Goodloe Marine, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 12, 2023
Docket61960
StatusPublished

This text of Goodloe Marine, Inc. (Goodloe Marine, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goodloe Marine, Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Goodloe Marine, Inc. ) ASBCA No. 61960 ) Under Contract No. W912EP-11-D-0020 )

APPEARANCES FOR THE APPELLANT: Michael H. Payne, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

Casey J. McKinnon, Esq. Cohen Seglias Pallas Greenhall & Furman PC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Susan E. Symanski, Esq. Bruce E. Groover, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville

OPINION BY ADMINISTRATIVE JUDGE PROUTY ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGEMENT 1

This is a case in which the government suspended work on the above-captioned dredging contract (the contract) for a little less than three months and the contractor, Goodloe Marine, Inc. (Goodloe) did not submit a claim seeking compensation for the added costs it incurred due to that suspension until more than five years and nine months after that suspension was lifted. Respondent, the United States Army Corps of Engineers (the Corps or the government), moves for summary judgment, contending that the Federal Acquisition Regulation (FAR) 52.242-14, Suspension of Work, requirement that a claim be “asserted in writing as soon as practicable after the termination of the suspension” is a specialized statute of limitations that trumps the general six-year Contract Disputes Act statute of limitations. Were we writing this opinion on a blank slate, we might join the government in saying to Goodloe, “too bad, so sad.” Nevertheless, for reasons explained below, prior law interpreting this and similar FAR provisions leads us to deny the government’s motion for summary judgment because the government has not established that it was prejudiced by Goodloe’s delay in asserting its claim in writing.

1 This appeal was recently assigned to the undersigned. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The undisputed material facts are straightforward and, for the most part, agreed upon by both parties. The contract involved in this appeal was a Multiple Award Task Order Contract for dredging near Tampa, Florida (see R4, tab 10; SUMF ¶ 1). 2 The contract included the standard FAR 52.242-14, Suspension of Work (APR 1984), clause (see R4, tab 1 at 59; 178) and a standard liquidated damages clause, FAR 52.211-12, Liquidated Damages – Construction (SEP 2000), tailored to set the amount at $1,026 per day late (R4, tab 11 at 697). By Delivery Order 002, dated January 6, 2012 (see R4, tab 13 at 989), the Corps directed Goodloe to perform a number of services, including dredging at “Cut-A,” “Cut-C,” and the Alafia River Channel (id. at 991-92). Delivery Order 002 had a delivery date for the aforementioned services of June 20, 2012 (R4, tab 13 at 1001). The Corps later extended that delivery date (R4, tab 20 at 1029).

One June 15, 2012, the Corps issued a “Suspension of Work” to Goodloe for the Cut-A, Cut-C and Alafia River Channel work on the basis of Goodloe’s alleged “failure to prevent impacts to migratory birds and their nests in accordance with” relevant contractual specifications. This suspension was to last until the end of the migratory bird season on August 31, 2012. (R4, tab 33 at 1855) Goodloe proposed a change to its procedures to allow it to resume its operations earlier (see R4, tab 35), but the Corps rejected it (see R4, tab 36). The suspension was ultimately lifted on September 4, 2012 (SUMF ¶ 10).

By early October 2012, the Corps was withholding liquidated damages in the amount of $53,352 for Goodloe being 52 days late (at that time) in completing the contract (app. supp. R4, tab 1 at 1-2). In a subsequent letter from Goodloe to the Corps dated October 10, 2012, Goodloe complained of the assessment of liquidated damages, writing:

Therefore, due to the fact that Goodloe Marine is of the opinion that the Corp improperly shut the project down for more than 80 days and has assessed [liquidated damages] for that period without any discussion gives us no recourse than to reserve our right to file a claim.

2 “SUMF” refers to a paragraph of the “Statement of Undisputed Material Facts” within the government’s motion for summary judgment. Unless otherwise noted, every such paragraph cited has been conceded by Goodloe in its “Statement of Genuine Issues of Material Fact” (SGMF) contained within its opposition to the government’s motion for summary judgment. 2 (App. supp. R4, tab 1 at 6). The same letter rejected the Corps’ purported oral offer to waive liquidated damages in return for Goodloe’s executing a release (id.).

In a letter dated October 30, 2012, Goodloe reiterated that it would not execute a modification that it saw as “requiring Goodloe Marine to give up the right to turn in a claim” (app. opp’n, ex. 1 at 1). 3

On August 14, 2013, Ms. Victoria Read from the Corps emailed the final progress payment paperwork to Goodloe (app. supp. R4, tab 3 at 16-17). Goodloe responded the same day:

As you should already know Goodloe Marine will be submitting several claims on the above referenced contract. We are working on variation and estimated quantities claims as well as other claims. We do not anticipate having these claims finalized for the next several months and therefore will not be signing a release of claims at this time.

(Id. at 16).

The claims were not, apparently, finalized in the next several months. Rather, the claim at issue today was submitted by Goodloe to the Corps on June 14, 2018. This claim sought $1,879,000 for additional costs incurred during the government- ordered suspension. It alleged that Goodloe was entitled to this relief both under the Suspension of Work clause and because the Corps violated the implied duty to cooperate. (R4, tab 38 at 1863) The contracting officer (CO) denied the claim on November 5, 2018 on the bases that it was submitted both after final payment and not as soon as practicable after termination of the suspension (R4, tab 39).

Goodloe brought a timely appeal to the Board.

3 Exhibit 1 to Goodloe’s opposition to the government’s motion for summary judgment is this letter. In general, we prefer to consider citations to the Rule 4 file as supplemented, but we also recognize that a response to a motion for summary judgment must sometimes be submitted prior to supplementation of the Rule 4 file. 3 DECISION

I. The Standard of Review

The standards for summary judgment are well established and need little elaboration here. Summary judgment should be granted if it has been shown that there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). A non-movant seeking to defeat summary judgment by suggesting conflicting facts “must set forth specific facts showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986) (quoting First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 288-89 (1968)). Nevertheless, “[t]he moving party bears the burden of establishing the absence of any genuine issue of material fact and all significant doubt over factual issues must be resolved in favor of the party opposing summary judgment.” Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed. Cir. 1987) (citing United States v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Dobyns v. United States
915 F.3d 733 (Federal Circuit, 2019)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Food Market Merchandising, Inc. v. Scottsdale Indemnity Co.
196 F. Supp. 3d 1004 (D. Minnesota, 2016)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Goodloe Marine, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/goodloe-marine-inc-asbca-2023.