H2L1-CSC, JV

CourtArmed Services Board of Contract Appeals
DecidedOctober 28, 2021
DocketASBCA No. 62086
StatusPublished

This text of H2L1-CSC, JV (H2L1-CSC, JV) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H2L1-CSC, JV, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) H2L1-CSC, JV ) ASBCA No. 62086 ) Under Contract No. W912QR-14-D-0012 )

APPEARANCE FOR THE APPELLANT: Bernard Mandel, Esq. Cleveland, OH

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Carlton A. Arnold, Esq. Engineer Trial Attorney U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE PROUTY 1

The issue before us in the government’s pending motion for summary judgment is a relatively straightforward one of contract interpretation: did the task order (TO 9) at issue on the above-captioned contract (the contract) require the removal and replacement of gutters and downspouts on two roofs that were required to be replaced, even though this requirement was not expressly stated in the synopsized “Scope of Work” attached to TO 9, but was included – very plainly – in the specifications and drawings also attached to that task order? Because we find that TO 9 required the removal and replacement of the gutters and did not conflict with the Scope of Work, we rule in favor of the government and deny the appeal.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

I. Preliminaries

On April 15, 2014, appellant, H2L1-CSC, JV (H-C), was one of several contractors awarded the contract, which was a multiple award task order contract (MATOC), for design/build construction in the area under the jurisdiction of the Louisville District of the United States Army Corps of Engineers (the Corps) (R4, tab 3). The contract worked like other MATOCs: When the Corps decided it wished to have work performed under the contract, it would issue a solicitation for performance of the project as a task order (TO) to H-C and the other MATOC awardees. Those contractors would, in turn, submit bids on the TO under the MATOC. The Corps would then

1 This appeal was recently re-assigned to Judge Prouty to draft the decision of the Board. consider the bids and award the TO as a firm-fixed-price contract based upon its evaluation of the various bids. (R4, tab 3 at 5)

II. TO 9 is Solicited and Awarded to H-C

In April 2014, Ivory Associates, roofing and waterproofing consultants, submitted a report to authorities at Westover Air Reserve Base (ARB) in Massachusetts regarding the condition of the roofs of five different buildings that it had surveyed on the base (R4, tab 4 at 152-58). The report made various recommendations for each of the five buildings. For the two buildings that (as will be seen) are the subject of this dispute – Buildings 2200 and 2201 – the report recommended very different actions. For Building 2200, the report found “only maintenance issues, at this time” (id. at 153-54). For Building 2201, on the other hand, the report recommended replacing the roof “as soon as possible” (id. at 154-55). It made no comment on the gutters of either Building 2200 or Building 2201 (id. at 153-55). For one of the other three buildings inspected, Building 5200, the report did recommend the replacement of the gutters (id. at 152).

Regardless of the report’s recommendations, the government decided to replace the roofs for both Building 2200 and Building 2201 and issued a solicitation under the contract to do so on August 25, 2014 (R4, tab 4 at 1). On September 30, 2014, TO 9 was awarded to H-C (id. at 2). According to a document attached to H-C’s opposition to the government’s motion for summary judgment, at about the same time, a different TO was awarded to a different contractor on the MATOC to replace the roof on another building at Westover ARB (Building 5200 – the one that the Ivory Associates report recommended replacing the gutters) (see app. opp’n, ex. B).

III. The Contents of TO 9

A. Preliminary Sections

The second page of TO 9 includes contract line item number (CLIN) 0001, which is, in fact, the only CLIN in TO 9. Before devolving into payment bond matters and subjects of even less interest to us today, it provided the following:

Roof Replacement of B2200 and B2201

FFP

Includes Demolition, Insulation and Remainder of work for Building 2200 and 2201. . . .

Award is for the Roof Replacement, Building B2200 and B2201, located at Westover ARB, MA. Contractor shall

2 provide all labor, equipment, supplies and construction services in accordance with all drawings, specifications and amendments 0001, and their proposal dated 23 September 2014.

(R4, tab 4 at 3) After the price break-out schedule (see R4, tab 4 at 4) and a number of contract clauses from the Federal Acquisition Regulation (FAR) reproduced in full (see R4, tab 4 at 6-9), TO 9 reproduced the Department of Defense Supplement to the Federal Acquisition Regulation (DFARS) 252.236-7001, Contract Drawings and Specifications. Notably, in subsection (b), this DFARS provision requires the contractor to check contract drawings immediately upon their receipt and notify the contracting officer (CO) of any discrepancies therein. Subsection (e) provides that “[t]he work shall conform to the specifications and the contract drawings identified on the following index of drawings: Drawings are included in the Technical Specifications.” (R4, tab 4 at 10) We will get to the specifications shortly.

B. The “Scope of Work”

Appendix A to TO 9 spans pages 11 through 37 of tab 4 of the Rule 4 file. It is labelled as “Scope of Work” 2 (R4, tab 4 at 11). Most of it consists of standard contract provisions, some of which were already provided in the contract. For example, it reproduces DFARS 252.236-7001, Contract Drawings and Specifications (see R4, tab 4 at 36-37), which, as we have already noted, was reproduced earlier in TO 9. Little of its 27 pages provides any guidance on the substance of the work that is to be accomplished.

The first page of Appendix A is labelled as “Task Order Scope of Work for Westover ARB Roof Replacement at Building [sic.] 2200 and 2201.” It further provides on the same page under “General Information” that, “[t]his Scope of Work covers Re Roofing projects at facilities located at Westover ARB in Westover, MA.” (R4, tab 4 at 11). Section 1.1, Pre-Bid Site Visit, explained that there would be no pre-bid site visits, but that the contractor would be provided “inspection reports and facility specific specifications with roof plans and specific details for each roof condition” (id.).

The only other portion of the “Scope of Work” detailing the work to be done (and “detailing” is perhaps too strong a word) is section 2. The relevant portions are reproduced below:

2 Most substantial government contracts include a “statement of work” and it is easy to see “scope of work” and read it as the same thing. Indeed, perhaps it is meant that way here (we do not know), but the words are not the same.

3 2. RE-ROOF PROJECT DATA

The Scope of Work (SOW) is for the construction services required to repair failed or failing roofs. The roofs have been inspected by an independent contractor and specifications written for each roof type. These specifications are included with this request for proposal.

2.1. Locations

The contractor shall repair failed or failing roofs at the locations specified.

See Technical Specifications for details of the roof and summary of work to be performed at each building.

(R4, tab 4 at 13) No other portion in the “Scope of Work” specifies further the actual work to be accomplished and it is bereft of such basic details as the type of roof to be installed.

C. The Specifications and Drawings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)
Rixon Electronics, Inc. v. United States
536 F.2d 1345 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
H2L1-CSC, JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h2l1-csc-jv-asbca-2021.