Alloy Products Corp. v. United States

157 Ct. Cl. 376
CourtUnited States Court of Claims
DecidedMay 9, 1962
DocketNo. 50187
StatusPublished
Cited by12 cases

This text of 157 Ct. Cl. 376 (Alloy Products Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alloy Products Corp. v. United States, 157 Ct. Cl. 376 (cc 1962).

Opinion

Laramoiíe, Judge,

delivered the opinion of the court:

Plaintiff seeks judgment on the ground that the defendant has been unjustly enriched as a result of coercion and duress alleged to have been exercised by defendant’s officials, particularly a Mr. Moore, which plaintiff claims induced its execution of the 1944 renegotiation agreement, and by virtue of a mistake of law in interpretation of the covenant against contingent fees contained in the contract. Plaintiff asks this court to exercise its equitable jurisdiction to reform the 1944 renegotiation agreement and to render judgment in behalf of petitioner in the sum of $85,000.

The defendant, by counterclaim, seeks to recover from the plaintiff $143,145.40, consisting of the total of the amounts of $37,256.91 and $105,888.49 paid by the plaintiff to one Mr. Alders in 1942 and 1943, on the ground that those amounts were not legal or proper expenses of performing the plaintiff’s contracts with the defendant during those years and should not have been allowed as such expenses under the renegotiation agreements in 1942 and 1943 or in the termination settlement of plaintiff’s war contracts.

Respecting plaintiff’s petition, defendant maintains: (1) under the Renegotiation Act, 58 Stat. 78, the Court of Claims is without jurisdiction to entertain suits to set aside or reform agreements entered into pursuant to that act; (2) under section 403(c) (4) of the Renegotiation Act, supra, renegotiation agreements were conclusive according to their terms, and could not be set aside, even in a proper forum, except upon “a showing of fraud or malfeasance or willful misrepresentation of a material fact.”

While we believe there is no doubt that the exclusive jurisdiction is within the Tax Court to set aside or reform agreements entered into pursuant to the Renegotiation Act, supra, another reason exists which compels this court to hold that plaintiff cannot recover on its petition. Section 403 (c) (1) of the Renegotiation Act, supra, provides for the making of [379]*379agreements respecting renegotiation of war contracts. Section 403(c) (4) provides:

For the purposes of this section the Board may make final or other agreements with a contractor or subcontractor for the elimination of excessive profits and for the discharge of any liability for excessive profits under this section. Such agreements may contain such terms and conditions as the Board deems advisable. Any such agreement shall be conclusive according to its terms; and except upon a showing of fraud or malfeasance or a willful misrepresentation of a material fact, (A) such agreement shall not for the purposes of this section be reopened as to the matters agreed upon, and shall not. be modified by any officer, employee, or agent of the United States, and (B) such agreement and any determination made in accordance therewith shall not be annulled, modified, set aside, or disregarded in any suit, action, or proceeding, [p. 84]

In the instant case an agreement was entered into between plaintiff and the District Price Adjustment Section at Chicago, Illinois, acting on behalf of the War Contracts Price Adjustment Board, as provided for in section 403(c)(1), supra.

Thus we are called upon to decide whether the agreement was induced by fraud or malfeasance or a willful misrepresentation of a material fact. In the absence of such a showing, of course, under the statute the agreement cannot be reopened or modified by any officer, etc., of the United States, nor could the agreement be annulled, modified, set aside, or disregarded in any suit, action, or proceeding.

The findings of the commissioner which are adopted by the court, are conclusive on the subject. It is found as a fact, following a recitation of all the proceedings and facts relating to the signing of the renegotiation agreement that the evidence summarized in the findings does not sustain a finding that plaintiff’s acceptance of the 1944 renegotiation agreement was induced by duress or coercion or by malfeasance on the part of the Government’s representatives at the June 1, 1945 meeting.

Plaintiff, of course, has excepted to the findings of fact. Plaintiff’s argument largely is that the findings are not supported by the evidence, or that the evidence leans in an[380]*380other direction. In most instances, plaintiff has not pointed to an identifiable reference to the record which is provided for in Rule 46(c) of the Rules of this court. However, the gravamen of plaintiff’s case seems to be that Mr.. Hugh D. Moore, a Government negotiator, allegedly on June 1, 1945, represented to the plaintiff that plaintiff would have to forego tax credits provided for in 26 U.S.C. § 8806 (1989 I.R.C.) (1952 Ed.), and the Renegotiation Act, sufra, unless it signed the renegotiation agreement for 1944. Plaintiff contends that Moore “only misrepresented the regulation respecting tax credits,” and that “this was the only misrepresentation that was needed to serve Moore’s purpose at the moment.” Plaintiff then says “that purpose was to force an agreement on plaintiff to which plaintiff otherwise would not have assented.”

The short answer to this contention of plaintiff is that not'only was plaintiff represented by competent counsel who knew or- could have ascertained the provisions of the Internal Revenue Code and the Renegotiation Act, supra, but that plaintiff was well acquainted with the statutes involved. The 1942 renegotiation agreement signed by plaintiff ex-, pressly referred to section 3806 tax credits. Plaintiff’s renegotiation for 1943 likewise provided for tax credits under section 3806. As a matter of fact, in each of those years such tax credits reduced the actual renegotiation refund of excess profits. Moreover, plaintiff signed the renegotiation agreement after several conferences and months of careful consideration, coupled with consultations with its attorney. Furthermore, plaintiff was well aware, long before the signing of the agreement, that Alders’ fees might be totally disallowed. Therefore, it was no real surprise to plaintiff when the fees were actually disallowed.

In summary, all the details of the Renegotiation Act. and regulations and the provisions of section 3806 of the Internal Revenue Act were clear and, if not known to the plaintiff, were readily obtainable. Furthermore, it seems highly unlikely that either Mr. Moore, the Government negotiator, or the District Price Adjustment Board at Chicago would willfully mislead plaintiff to its disadvantage.

[381]*381As a matter of fact, plaintiff’s concept of duress is not sustained by the decisions of this court. For instance, in the case of Fruhauf Southwest Garment Co. v. United States, 126 Ct. Cl. 51, the court held that the legal meaning of economic duress involves a step beyond mere illegality and implies that a person has been unlawfully constrained or compelled by another to perform an act under circumstances which prevent the exercise of free will. No such showing has 'been made in this case.

In the case of Du Puy v. United States, 67 Ct. Cl. 318, 381, this language was used:

* * * In the case at bar the plaintiff, during the negotiations for settlement, was represented by able attorneys, and both they and the plaintiff knew before the settlement was signed everything that they know now.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airco, Inc. v. United States
557 F.2d 237 (Court of Claims, 1977)
American Aspen Corp.
513 F.2d 639 (Court of Claims, 1975)
Hinton
513 F.2d 638 (Court of Claims, 1974)
Oak Distributing Co. v. Miller Brewing Company
370 F. Supp. 889 (E.D. Michigan, 1973)
Carl M. Halvorson, Inc. v. United States
461 F.2d 1337 (Court of Claims, 1972)
Norman J. Mulholland v. The United States
361 F.2d 237 (Court of Claims, 1966)
Harvey-Whipple, Inc. v. The United States
342 F.2d 48 (Court of Claims, 1965)
Harvey-Whipple, Inc. v. United States
342 F.2d 48 (Court of Claims, 1965)
Tuason Construction Co.
166 Ct. Cl. 597 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
157 Ct. Cl. 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alloy-products-corp-v-united-states-cc-1962.