Consolidated Industries , Inc. v. United States

195 F.3d 1341, 1999 U.S. App. LEXIS 28905, 1999 WL 997773
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 4, 1999
Docket98-5167
StatusPublished
Cited by19 cases

This text of 195 F.3d 1341 (Consolidated Industries , Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Industries , Inc. v. United States, 195 F.3d 1341, 1999 U.S. App. LEXIS 28905, 1999 WL 997773 (Fed. Cir. 1999).

Opinion

FRIEDMAN, Senior Circuit Judge.

This appeal challenges a decision of the Court of Federal Claims that upheld a contracting officer’s default termination of the appellant Consolidated Industries, Inc. (“Consolidated”)^ government contract for failure to meet the contractual delivery schedules. We affirm.

I

The pertinent facts, as set forth in the opinion of the Court of Federal Claims and in the record, are undisputed.

In March 1988 Consolidated entered into a contract with the Army to produce battery assemblies for an anti-tank weapons system. The contract had been set aside for a small business concern (which Consolidated was, Tr. 84-85), pursuant to Section 8(a) of the Small Business Act, 15 U.S.C. 637(a) (1988). The government issued a number of orders for delivery of specified numbers of assemblies on speci *1343 fied dates, and made progress payments to Consolidated during the performance of the contract.

Between 1988 and 1993 Consolidated failed to meet several delivery dates, which were extended. The government also found flaws in some of the battery assemblies that Consolidated produced.

In October 1994, the parties agreed to modify the contract, which was provided by a written modification (“the Modification”) under which:

1. Consolidated agreed to ship 1800 battery assemblies “in order to liquidate progress payments” already made. Sixty were to be shipped in January 1995, 100 a month from February 1995 to June 1996, and forty in January 1996.

2. The parties agreed to a no cost termination of the balance of the contract.

The Modification included the following provisions:

The contractor unconditionally waives any charges against the government arising under this order/contract or by reason of cancellation, including, without limitation, all obligations of the government to make further payments or to carry out any further undertakings under the cancelled portion of the contract. The government acknowledges that the contractor has no obligation to perform further work or services or to make further deliveries under the cancelled portion of the contract. Nothing in this paragraph affects any other covenants, terms, or conditions of the contract.
The parties agree that this modification constitutes full, final and complete settlement, satisfaction and accord for any and all claims arising out of this order/contract, whether past or present.

Consolidated failed to make the January and February deliveries the Modification required, and the contracting officer terminated the contract for default. The contracting officer made detailed findings about the performance of the contract and her reasons for termination. The contracting officer described her consideration of seven specific factors the Federal Acquisition Regulations (“FAR”) require a contracting officer to consider in determining whether to terminate for default. As those regulations required, the Commanding General of the military entity involved (General Link) approved the default termination.

Consolidated then filed the present ease in the Court of Federal Claims seeking to convert the default termination into one for the convenience of the government. It sought damages of $2,417,494.13, based on the government’s alleged breach of the contract. The government filed a counterclaim for $515,062.12, covering the progress payments Consolidated had failed to liquidate by delivering battery assemblies pursuant to the Modification.

After trial, the Court of Federal Claims held that the contracting officer properly had terminated the contract for default and dismissed the complaint. The court ruled that the Modification constituted an accord and satisfaction of Consolidated’s “claims of increased costs due to alleged defective specifications,” and that “the Contracting Officer exercised reasonable discretion in terminating a contract for default.” With respect to the government’s counterclaim for unliquidated progress payments, the court stated that Consolidated “conceded the outstanding progress payments, and stated at trial that it has no defenses if we rule that the modification acted as an accord and satisfaction. We grant defendant’s counterclaim on the basis of that representation.”

II

The contract incorporated the standard default termination provision contained in FAR section 52.249-8, which permits such termination for specified defaults by the contractor. See 48 C.F.R. § 52.249-8. The contracting officer has broad discretion to determine whether to terminate a contract for default and we will only overturn that decision, if it is “arbitrary, capricious or constitutes an *1344 abuse of discretion.” McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1326 (Fed. Cir.1999) (citing Darwin Constr. v. United States, 811 F.2d 593, 598 (Fed.Cir.1987)). We agree with the Court of Federal Claims that the contracting officer’s decision to terminate this contract for default “was not arbitrary, capricious, or an abuse of discretion.”

The default for which the contracting officer terminated the contract was “the specific failure of the contractor to meet the contractual delivery date of 30 Jan 95 and 28 Feb 95” agreed to in the Memorandum. As the Court of Federal Claims noted, “[t]he Government may terminate a contract for failure to deliver supplies within the time specified in the contract.” FAR § 52.249-8(a)(l) (“The Government may ... terminate this contract ... if the contractor fails to(i) Deliver the supplies ... within the time specified in this contract or any extension....”). “[Wjhere a contractor fails to comply with contract delivery schedules the contract may be terminated, pursuant to the default clause.... ” Churchill Chem. Corp. v. United States, 221 Ct.Cl. 284, 602 F.2d 358, 362 (Ct.Cl.1979).

Consolidated seeks to excuse its failure to meet the contractual delivery dates by invoking the “excusable delay” exception to this principle. See 48 C.F.R. § 49.402-3(j) (1998); Simmonds Precision Prods., Inc. v. United States, 212 Ct.Cl. 305, 546 F.2d 886, 890-91 (Ct.Cl.1976); DeVito v. United States, 188 Ct.Cl.979, 413 F.2d 1147, 1151 (Ct.Cl.1969). It claims that its delays were attributable to the government’s own deficiencies of providing defective specifications and failing to aid it in correcting the defects in its product.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sungjee Construction Co., Ltd.
Armed Services Board of Contract Appeals, 2023
Frazier Investments, Inc. d/b/a Optimum Construction
Armed Services Board of Contract Appeals, 2023
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Spodek v. United States Postal Service
58 F. Supp. 3d 728 (N.D. Texas, 2012)
Emiabata v. United States
102 Fed. Cl. 787 (Federal Claims, 2012)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)
Takota Corp. v. United States
90 Fed. Cl. 11 (Federal Claims, 2009)
Pinckney v. United States
88 Fed. Cl. 490 (Federal Claims, 2009)
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Beard v. District of Columbia Housing Authority
584 F. Supp. 2d 139 (District of Columbia, 2008)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Lanterman v. United States
75 Fed. Cl. 731 (Federal Claims, 2007)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
Specialty Transportation, Inc. v. United States
57 Fed. Cl. 1 (Federal Claims, 2003)
O'Connor v. United States
50 Fed. Cl. 285 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
195 F.3d 1341, 1999 U.S. App. LEXIS 28905, 1999 WL 997773, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-industries-inc-v-united-states-cafc-1999.