Carl M. Halvorson, Inc. v. United States

461 F.2d 1337, 198 Ct. Cl. 882, 1972 U.S. Ct. Cl. LEXIS 87
CourtUnited States Court of Claims
DecidedJune 16, 1972
DocketNo. 352-68
StatusPublished
Cited by5 cases

This text of 461 F.2d 1337 (Carl M. Halvorson, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carl M. Halvorson, Inc. v. United States, 461 F.2d 1337, 198 Ct. Cl. 882, 1972 U.S. Ct. Cl. LEXIS 87 (cc 1972).

Opinion

'Per Curiam :

This case was referred to Trial Commissioner Roald A. Hogenson with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166 (c). The commissioner has done so in an opinion and report filed on June 29,1971, wherein such facts as are necessary to the opinion are set forth. Defendant requested review by the court of the commissioner’s report and the case has been submitted to the court on oral argument of counsel for the defendant and the briefs of the parties. Since the court agrees with the opinion and recommended [886]*886conclusion of the trial commissioner it hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is granted as to plaintiff’s claims for delays in contract performance resulting from defendant’s defective contract drawings both with respect to the sewerline across the China Creek channel and also with respect to the D Street waterline across Locust Street and, to that limited extent, defendant’s cross-motion for summary judgment is denied with proceedings before tiffs court suspended for a period of 90 days to permit the parties to return to the Corps of Engineers Board of Contract Appeals for determination of remaining issues on such claims, in accordance with this opinion. With respect to all other claims of the petition, the court concludes that plaintiff’s motion for summary judgment is denied, that defendant’s cross-motion is granted and that the petition is dismissed.

OPINION OP COMMISSIONER

Hogenson, Commissioner: This contract case questions pursuant to the standards for judicial review prescribed by the Wunderlich Act the finality of a decision of the Corps of Engineers Board of Contract Appeals, ENGr BCA No. 2784, 68-2 BCA ¶7344.

On April 16, 1962, plaintiff entered into Contract No. DA-45-164-CIVEN'Gr-62-302 with the Corps of Engineers for performance of certain parts of an overall project relocating a small city named Arlington, Oregon, which was necessitated by the construction of the John Day Dam on the Columbia River.

The nature of the overall project is reasonably summarized in the Board’s decision as follows:

* * * The business district and part of the residential area of the City of Arlington were relocated, as was the railroad and a small creek which went through the City of Arlington, known as China Creek. The principal features of the contract work [plaintiff’s contract with the Corps of Engineers] were clearing and grubbing, which included removal of old buildings and foundations, construction of a saturated fill area to be utilized as the site of the new business district, relocation of cer[887]*887tain streets adjacent to and in the relocated business district fill, construction of a concrete line channel for an existing creek, construction of a roadbed for a railroad shoofly, and construction of channel crossings for the shoofly and certain city streets. All work relating to installation of new sewer and water lines and grading and paving of residential streets were designed and performed under contracts advertised and awarded by the City of Arlington. The responsibilities of the City and the work to be performed pursuant to the authority of the City were set forth in a contract entered into between the City and the Government [United States] on 16 February 1961.

There were four contracts entered into by the City of Arlington to accomplish the parts of the relocation program assumed by the City. Three of them had plaintiff as the prime contractor: No. 1, dated October 9,1961, for construction of water and sewer systems and street improvements in the relocated residential area, and a new water reservoir; No. 2, dated May 24, 1962, for the construction of the water and sewer systems in the business district fill area and connection of such systems with the systems serving the residential area to the south, which contract was later amended to include installation of a new 8-inch water supply line from the City well house along E Street and connecting to the supply line from the new reservoir; and No. 3, dated June 15, 1962, for raising the City well house in place as well as making modifications thereto.

The fourth City of Arlington contract was one dated November 28,1962, with another contractor for relocation of the City Hall, which did not involve plaintiff. The only other contract involved in the relocation project was one between the State of Oregon and Pacific Concrete Company for construction of a viaduct, with plaintiff the subcontractor for construction of the viaduct ramps.

Thus, mainly as the prime contractor, but in relatively minor part as a subcontractor, plaintiff performed all of the relocation work, except relocation of the City Hall.

By the terms of its contract with defendant, the City was responsible for the administration of the contracts awarded by it, and retained an architect-engineer firm which prepared [888]*888the plans and specifications 'and acted as tbe supervising engineer for tbe City contracts. Defendant by its contract with tbe City, reserved tbe right to approve tbe City’s plans and specifications and to review and approve change orders and related expenditures for work to be performed under tbe City contracts.

Special Condition 1 (SC-1) of plaintiff’s contract with defendant required plaintiff to commence the specified contract work within 10 calendar days, and to complete as required by SC-le all such work including clean-up of the premises within 330 calendar days after receipt by plaintiff of defendant’s notice to proceed.

Plaintiff received defendant’s notice to proceed on April 19, 1962, and tbe overall contract completion date was thus fixed as March 15,1963.

However, Special Condition 1 (SC-1) also provided time limitations on various parts of tbe contract work and thus for priorities of work completion as follows:

a. The Contractor shall complete the removal, hauling and stockpiling of railroad track materials within 50 calendar days after date of receipt of notice to proceed.
b. The Contractor shall complete the subgrade of the detour, Locust Street, Columbia Street, Main Street and E. Street, except new bridge on Locust Street, within 90 calendar days after date of receipt of notice to proceed.
g. The Contractor shall complete the construction of the China Creek Channel walls from Station 2+77.03 to Station 5 + 60 on the right; from Station 2 +47.46 to Station 7+07.2 on the left; the floor from the designated construction point at Station 6+10 to Station 3+10; the left outlet wing wall and the left stilling basin wall from Station 14 + 56.42 to Station 15 + 14.7 within 120 calendar days after date of receipt of notice to proceed.
d. The Contractor shall complete the grading of the Condon Branch Shoofly within 140 calendar days after date of receipt of notice to proceed.

The provisions of SC-1c, supra, were modified during contract performance as hereinafter related, with SC-1/ added by such modification.

[889]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Natural Resources & Conservation v. United States
30 Cont. Cas. Fed. 70,906 (Court of Claims, 1983)
Sornsin Construction Co. v. State
26 Cont. Cas. Fed. 83,215 (Montana Supreme Court, 1978)
General Dynamics Corp. v. United States
585 F.2d 457 (Court of Claims, 1978)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
461 F.2d 1337, 198 Ct. Cl. 882, 1972 U.S. Ct. Cl. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carl-m-halvorson-inc-v-united-states-cc-1972.