Brechan Enterprises, Inc. v. United States

34 Cont. Cas. Fed. 75,317, 12 Cl. Ct. 545, 1987 U.S. Claims LEXIS 118
CourtUnited States Court of Claims
DecidedJune 26, 1987
DocketNo. 247-84C
StatusPublished
Cited by9 cases

This text of 34 Cont. Cas. Fed. 75,317 (Brechan Enterprises, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brechan Enterprises, Inc. v. United States, 34 Cont. Cas. Fed. 75,317, 12 Cl. Ct. 545, 1987 U.S. Claims LEXIS 118 (cc 1987).

Opinion

OPINION

BRUGGINK, Judge.

This contract action involves a claim based on an alleged differing site condition. It is presently before the court upon the parties’ cross-motions for summary judgment. For reasons set forth herein, both parties’ motions are denied.

FACTUAL BACKGROUND

In 1977, a breakwater was constructed at the Harbor of Port Lions in Southwestern Alaska under the direction of the United States Army Corps of Engineers (“COE”). On October 12, 1982, Brechan Enterprises, Inc. (“Brechan”) entered into a contract to extend and repair the breakwater. As part of Brechan’s obligation under the contract, it was required to dredge and dispose of approximately 8,700 cubic yards of material to increase the depth of the entrance channel which ran perpendicular to the breakwater. The specifications called for dredging to a uniform elevation of minus 15 feet. Within the designated limits of dredging, this translated into a requirement for dredging a minimum of 2V2-3 feet of bottom material. Brechan’s bid for the dredging portion of the contract was $167,500.00 for the first 6,700 yards and $22.00 per cubic yard for up to 2,000 additional cubic yards.

Section 2B of the Technical Provisions of the contract specifications dealt with dredging and provided in part as follows:

1. Work Covered by This Section: The work covered by this section shall include the removal and disposal of all dredged materials as specified herein or indicated on the drawings or to bedrock. Blasting shall not be performed to remove rock if encountered within the designated dredging limits.
2. Character of Materials. Soil explorations have been made by the Government in the area to be dredged. The locations of the explorations made are appended herein. Additional subsurface information is available at the office of the District Engineer. Rock from the existing breakwater and other debris are to be expected and, if encountered, shall not be considered materially different within the scope of clause 4 of the General Provisions. Although the results of the above-mentioned explorations are representative of subsurface conditions [547]*547at their respective locations and for their respective vertical reaches, local variations in the subsurface materials are to be expected, and if encountered, will not be considered as materially differing within clause 4 of the General Provisions.

The contract contained the standard differing site conditions clause in its General Provisions.1 Appended to the contract were exploration logs which contained results from boring probe holes. These holes had been sunk for the original 1977 construction of the breakwater, for which no dredging had been contemplated.2 None of the probe holes were within the area to be dredged by the contractor.

Brechan began its dredging operations on June 29, 1988 using a barge-mounted crane with a three cubic yard clamshell bucket. During most dredging processes, John Schwicht, the Government’s onsite project engineer, was aboard the dredging barge to observe operations. Dredging proved to be difficult from the outset, as was observed by Schwicht in his periodic reports. Government Surveillance Report No. 148, dated June 30, 1983, for example stated that production was “painfully slow. Clamshell seems just too light to penetrate through clay-gravel layer which has been encountered. Boring logs of specifications do show that this type of material is present.” Government Surveillance Report No. 150 dated July 1, 1983, stated:

Contractor shut down dredging operation in P.M. due to low productivity. Material which seems to be the most difficult to dredge is a blue marine clay matrix around an angular gravel. This material is quite hard and clamshell we are using does not seem to have sufficient mass to penetrate.

On July 5, 1983, John Tyhuis, Brechan’s project manager, wrote the following to the Contracting Officer (“CO”):

During this week ending July 2,1983, we attempted to clam material from the entrance channel at the breakwater____ We feel the soil reports are in error in that we are encountering very hard gravelly clay.
Please be advised that there may be a possible claim if the material is in fact different than what the soil data inferred.

(Emphasis added.) In that same letter, Ty-huis notified the COE that Brechan planned to retain an independent soil testing firm to get a second opinion as to the classification of this material.

The firm which Brechan retained, R & M Consultants, gave a descriptive classification of the materials being dredged as “sand with some cobbles and gravel and traces [of] salt and clay.” This classification described the gradation, or size of the material, not its compaction or density, which R & M did not test. On July 18, 1983, Tyhuis discussed the test results with the Resident Contracting Officer (“RCO”), Robert E. Morris. During this conversation, Tyhuis acknowledged that the gradation of the material did not substantially [548]*548differ from that indicated in the COE’s earlier test borings. On August 1, 1983, the RCO notified Brechan by letter that, based on his conversation with Tyhuis and the results of the testing done by R & M, a differing site condition did not exist. The letter went on to state that “this office considers the matter closed.” Brechan did not respond in writing directly to this letter.

After Brechan had obtained a power arm excavator, dredging operations resumed on or about August 10. At first, dredging operations improved, as noted in Government Surveillance Report dated August 10, 1983: “Dredging began by noon on 10 August. Results much improved with new bucket but it appears that we will get about one load every other day. This translates into about 35 working days.”

The initial progress slowed, however, and Brechan again began experiencing very difficult dredging. The surveillance report dated September 30,1983 specifically noted that “[I]t is quite possible that material described in [the] boring logs as ‘refusal on rock’ was actually this material which is quite dense.”

By letter dated October 5, 1983, Brechan again informed the government of a potential differing site condition:'

We are still encountering extremely hard material within the dredging limits at the breakwater.
We had the site visited by Lawrence Per-ko (Senior Geotechnical Engineer for R & M Consultants) on September 7, 1983. Additional samples of dredged material were obtained for testing. We are awaiting results of these tests as to the nature and classification of this material.
From the record of tests provided and materials sampled in the specifications for this project we had expected no problem in digging the material in the entrance channel at the breakwater. The blow counts and descriptions of the materials led us to believe that the material would not be difficult to remove. We believe that on the exploration logs PH-5, PH-6, and PH-7 that where refusal on rock is described that there is not rock at these elevations and it is glacial till. We are encountering this type of material in the majority of our dredging.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Corp. v. General Motors Corp.
807 N.E.2d 70 (Indiana Court of Appeals, 2004)
D.F.K. Enterprises, Inc. v. United States
45 Fed. Cl. 280 (Federal Claims, 1999)
General Motors Corp. v. Northrop Corp.
685 N.E.2d 127 (Indiana Court of Appeals, 1997)
Neal & Co., Inc. v. City of Dillingham
923 P.2d 89 (Alaska Supreme Court, 1996)
Pacific Northern Timber Co. v. United States
38 Cont. Cas. Fed. 76,455 (Federal Claims, 1992)
Roberts v. United States
13 Cl. Ct. 774 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,317, 12 Cl. Ct. 545, 1987 U.S. Claims LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brechan-enterprises-inc-v-united-states-cc-1987.