This text of GSC Construction Incorporated (GSC Construction Incorporated) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GSC Construction Incorporated, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) GSC Construction, Incorporated ) ASBCA Nos. 59046, 59957 ) Under Contract No. W9126G-11-D-0061 )

APPEARANCE FOR THE APPELLANT: James S. DelSordo, Esq. Argus Legal, PLLC Manassas, VA

APPEARANCES FOR THE GOVERNMENT: Michael B. Goodman, Esq. Engineer Chief Trial Attorney Jason R. Chester, Esq. Ronald J. Goodeyon, Esq. Stephanie J. Milburn, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Tulsa

MAJORITY OPINION BY ADMINISTRATIVE JUDGE PAGE 1

In this construction-contract case, GSC Construction, Inc. (GSC, appellant or the contractor) seeks additional compensation from the government. It asserts that the government ordered it to perform extra-contractual work for which it has not been paid, and also seeks the release of liquidated damages and retainage withheld by the government. Both entitlement and quantum are before the Board. 2 Familiarity is presumed with the Board's denial of the government's motion for summary judgment in GSC Construction, Inc., ASBCA No. 59046, 14-1BCA135,739. We grant the appeals ~p~. . FINDINGS OF FACT

The Contract, Relevant Request for Proposals (RFP) Amendments, and Task Order

As described in 1 1.1 GENERAL DESCRIPTION OF WORK, the solicitation was for "Base Multiple Award Task Order Contracts (MATOC) for Design and Construction of Warehouses in the West of the Mississippi." The Department of the Army (Army or

1 These appeals were heard by Judge Timothy P. Mcllmail. 2 See, e.g., tr. 1/61; see also the Board's Order of May 19, 2015 concurring with the · parties' joint status report of May 14, 2015 requesting that entitlement and quantum be heard in a single proceeding. government) intended to award more than one contract, with task orders for individual projects. (R4, tab 4(e) at 1740)

< On September 15, 2011, the Army awarded Task Order 0001 (the task order) to GSC. This was done pursuant to Contract No. W9126G-11-D-0061 (the contract) (R4, tab 4(p) ), an indefinite delivery, indefinite quantity (ID/IQ) contract for work at Ft. Sill, Oklahoma. The task order amount was $11,9~1,460 (id. at 3377). The contract - as awarded incorporated by reference "GSC' s proposal dated 29 August 2011, solicitation W9126G-1 l-R-0053, and all twelve (12) amendments." Contract line items (CLINS) that described particular work were each priced in a fixed, lump sum amount. (Id. at 3378) According to§ 01 10.00,, 2.0 SCOPE, the purpose of the contract was to "Construct a combined Central Issue Facility (CIF) for permanent party troops and soldiers in Advanced Individual Training (AIT)" (id., tab 4(e) at 1768).

Contract § 00 72 00, , 1.3 PROPOSED BETTERMENTS (AUG [l 9]97) also made GSC's proposal part of the contract:

(a) The minimum requirements of the contract are identified in the Request for Proposal. All betterments offered in the proposal become a requirement of the awarded contract. (b) "B.~tterme_nt" is defined as any component or system which exceeds the minimum requirements stated in the Request for Proposal. This includes all betterments identified in the proposal and/or all Government identified betterments.

· (R4, tab 4{a) at 32; see also§ 00 73 00 (ID/IQ) SPECIAL CONTRACT REQUIREMENTS, , 1.3, id. at 32)

Paragraph 1.10 BASE ID/IQ CONTRACT specifically applied the "requirements of the Base ID/IQ Contract Division 00 PROCUREMENT AND CONTRACTING REQUIREMENTS sections and documents and Division OI GENERAL REQUIREMENTS sections ... except as otherwise specified in the task order documents" (R4, tab 4(p) at 3388).

RFP Amendment 7, which was ~ffective March 28, 2011 (R4, tab H at 3150), required at, 2.b the following change to the Statement of Work (SOW): "In paragraph 6.4.6.1, replace all 'Infrastructure Contractor' with 'D/B [Design/Build] Contractor"' (id. at3151).

Contract§ 014504.00 10,, 3.8 COMPLETION INSPECTION provides in, 3.8.1 for preparation of a "punch list of items which do not conform to the approved drawings and specifications .... " After these deficiencies were corrected, the parties were to proceed to

2 a "Pre-Final Inspection ('ti 3.8.2) then a Final Acceptance Inspection ('ti 3.8.3)." (R4, tab 4(p) at 3556)

Among standard contract clauses from the Federal Acquisition Regulation (FAR) is 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984). At 't[ (a), this clause requires the design and construction of the CIF to be completed no later than 519 days after receipt of notice to proceed. (R4, tab 4(p) at 3 3 83) That notice was issued November 17, 2011 (id., tab Q).

Other :fAR clauses incorporated by reference were 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) and 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION ALT 1 (APR 1984) (R4, tab 4(a) at 9). See also § 00 72 00 SPECIAL CONTRACT REQUIREMENTS 't[ 1.2 DESIGN/BUILD CONTRACT - ORDER OF PRECEDENCE (AUG [19]97), which incorporates the "successful offeror's accepted proposal" as part of the contract (id. at 3.2). ·

In accordance with 't[ (e) of FAR 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002), also incorporated by reference, the contracting officer (CO) was allowed to "retain a maximum of 10 percent of the amount of the payment [due the contractor] until satisfactory progress is achieved" (R4, tab 4 at 9).

FAR clauses incorporated by full text included 52.211-12 LIQUIDATED DAMAGES- CONSTRUCTION (SEP 2000) (R4, tab 4(a) at 12). This provision.is reiterated at§ 00 73 10, 'ti 1.3, which allowed the government to assess against GSC "$1280 for each calendar day of delay until the work is completed or accepted ... " (R4, tab 4(p) at 3384).

The contract also included FAR 52.211-10 (R4, tab 4(a) at 12). Relevant here is added note (3), which states:

(3) 0 & M Manuals. 0 & M Manuals shall be developed and submitted in accordance with Contract Section O1 78 02.00.10 Closeout Submittals, at least 60 calendar days prior to the scheduled contract completion date. Upon approval of fully developed O & M Manuals, the Contractor shall have earned the withholding amount shown for "Operation and Maintenance Manuals" in Contract Section 01 78 02.00 Closeout Submittals.

(Id., tab 4(p) at 3383-84)

In§ 00 73 10, TASK ORDER SUPPLEMENTAL CONTRACT REQUIREMENTS, 't[ 1.4 contains Defense Federal Acquisition Regulation (DFARS) clause, 252.236-7001 . CONTRACT DRAWINGS, MAPS, AND SPECIFICATIONS (AUG 2000). Of particular interest

3 are 1 1.4(c )( 1), which states that "Large-scale drawings shall govern small-scale drawings" and 11.4(d), which provides:

Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent o.f the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and \__,described in the drawings and specifications.

(R4, tab 4(p) at 3384-85)

SOW 16.3.1.4 states that the infrastructure drawings were being provided to the D/B contractor as a reference "for information only" (R4, tab 4( e) at 1817). SOW 1 6.3 .1.5 reiterates that "infrastructure drawings are provided as 'for information only' reference" (id., tab 4(p) at 34 72).

sow 16.3 .2 SITE STRUCTURES AND AMENITIES calls for the contractor to: "Provide one dumpster pad and enclosure per facility" (R4, tab 4(e) at 1818).

In relevant part, RFP Amendment 4, § 0110 00,_SOW 16.4.6 BASE UTILITY INFORMATION apprises the contractor of the following:

6.4.6.1 Utilities: The Installation's DPW supervises infrastructure and utilities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
GSC Construction Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsc-construction-incorporated-asbca-2019.