P. H. L. Development Corp. v. Sammy Garrison Construction, Inc.

319 S.E.2d 543, 171 Ga. App. 393, 1984 Ga. App. LEXIS 2213
CourtCourt of Appeals of Georgia
DecidedJune 28, 1984
Docket67966
StatusPublished
Cited by6 cases

This text of 319 S.E.2d 543 (P. H. L. Development Corp. v. Sammy Garrison Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. H. L. Development Corp. v. Sammy Garrison Construction, Inc., 319 S.E.2d 543, 171 Ga. App. 393, 1984 Ga. App. LEXIS 2213 (Ga. Ct. App. 1984).

Opinion

Carley, Judge.

Appellant-contractor entered into a written contract with appellee-subcontractor whereby appellee agreed to erect a pre-engineered metal building. After construction began, a dispute arose between the parties, and eventually appellee was prevented from performing any further work on the project. Appellee initiated the instant suit against appellant, seeking to recover the remaining balance of the contract price, plus an amount for additional work performed and expenses incurred as evidenced by certain change orders. Appellant answered and counterclaimed, alleging breach of contract by appellee. Appellant sought damages for expenses it had allegedly incurred in completing the contract. Following a jury trial, a verdict was returned for appellee for the full balance of the contract price plus the additional amount as evidenced by the change orders. Appellant appeals from the judgment entered on the verdict.

1. Appellant enumerates as error the general grounds. The evidence, while not without conflict, authorized the jury to make the following findings of fact: Under the terms of the contract, appellee was to erect a large pre-engineered metal building. Appellant was to fur *394 nish all of the necessary materials for the erection of the building. Sometime after commencement of the construction of the building, appellee discovered that appellant had not provided all of the necessary materials, and that some of the materials that had been provided were damaged. Delays in the subsequent erection of the building were caused by the lack of materials and by bad weather. Despite appellee’s numerous requests, appellant never provided the missing materials, which included roofing, side wall screws and mastic, nor did appellant replace the original damaged roof sheets. Due to time constraints and the specific instructions by the owners of the building, appellee completed the building without the missing materials and by utilizing the damaged roof sheets where possible. Specifically, the roof was erected without certain screws and mastic in areas in which they could later be applied. At all times, appellee had been ready, willing and able to return to the project upon the receipt of the missing materials. Approximately two weeks after appellee’s completion of its initial work on the project, appellee returned to the job at the owner’s request in order to repair reported leaks in the roof. The following week, appellee received another call to repair additional leaks. Appellee sent a crew to the job site but was prevented by appellant from performing any further work on the building at that time. With the owner’s permission, appellee was able to repair the leaks the following weekend. Appellee has received no other calls from appellant or the owner concerning the need for any further repairs to the building. There was evidence that 85 to 90% of the roofs of similar metal buildings leak initially, and that it is common practice for the erector of such metal buildings to return to the job for up to a year in order to repair leaks. There was also evidence that appellee had performed the job in a satisfactory manner, and the job was completed except for materials it never received. Furthermore, appellee did not perform the job in the specified time period because of delays caused by the lack of materials.

Appellant contends that on this evidence a finding is demanded that appellee did not fully perform its obligation under the contract, and that appellee may not recover the full contract price but only for that portion of the contract which it has performed. Appellant relies specifically on appellee’s admission that it never applied the mastic or screws in the erection of the roof.

“ ‘[I]t is generally held that, where the compensation is due only on the performance of the contract, a literal and strict performance is not required, and if the builder acting in good faith and intending and attempting to perform his contract, does so, he may recover the contract price, notwithstanding slight and trivial defects or deviations in performance, for which compensation may be made, in all its material and substantial particulars, by an allowance to the owner.’ *395 [Cits.]” (Emphasis supplied.) Allied Enterprises v. Brooks, 93 Ga. App. 832, 834 (3) (93 SE2d 392) (1956). The evidence of record authorized the jury to find that appellee substantially performed the contract. There was evidence that appellee completed the erection of the building with the exception of the placement of the missing materials. There was further evidence in the form of testimony by appellee’s expert that the work was satisfactorily performed. Moreover, we note that because there was evidence to authorize the jury to find that appellee’s obligations under the contract had been substantially performed, such of appellant’s contentions as are predicated upon the terms of the contract regarding appellee’s default are without merit.

Furthermore, under the above-stated principles of law, the evidence in the instant case does not demand that appellant be given an “allowance” for any “slight and trivial defects in [appellee’s] performance.” Allied Enterprises v. Brooks, supra at 834. It has been held that “ ‘where a defendant prevents the performance of a stipulation of a contract undertaken by the plaintiff, he is estopped from setting up in his own behalf any injury which may have resulted from the non-performance of such condition.’ [Cits.]” Allied Enterprises v. Brooks, supra at 834. Thus, even if the evidence demanded a finding that appellee’s work was incomplete or defective in the manner alleged by appellant, the jury was clearly authorized to also find that by not providing the necessary materials and by preventing its crews from repairing the leaks in the roof, appellant wrongfully prevented appellee from timely performing the remainder of the work on the contract. A finding that appellee was entitled to the entire contract price plus the amount for additional work was authorized by the evidence.

2. Appellant enumerates as error the admission, over its hearsay objection, of testimony to the effect that its men had been on the roof after appellee had left the job. The transcript reveals that similar testimony by other witnesses was later admitted into evidence without objection. The erroneous admission of evidence over objection is not reversible error where similar evidence is subsequently admitted without objection. See Cloer v. Life & Cas. Ins. Co., 222 Ga. 798, 801 (2) (152 SE2d 857) (1966); Eiberger v. Martel Electronic Sales, 125 Ga. App. 253, 255 (6) (187 SE2d 327) (1972).

3. During trial, appellant attempted to admit into evidence a letter written by a non-party to the action and addressed to appellant. The letter referred to specific areas of defective workmanship which the author had discovered during his inspection of the project. Appellee made a hearsay objection. The trial court allowed the witness for appellant to testify as to the existence and nature of the letter and as to appellant’s subsequent actions and conduct which resulted from *396 the letter. However, testimony as to the contents of the letter and the letter itself were excluded. Appellant enumerates as error the exclusion of the letter, asserting that it was admissible as original evidence to explain conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southeastern Erectors, LLC v. Premier Building Systems, Inc.
820 S.E.2d 214 (Court of Appeals of Georgia, 2018)
Daniel v. Parkins
409 S.E.2d 233 (Court of Appeals of Georgia, 1991)
Collins v. Davis
366 S.E.2d 769 (Court of Appeals of Georgia, 1988)
Hall v. State
350 S.E.2d 801 (Court of Appeals of Georgia, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
319 S.E.2d 543, 171 Ga. App. 393, 1984 Ga. App. LEXIS 2213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-h-l-development-corp-v-sammy-garrison-construction-inc-gactapp-1984.