Pinewood Realty Ltd. Partnership v. United States

617 F.2d 211, 223 Ct. Cl. 98, 1980 U.S. Ct. Cl. LEXIS 97
CourtUnited States Court of Claims
DecidedMarch 19, 1980
DocketNo. 419-78
StatusPublished
Cited by14 cases

This text of 617 F.2d 211 (Pinewood Realty Ltd. Partnership v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinewood Realty Ltd. Partnership v. United States, 617 F.2d 211, 223 Ct. Cl. 98, 1980 U.S. Ct. Cl. LEXIS 97 (cc 1980).

Opinion

SMITH, Judge,

delivered the opinion of the court:

Plaintiff, Pinewood Realty Limited Partnership,1 an organization existing under the laws of the State of New York, asserts claims against defendant for breach of contract. Both parties have filed motions for summary judgment, on which we have heard oral argument.

On May 18, 1977, plaintiffs predecessor in interest, Drake Realty Associates (Drake), submitted, in writing, the high bid to purchase Pinewood Apartments2 of Metairie, Louisiana, from the U.S. Department of Housing and Urban Development (HUD), which offer was accepted on May 24, 1977. On June 16,1977, Drake requested authority to assign the contract to plaintiff, which assignment took place on July 12, 1977, after appropriate consent thereto was granted on July 5. Prior to the assignment on June 28, 1977, a suit was filed by one Bradley in the United States District Court for the Eastern District of Louisiana seeking to enjoin the sale of Pinewood Apartments by HUD, and HUD sent the purchaser a copy of the Bradley complaint on [101]*101July 5, 1977. On July 7, 1977, HUD sent a letter to Drake confirming a "postponement” of the original closing date from July 25, 1977, to August 24, 1977, in which Drake concurred.3 A notice of lis pendens was filed against the property on July 11, 1977, because of the Bradley suit. On August 16, 1977, HUD confirmed by letter a further "postponement” of closing until September 26, 1977, on which Pinewood Realty noted its acceptance.

On September 23, 1977, HUD again suggested that the closing date be "postponed” until October 26, 1977. On September 26, 1977, Pinewood Realty’s attorney, by letter, consented to this final "extension” but stated expressly that its consent would not act to vitiate its rights to damages and lost profits incurred by Pinewood Realty as a result of the delays from the original closing date until actual closing. On October 4, 1977, HUD responded by informing plaintiff that it was accepting the "extension” but not admitting the liability of the Government for damages or lost profits due to the delays. On October 17, 1977, HUD reduced the purchase price by $9,000 for maintenance repair work required on the project.

On October 25, 1977, the district court dismissed the Bradley suit4 and closing was concluded on October 27, 1977, in the New Orleans offices of HUD.

On November 14, 1977, plaintiff filed an "administrative notice of claim” against defendant for contract damages. On December 15, 1977, plaintiff was notified that HUD had no administrative procedure to process Pinewood Realty’s administrative claim and that defendant considered that plaintiff had no right to damages.

This suit followed, in which plaintiff alleges that it was' ready, willing, and able to perform the terms of the contract of sale on or before the original closing date and that defendant caused plaintiff harm by not closing on the original date set, July 25, 1977. Plaintiff seeks damages for delay, lost profits, and additional expenses incurred. For reasons stated below, we hold that plaintiff is entitled to a partial recovery on its claims.

[102]*102I.

The threshold question presented to us is whether we should apply federal or Louisiana law in determining the rights of the parties to this contract. Plaintiff argues that since the contract deals with the sale of land, and since the place designated for the execution and performance of the contract is Louisiana, the law of that state should apply. If the resolution of this dispute were to affect the underlying property system in Louisiana, that state might have a significant interest in this contract, but that is not the case, and we reject this argument by plaintiff and apply federal law. There is no question in the present case as to the extent of the property interest conveyed by HUD to plaintiff, but merely as to the rights and obligations of the parties under a contract with the federal government. Such contracts are normally governed by a uniform federal law and not by the particular laws of the states where they are made or performed, except in most unusual circumstances.5

II.

Plaintiff bases its claims on the following clause of the contract of purchase:

9. Time is of the essence of this contract. The sale shall be closed within 60 days following execution hereof by the Seller at the offices of the Seller, or at such other time and place as may be agreed on by the parties in writing. Should the Purchaser fail or refuse to perform his part of the contract promptly at the time or in the manner herein specified, the earnest money deposited herewith shall, at the option of the Seller, be retained as liquidated damages.

It is true, as plaintiff claims, that the contract specifically provides that time is of the essence, but it is equally apparent that the first two "extensions” or "postponements” restated the time of closing and were agreed to in writing by the parties. This, too, was in accordance with a [103]*103specific provision in clause 9 of the contract. Thus, plaintiff is hardly in a position to claim a breach arising out of these two postponements on the basis that time was of the essence, when such modifications were a result of mutual consent.

Plaintiffs claim for damages would fail even if the two postponements had not formally been agreed to. As we said in DeVito:6

Time is of the essence in any contract containing fixed dates for performance. When a due date has passed and the contract has not been terminated for default within a reasonable time, the inference is created that time is no longer of the essence so long as the constructive election not to terminate continues and the contractor proceeds with performance. * * * [Emphasis supplied.]

If plaintiff truly thought these postponements were actual breaches of the contract, under federal law plaintiff had a duty to call upon HUD to meet its obligations. Without such an assertion, plaintiff lost its right to rescission and cannot deny the existence of the contract.7 It is inconsistent for plaintiff to claim that "[t]ime is of the essence” in this contract and repeatedly to allow HUD to postpone the closing date. The purchaser’s acquiescence in the first two extensions could only be seen as a waiver of its right to terminate the contract. The purchaser also failed during the first two extensions to make any express reservation of its "right” to damages. Considering the language of clause 9 of the contract, and in the absence of contrary evidence in the record, it can only be inferred that the first two postponements resulted from the mutual agreement of the parties pursuant to the contract.

III.

The third postponement or extension is a different matter. By agreement in writing the closing date had been reset for September 26, 1977. In responding to HUD’s [104]*104suggestion of a further 30-day postponement to October 26, 1977, plaintiff for the first time put HUD on notice that it was contemplating a suit for damages on the basis of the repeated "extensions” of the closing date. If plaintiff had any earlier subjective, unexpressed intentions in this respect they were not binding on HUD.8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Detroit Housing Corp. v. United States
55 Fed. Cl. 410 (Federal Claims, 2003)
Dangfeng Shen Ho v. United States
49 Fed. Cl. 96 (Federal Claims, 2001)
Price v. United States
46 Fed. Cl. 640 (Federal Claims, 2000)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
Nematollahi v. United States
38 Fed. Cl. 224 (Federal Claims, 1997)
Morris v. United States
40 Cont. Cas. Fed. 76,832 (Federal Claims, 1995)
Alaska American Lumber Co. v. United States
37 Cont. Cas. Fed. 76,286 (Court of Claims, 1992)
In re De Los Angeles
101 B.R. 722 (E.D. Oklahoma, 1989)
Jackson v. United States
12 Cl. Ct. 363 (Court of Claims, 1987)
Fairington Apartments v. United States
7 Cl. Ct. 647 (Court of Claims, 1985)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
617 F.2d 211, 223 Ct. Cl. 98, 1980 U.S. Ct. Cl. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinewood-realty-ltd-partnership-v-united-states-cc-1980.