint Motion for Summary Judgment

A. Preliminary Statement

Defendants argue that Bedwell lawfully terminated the subcontract because plaintiff materially breached the terms of the subcontract: (a) when it failed to furnish the bond; or (b) when it filed a Petition for *1327 Arrangement; or (c) when it failed to pay bills for labor and material as they became due. In order to grant summary judgment in defendants’ favor it is only necessary to conclude that defendants have “show[n] that there is no genuine issue as to any material fact and that [they are] entitled to a judgment as a matter of law,” Fed.R. Civ.P. 56(c), with respect to any one of these three contentions. Defendants have not met this burden, for there remains a controverted material fact: did Bedwell breach the subcontract by refusing to make prompt progress payments to plaintiff. I shall therefore deny the defendants’ motion for all the relief asked. However, if Bed-well prevails on this disputed issue at trial, I hold as a matter of law that plaintiff materially breached the subcontract when it filed a Petition for Arrangement. 6 I have adjudicated this latter issue pursuant to the command of Fed.R.Civ.P. 56(d); in this case I can “practicably] ascertain that this material fact[ ] [plaintiff’s breach] exist[s] without substantial controversy.” Fed.R. Civ.P. 56(d). I can narrow and thereby simplify the issues for trial.

B. Discussion

1. Bedwell’s breach of the subcontract

Plaintiff avers that it “repeatedly made demands upon defendant, Bedwell, for progress payments due and owing as per the terms of [the] contract, which defendant refused to pay, thereby materially breaching the contract.” Complaint, ¶ 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shen Valley Masonry, Inc. v. S. P. Cahill & Associates, Inc.
57 Va. Cir. 189 (Virginia Circuit Court, 2001)
Bernstein v. Donaldson (In Re Insulfoams, Inc.)
184 B.R. 694 (W.D. Pennsylvania, 1995)
Bohm v. Commerce Union Bank of Tennessee
794 F. Supp. 158 (W.D. Pennsylvania, 1992)
Lubecki v. Omega Logging, Inc.
674 F. Supp. 501 (W.D. Pennsylvania, 1987)
McKinstrey v. Shakey's Inc.
755 F.2d 932 (Sixth Circuit, 1985)
Consolidated Rail Corp. v. Delaware & Hudson Railway Co.
569 F. Supp. 26 (E.D. Pennsylvania, 1983)
Draft Systems, Inc. v. Rimar Manufacturing, Inc.
524 F. Supp. 1049 (E.D. Pennsylvania, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
506 F. Supp. 1324, 28 Cont. Cas. Fed. 81,295, 1981 U.S. Dist. LEXIS 9395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-e-c-ernst-inc-v-curtis-t-bedwell-sons-inc-paed-1981.