Thompson v. United States

91 Ct. Cl. 166, 1940 U.S. Ct. Cl. LEXIS 59, 1940 WL 4139
CourtUnited States Court of Claims
DecidedMay 6, 1940
DocketNo. 42963
StatusPublished
Cited by11 cases

This text of 91 Ct. Cl. 166 (Thompson v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson v. United States, 91 Ct. Cl. 166, 1940 U.S. Ct. Cl. LEXIS 59, 1940 WL 4139 (cc 1940).

Opinion

Whaley, Chief Just-ice,

delivered the opinion of the court:

Plaintiffs entered into a contract with the defendant on March 22, 1929, to “furnish labor and materials, and perform all work required for tunnel, canal lining and structures, as described in Schedule No. 3 of Specifications No. [174]*174484, North. Branch Canal, Yakima (Kittitas Division) Project — Washington,” for a consideration of $345,878.25, the work to commence within 30 calendar days after date of receipt of notice to proceed and to be completed within 600 calendar days from that date. The contract was on the approved standard Govermnent form for construction work and the specifications were attached thereto.

The contract price was made up of estimated quantities of material, except for grout connections and electrical outlets, at specific unit prices, and the total consideration was variable.

The work consisted of a concrete-lined circular pressure tunnel with an internal diameter of 111 inches and an over-all length, including inclined shafts, of approximately 3,596 feet. It was designed to carry water from the south side of the Yakima Elver to the north side of the river for the irrigation of lands of the Kittitas Project and was to go down through the rock under the river about 160 feet below the river bed and to withstand an unbalanced hydrostatic head of about 350 feet. This undertaking was under the Bureau of Keclamation.

Previous to advertising for bids, the Government engineers had made core borings at the site of the work which showed the character of the soil and rock through which the tunnel would go and, as a result of these borings, the Government engineers had concluded that the tunnel would be of rock which could withstand the hydrostatic pressure inside the tunnel which would be exerted against practically a solid wall of rock in all directions.. The specifications were made and the tunnel was designed to fit this situation. With the exception of a few instances the design required an unreinforced concrete lining of approximately 15 inches thick on the outside of the tunnel. The inside diameter of the tunnel was to be 9 feet 3 inches.

Plaintiffs commenced work in April 1929 by sinking a -vertical shaft in the central portion of the projected tunnel in order that the work might be prosecuted in both directions. After about 6 months’ work and some 1,200 feet of the tunnel had been driven, the Government engineers [175]*175determined tbat the tunnel would have to be redesigned because of the relatively unstable materials surrounding the tunnel in order to take care of the hydrostatic pressure. Accordingly, new plans and drawings were made so as to provide for reinforced linings of 30 inches where the original contract provided for only 15 inches. This also required the excavation of a larger amount of unstable material so as to provide for the extra reinforced concrete. It required also additional reinforced steel and certain timber bracings. These changes were radically and materially different from the original design contemplated by the specifications and on which the contract had been executed and grew out of conditions unknown to and not contemplated by either party when the contract was entered into. The extent of these unforeseen conditions which required these changes, could only be determined as the work progressed and necessarily required additional time for completion. At the time the additional work was ordered the contracting officer did not issue a written change order under Article 3 of the contract but orally instructed the contractors to comply with the new design and the work entailed thereunder as the project progressed. The contractors obeyed the oral orders of the contracting officer and complied with the new design and were paid by the contracting officer according to the unit prices as called for in the original contract. These conditions continued from the time of the changed plans in this indifferent and unsatisfactory way and the work proceeded until October 30, 1930, at which time the contracting officer forwarded a change order to the plaintiffs in which was contained the unit prices of the original contract on some of the items and estimated prices for other items in connection with the' additional work. The increased price as allowed by the contracting officer was $106,597.53 and the plaintiffs were given an additional 150 days in which to complete the contract.

The completion date of the contract was on or about December 3,1930, and, before the forwarding of the proposed change order, no orders for an extension of time had been granted [176]*176by the contracting officer although this additional work, occasioned by the new design, necessarily involved additional time for completion. In a letter written by the contracting officer transmitting the change order plaintiffs were instructed to sign the change order, if it was satisfactory, and if it were not they were instructed to return it without signature but with a statement as to the items to which exceptions were taken. The plaintiffs retained this change order until November 25, 1930, when they returned it as “satisfactory” and “accepted.”

Under the terms of the contract, where extra work .involved more than $500, it was necessary to receive the approval of the Assistant Secretary of the Interior, and this approval was not obtained until December 29, 1930.

On May 8,1931, plaintiffs wrote a letter to the contracting officer in which it was stated that they had been subjected to heavy losses on the contract and asked to be rewarded for the work as done by them. They further stated that the reason for signing the change order was their financial embarrassment because of their attempt to complete the work and their fear of having liquidated damages assessed against them after the completion date of December 3, 1930, by reason of the fact that no extension of time had been given by the contracting officer other than that stated in the written change order.

The work was completed on June 6, 1931.

The contracting officer entertained the claim, as made by the plaintiffs in their letter of May 8, 1931, but denied it. The contracting officer did, however, notify the plaintiffs on July 13, 1931, that they had the right to appeal from his decision to the Secretary of the Interior and that they could make an appeal within 30 days.

Plaintiffs filed an appeal with the Secretary of the Interior on August 11, 1931, which was within the 30 days from the decision of the contracting officer. The Secretary of the Interior entertained the appeal and rendered a decision on December 7, 1932, in which he held that there had been an enormous increase in quantities of excavation, concrete, and reinforcing steel and that the order for changes had been signed by the contractors under duress and the change order was therefore void.

[177]*177The Secretary of the Interior had an audit made of plaintiffs’ work under the changed conditions and on June 23, 1933, rendered a decision in which he found that plaintiffs were entitled to an additional amount of $92,202.06, as an equitable adjustment on account of increased work performed.

This sum was vouchered by the contracting officer for plaintiffs’ signature and release and, upon its execution by the plaintiffs, the voucher was forwarded to the General Accounting Office for settlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
131 Fed. Cl. 275 (Federal Claims, 2017)
Koga Engineering & Construction, Inc. v. State
222 P.3d 979 (Hawaii Supreme Court, 2010)
KOGA ENGINEERING & CONSTRUCTION, INC. v. State
203 P.3d 676 (Hawaii Intermediate Court of Appeals, 2009)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
Penn-Ohio Steel Corporation v. The United States
354 F.2d 254 (Court of Claims, 1965)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)
Kawneer Co. v. United States
100 Ct. Cl. 523 (Court of Claims, 1943)
Arundel Corp. v. United States
96 Ct. Cl. 77 (Court of Claims, 1942)
Seeds v. United States
92 Ct. Cl. 97 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
91 Ct. Cl. 166, 1940 U.S. Ct. Cl. LEXIS 59, 1940 WL 4139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-v-united-states-cc-1940.