Simmonds Precision Products, Inc. v. United States

546 F.2d 886, 23 Cont. Cas. Fed. 80,884, 212 Ct. Cl. 305, 1976 U.S. Ct. Cl. LEXIS 331
CourtUnited States Court of Claims
DecidedDecember 15, 1976
DocketNo. 327-74
StatusPublished
Cited by11 cases

This text of 546 F.2d 886 (Simmonds Precision Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simmonds Precision Products, Inc. v. United States, 546 F.2d 886, 23 Cont. Cas. Fed. 80,884, 212 Ct. Cl. 305, 1976 U.S. Ct. Cl. LEXIS 331 (cc 1976).

Opinion

Per Curiam :

This case comes before the court on plaintiff’s request, filed February 9, 1976, for review by the court of the recommended decision of Trial Judge Lloyd Fletcher, filed January 6, 1976, pursuant to Rule 166(c), on plaintiff’s motion and defendant’s cross-motion for summary judgment and on defendant’s motion, filed May 10,1976, that the court adopt the recommended decision of the trial judge. Upon consideration thereof, together with the briefs and oral argument of counsel, since the court agrees with the trial judge’s recommended decision, as hereinafter set forth, it hereby affirms and adopts the decision as the basis for its judgment in this case. It is, therefore, concluded that plaintiff has failed to establish that the decision of the Armed Services Board of Contract Appeals was legally erroneous, arbitrary, capricious or unsupported by substantial evidence. Accordingly, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is allowed and plaintiff’s petition is dismissed. Judgment is entered for defendant on its counterclaim in the amount of $4,321.21.

OPINION OE TRIAL JUDGE

Fletcher, Trial Judge:

In this contract dispute, the plaintiff, Simmonds Precision Products, Inc., pursuant to the familiar standards of the Wunderlich Act (41 TJ.S.C. §§ 321-22), challenges the finality of the adverse decision by the Armed Services Board of Contract Appeals and seeks recovery of $11,087.97 withheld by the Government as [309]*309liquidated damages under multiple contracts for the supply of aircraft parts and equipment. Simmonds’ appeal from the contracting officer’s adverse decision was not only denied by the Armed Services Board of Contract Appeals; the Board further allowed a counterclaim 'by the Government for $4,324.21 in additional liquidated damages not previously withheld. The Board also rejected a $22,000 claim by plaintiff for its alleged additional costs incurred because of Government actions which it says amounted to a constructive acceleration. Since the Board’s disposition of the liquidated damage claim appears clearly correct on this record, its findings and decision on those claims are sustained for reasons set forth below. On the claim of constructive 'acceleration, the plaintiff’s petition must be dismissed.

The facts involved will be briefly summarized. Simmonds had been awarded some 36 indefinite quantity supply contracts for aircraft parts and equipment with various delivery dates ranging from December 27,1970, through September 30, 1971. For reasons mentioned below, by mid-June 1971, Simmonds was either already delinquent, or about to become so, in its deliveries under all of these contracts. By then the Government had become so concerned over the imminent delinquencies that it sent its procurement contracting officer (PCO), William Rehrer, to the Simmonds plant for the purpose of investigation and negotiation of new delivery dates. Rehrer spent the afternoon of June 15,1971, discussing with plaintiff’s personnel new delivery dates for 17 delinquent contracts under which plaintiff had indicated it would be •unable to make timely deliveries. Negotiations continued into June 16, 1971 with Rehrer pressing hard for firm delivery dates and stating that as a part of any extension of such dates, the Government would require the addition of liquidated damages provisions to not only the delinquent contracts but also to those contracts which while not yet delinquent might well become so. Paul C. Hill, Esquire, plaintiff’s general counsel and manager, joined the negotiations and insisted that any revised delivery dates could not be firm dates, but merely the best estimates that could be projected at the time. Rehrer responded that he had to have firm delivery dates determined by the following day when [310]*310be would be departing tbe plant, and that if firm dates were not set 'by that time, be might have to put plaintiff’s name on tbe so-called “Contractor Experience List,” i.e., a list of those contractors whose capability must be evaluated prior to the award of any contract.

On June 17, the parties met again in a final effort to work out a specific agreement. At this conference, plaintiff did provide new delivery dates, many of which it asserted were necessarily “padded” to insure timely compliance. At this time, plaintiff’s representative also described the reasons for the delays it had experienced without, however, attempting to assess the specific impact of any particular delay.

'Several of the delays which had seriously handicapped plaintiff were beyond its control, and were given sympathetic consideration 'by the Government. These delays included: (1) an anti-trust suit filed against the company by the Government and a union (IUE), as a .result of which Simmonds had to divest itself of part of its operations; (2) interference by the union with attempts by plaintiff to sell part of its business, accompanied by walkouts and slowdowns; (3) an injunction obtained against the company which had delayed it for over a year in moving its operations from Long Island City to Vergennes, Vermont; and (4) the failure of several of Simmonds’ suppliers to fill orders placed with them. Plaintiff claimed that these delays were of sufficient magnitude as to justify a four to six-month extension in the delivery dates, but the Government did not agree. The Government representative instead countered with a proposal of a two to three-month extension as more reasonable.

The time of extension was not the only point of dispute in these negotiations. Another problem revolved around the liquidated damages provisions which the Government demanded in exchange for any time extensions. Defendant had originally insisted upon a rate of one percent per day per delinquent item shipped, with a maximum rate of 25 percent. But plaintiff was able to bargain these rates down to one-tenth of one percent a day per delinquent item, not to exceed 13 percent. With respect to liquidated damages, two different sets of contracts were involved, one set assigned originally to the Long Island City plant and already de[311]*311linquent, and the other set assigned to the Yergennes, Vermont plant and not yet delinquent. On the latter set of non-delinquent contracts, the parties agreed to a liquidated damages rate of one-twentieth of one percent per delinquent item, with a maximum of 13 percent.

The clause, as finally included, provided for liquidated damages as follows:

* * * [/«.] accordance with ASPR 7-603.39 at a rate of y10 of 1% per day [y20 of 1% for non-delinquent contracts] with a not to exceed maximum rate of thirteen (13) percent. [Emphasis supplied.]

However, the ASPR provision referenced in this clause was the wrong provision. ASPR 7-603.39 is for “Termination for Default-Damages for Delay-Time Extensions,” and is designed for use in fixed-price construction contracts rather than for fixed-price supply contracts such as the present ones.

Plaintiff’s contract manager watched the contracting officer include the erroneous ASPR in the contracts and asked, “Is that the clause you are putting in?” The contracting officer merely answered in the affirmative and nothing more was said about it between the parties. Even when the contract modifications were formally executed, no one raised a question concerning the erroneous ASPR reference.

Plaintiff again became delinquent in the performance of its contracts after the adoption of the June 17 modification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolidated Industries , Inc. v. United States
195 F.3d 1341 (Federal Circuit, 1999)
Jana, Inc. v. United States
40 Cont. Cas. Fed. 76,862 (Federal Claims, 1995)
Tomoegawa (U.S.A.), Inc. v. United States
763 F. Supp. 614 (Court of International Trade, 1991)
Kelley v. United States
36 Cont. Cas. Fed. 75,771 (Court of Claims, 1989)
DiGiorgio v. United States
8 Ct. Int'l Trade 192 (Court of International Trade, 1984)
Federal Deposit Ins. Corp. v. United States
527 F. Supp. 942 (S.D. West Virginia, 1981)
Inforex, Inc.
650 F.2d 286 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
546 F.2d 886, 23 Cont. Cas. Fed. 80,884, 212 Ct. Cl. 305, 1976 U.S. Ct. Cl. LEXIS 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simmonds-precision-products-inc-v-united-states-cc-1976.