Pacific Northern Timber Co. v. United States

38 Cont. Cas. Fed. 76,455, 27 Fed. Cl. 331, 1992 U.S. Claims LEXIS 219, 1992 WL 379676
CourtUnited States Court of Federal Claims
DecidedDecember 18, 1992
DocketNo. 91-1340C
StatusPublished

This text of 38 Cont. Cas. Fed. 76,455 (Pacific Northern Timber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Northern Timber Co. v. United States, 38 Cont. Cas. Fed. 76,455, 27 Fed. Cl. 331, 1992 U.S. Claims LEXIS 219, 1992 WL 379676 (uscfc 1992).

Opinion

OPINION

BRUGGINK, Judge.

This Tucker Act1 claim is before the court on defendant’s motion to dismiss for lack of jurisdiction following transfer here from the United States Court of Appeals for the Federal Circuit.2 944 F.2d 912. The issue to be decided is whether plaintiff, Pacific Northern Timber Co. (“PNT”), failed to file within the six-year limitations period or during a tolling thereof. For the reasons that follow, the motion is granted.

I. FACTUAL BACKGROUND

On June 9, 1954, the Government, acting through the United States Forestry Service, awarded contract No. A 10fs-1283 to PNT. As originally written, the contract provided for the government’s sale of approximately three billion board feet of timber located in the Tongass National Forest, Alaska over a 50-year period ending December 31, 2006. However, because PNT failed to install a pulp plant as contemplated in the contract, the contract term was shortened by 25 years. The contract thus terminated December 31, 1981. Paragraph 2 (“It 2”) of the contract provided for initial rates of pay for the timber and for rate redetermination for each five-year period thereafter for the duration of the contract.3 By the terms of It 2, PNT was to receive advance notice of the rates recommended by the Regional Forester to the Chief of the Forestry Service (“Chief”). This notice allowed PNT the chance to make suggestions as to rates with which it disagreed. If the parties continued to disagree as to the redetermined rates, the Chief of the Forest Service would resolve the disagreement based on a review of both PNT’s suggestions and the Regional Forester’s recommendations.4

[333]*333The contract also contained Paragraph 22 (“H 22”), which read as follows:

Complaints by Purchaser. Complaints by the purchaser as to any action taken by a forest officer respecting this contract shall not be considered unless made in writing within thirty (30) days of such action to the forest officer having jurisdiction unless the purchaser furnishes satisfactory reason for allowing a longer time.

On December 30, 1976, the Regional Forester sent PNT the rate redetermination appraisal summary for the final five-year period, 1977-1981. PNT persuaded the Chief to make some changes in the rates in early June, 1977. Still dissatisfied, PNT appealed to the Department of Agriculture Board of Contract Appeals (“Board” or “AgBCA”) on June 24, 1977. PNT complained that in redetermining the rates, the Forest Service had breached the contract by not applying its “standard method then in use,” resulting in rates that were not “equitable.” PNT first sought a new appraisal, but after the contract was completed, PNT amended its complaint to seek a refund based on the difference between the base stumpage rate as to which the parties originally contracted and the rate established by the Chief. The complaint alleges that the Board’s jurisdiction arose pursuant to 7 C.F.R. § 24.4(e) (1976), a provision that precludes the possible application of a disputes clause.5

PNT’s current parent corporation, Alaska Lumber & Pulp Co. (“ALP”),6 also had a 50-year contract to purchase Tongass timber. Unlike PNT’s contract, the ALP contract provided for an appeal of the Forest Service’s redetermined rates to a three-member rate review board. At the time PNT was making its appeal to the Board, ALP had an appeal pending before the rate review board. ALP’s appeal concerned rate redeterminations for the five year period beginning in 1976. Under the circumstances, PNT and the Forest Service agreed to suspend PNT’s appeal proceedings until the Secretary of the Department of Agriculture (“Secretary”) could review and decide on the rate review board’s recommendations as to the ALP contract. The rate review board issued its recommendations on July 27, 1979, but on August 23, 1980, the Secretary rejected them. PNT’s appeal was thereafter activated.

In 1983, the Board held a hearing on the PNT appeal, after which it allowed the parties to supplement the record with revised exhibits and experts’ affidavits. After the presiding administrative judge retired, the succeeding judge heard further oral arguments in 1987. On September 13, 1990, more than 13 years after PNT first filed its notice of appeal, the Board rejected PNT’s appeal.

The Board held that the Contract Disputes Act (“CDA”)7 was not applicable because the dispute occurred before the CDA took effect, nor could its jurisdiction arise [334]*334under 7 C.F.R. § 24.4(a) (1976),8 because, the Board concluded, PNT’s contract had no disputes clause. Instead, the Board agreed with PNT that it could exercise jurisdiction under 7 C.F.R. §§ 24.4(e) and 24.5.9 The Board also expressed the view that “[determination of the contract price is not an award of damages within the limitation on jurisdiction to award monetary damages (7 C.F.R. 24.4(e)(3)).”

PNT appealed the Board’s decision to the Federal Circuit on October 19, 1990. Because the dispute arose before March 1, 1979, the effective date of the CDA, the Federal Circuit dismissed the appeal for lack of jurisdiction and transferred the case here pursuant to 28 U.S.C. § 1631 (1988). The court specified that by its transfer of the case, it expressed “no opinion on the Claims Court’s jurisdiction.”10

PNT contends that jurisdiction is proper here under the Tucker Act. Moving to dismiss, defendant urges that the claim is outside the applicable six-year limitations period, 28 U.S.C. § 2501 (1988). Defendant contends that at best, PNT’s claim accrued on January 1, 1982, the day following contract expiration.

PNT’s opposition to dismissal is summarized in the following argument:

(1) Section 22 of the contract was a “disputes clause” which directed that a complaint “as to any action taken by a Forest Officer respecting this contract” had to be filed with the “forest officer having jurisdiction” (in this case the Secretary acting through the AgBCA) or it would not be “considered.” Under then existing law11 (i.e., June 10, 1977, prior to passage of the Contract Disputes Act, 41 U.S.C. § 601), plaintiff had to exhaust its administrative remedies by filing an administrative appeal of the Chief’s rate redetermination with the AgBCA before filing an action in this court. Crown Coat Front Co. v. United States, 386 U.S. 503 [87 S.Ct. 1177, 18 L.Ed.2d 256] (1967);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Wunderlich
342 U.S. 98 (Supreme Court, 1951)
United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)
United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Norman J. Mulholland v. The United States
361 F.2d 237 (Court of Claims, 1966)
Bird & Sons, Inc. v. The United States
420 F.2d 1051 (Court of Claims, 1970)
Empire Institute of Tailoring, Inc. v. United States
161 F. Supp. 409 (Court of Claims, 1958)
Mingus Constructors, Inc. v. United States
33 Cont. Cas. Fed. 74,407 (Court of Claims, 1986)
Brechan Enterprises, Inc. v. United States
34 Cont. Cas. Fed. 75,317 (Court of Claims, 1987)
Handel v. United States
35 Cont. Cas. Fed. 75,605 (Court of Claims, 1988)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Phoenix Bridge Co. v. United States
85 Ct. Cl. 603 (Court of Claims, 1937)
Plato v. United States
86 Ct. Cl. 665 (Court of Claims, 1938)
H. R. Henderson & Co. v. United States
169 Ct. Cl. 228 (Court of Claims, 1965)
Camacho v. United States
495 F.2d 1363 (Court of Claims, 1974)
S. J. Groves & Sons Co. v. United States
661 F.2d 170 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,455, 27 Fed. Cl. 331, 1992 U.S. Claims LEXIS 219, 1992 WL 379676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-northern-timber-co-v-united-states-uscfc-1992.