Sasser & Co. v. Griffin

210 S.E.2d 34, 133 Ga. App. 83, 1974 Ga. App. LEXIS 976
CourtCourt of Appeals of Georgia
DecidedOctober 21, 1974
Docket49659, 49660
StatusPublished
Cited by38 cases

This text of 210 S.E.2d 34 (Sasser & Co. v. Griffin) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sasser & Co. v. Griffin, 210 S.E.2d 34, 133 Ga. App. 83, 1974 Ga. App. LEXIS 976 (Ga. Ct. App. 1974).

Opinion

Eberhardt, Presiding Judge.

Plaintiff, a subcontractor, brought this action against Sanford and Space, the prime contractor, seeking payment under the subcontract, and against the owners of property on which Sanford and Space constructed a high-rise apartment building, seeking the establishment of a lien thereon. From a denial of plaintiffs motion for summary judgment, plaintiff appeals on a certificate of review (Case 49659). By cross appeal Sanford and Space assert errors as to the trial court’s disposition of various other motions made during the proceedings below (Case 49660).

Plaintiff contends it is entitled to a summary judgment or at least a partial summary judgment in the amounts of $29,749.59 (for one contract) and $1,500 (for a second contract). The pleadings, affidavits and interrogatories show that the owners of certain property in Savannah, Georgia contracted with Sanford and Space for the construction of a high-rise apartment building. Sanford and Space in turn entered into two subcontracts *84 with plaintiff to install the plumbing and heating systems and the air conditioning units for the building. The entire project was to be completed by April 1,1971, according to the prime contract to which plaintiff bound itself. Plaintiff did not complete performance until July, 1971 and there is evidence that plaintiff performed additional work on the project in August, 1971.

Both subcontracts provided that plaintiff was to be paid by Sanford and Space "as the work progresses, based on estimates and certificates of the architects or contractor and payments will be made from money received from the owner only and divided pro rata amount [sic] all approved accounts of subcontractors labor and material.” (Emphasis supplied.) This provision was amended in the plumbing and heating contract in that the italicized words were stricken and there was substituted "[b]y 20th of each month following, less 10% retained until completion of job. Subcontractor will be paid by contractor for approved work in place even though payment by the owner has been withheld from contractor for reasons not the fault of the subcontractor.” The air conditioning subcontract was not so amended but does contain this added provision: "Payment within 10 days of receiving money from owner — approximately 20th of the month.”

In July, 1971, the designing architect certified that the project was substantially complete and directed the owners to pay to Sanford and Space all retainage under the contract on work completed by that time. The owners claim they have paid Sanford and Space all monies due them under the contract, though they deny approval of the project. (The owners and Sanford and Space are presently involved in litigation in Chatham Superior Court). In August, 1971, the owner’s lessee Housing Authority began occupying the building. On October 29, 1971, the plaintiff filed for record a materialman’s claim of lien for $29,516.06 on the plumbing and heating subcontract and $1,500 on the air conditioning subcontract. Held:

1. Under Ga. L. 1967, p. 456 (Code Ann. § 67-2002 (2)), the recording of a materialman’s lien must be within three months after the last material is furnished to the *85 construction project. Even though the project was certified as being substantially complete on July 29, the plaintiff has submitted affidavits and invoices showing equipment and labor were furnished to the project on July 30, August 2 and August 4, all within three months of filing on October 29. None of the three owners has submitted any evidence in rebuttal, but rest on the denials of timely filing in their answers. "When a motion for summary judgment is made and supported as provided in this section, an adverse party may not rest upon the mere allegations or denials of his pleadings, but his response, by affidavits or as otherwise provided in this section must set forth specific facts showing that there is a genuine issue for trial.” Civil Practice Act § 56 (e) (Code Ann. § 81A-156). There being no genuine issue of fact as to plaintiffs establishment of a materialman’s lien in the amounts alleged, it was error not to grant plaintiffs motion for summary judgment for that purpose against defendants Joseph Griffin, Jr., and Chatham-Savannah. As to lessee, Housing Authority, as an original proposition, Ga. L. 1937, pp. 210, 229; 1939, p. 124 (Code Ann. § 99-1130) may exempt it from a "lien upon its real property,” but in leasing the property it took subject to any lien rights of which it may have had actual notice. Oglethorpe Sav. & Trust Co. v. Morgan, 149 Ga. 787 (1) (102 SE 528). An estate for years may be subjected to the lien. James G. Wilson Mfg. Co. v. Chamberlin-Johnson-Dubose Co., 140 Ga. 593 (79 SE 465). Here a factual issue remains.

None of the owners has a contractual liability, jointly or otherwise, to plaintiff since they were not parties to the subcontracts between plaintiff and Sanford and Space, but this does not prevent the establishment of a lien by a subcontractor under Code Ann. § 67-2001 (2). See Stein Steel & Supply Co. v. Goode Const. Co., 83 Ga. App. 821 (65 SE2d 183).

2. Sanford and Space and their surety, defendant Travelers Indemnity Company, have defended against plaintiffs action on the contract on two grounds: (a) payment by owners to Sanford and Space was a condition precedent to latter’s liability to plaintiff under the terms of both subcontracts, and owners had not paid all sums *86 due under the prime contract; and, (b) plaintiff had breached the subcontract by not completing performance by the time required in the prime contract.

The owners and Sanford and Space cross claimed against each other in the event either should be found liable to plaintiff. Other defenses and motions proffered by Sanford and Space will be treated below in Division 3 dealing with its cross appeal.

(a) The language in the amendment of the plumbing and heating subcontract clearly shows that the parties intended for plaintiff to be paid independently of payments received from the owners by Sanford and Space. While the owners deny approval of the entire project, they do not dispute that plaintiff has completed his performance under the subcontract. That contract is to be enforced as written. "It is the duty of the courts to construe and enforce contracts as made, and not to make them for the parties.” Carr v. L. & N. R. Co., 141 Ga. 219, 222 (80 SE 716); Gray v. Akin, 205 Ga. 649, 652 (54 SE2d 587). We are not at liberty to revise a contract while professing to construe it. Reynolds v. Tufts, 123 Ga. App. 147, 149 (179 SE2d 652).

There is, however, no such amendment to the air conditioning subcontract, and it provides "payments will be made from money received from the owner only” and "payment within 10 days of receiving money from owner — approximately 20th of the month.”

A provision in a contract may make payment by the owner a condition precedent to a subcontractor’s right to payment if "the contract between the general contractor and the subcontractor should contain an express condition clearly showing that to be the intention of the parties.” Thomas J. Dyer & Co. v. Bishop Internat. Engineering Co., 303 F2d 655, 661.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mueller Systems, LLC v. Sipco, LLC
Court of Appeals of Georgia, 2025
Pinnacle Properties V, LLC v. Mainline Supply Of
Court of Appeals of Georgia, 2012
Pinnacle Properties V, LLC v. Mainline Supply of Atlanta, LLC
735 S.E.2d 166 (Court of Appeals of Georgia, 2012)
Powell Company v. McGarey Group, LLC
508 F. Supp. 2d 1202 (N.D. Georgia, 2007)
Gould v. Gould
523 S.E.2d 106 (Court of Appeals of Georgia, 1999)
Resurgens Plaza South Associates v. Consolidated Electric Supply, Inc.
452 S.E.2d 784 (Court of Appeals of Georgia, 1994)
Exterior Wall Systems, Inc. v. Dean
436 S.E.2d 543 (Court of Appeals of Georgia, 1993)
Caribbean Lumber Co. v. Anderson
422 S.E.2d 267 (Court of Appeals of Georgia, 1992)
U3S Corp. of America v. Parker
414 S.E.2d 513 (Court of Appeals of Georgia, 1991)
Georgia Glass & Metal, Inc. v. Arco Chemical Co.
410 S.E.2d 142 (Court of Appeals of Georgia, 1991)
Uniflex Corp. v. Saxon
402 S.E.2d 67 (Court of Appeals of Georgia, 1991)
A. L. Williams & Associates, Inc. v. Faircloth
380 S.E.2d 471 (Court of Appeals of Georgia, 1989)
Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)
Spicewood, Inc. v. Ferro Pipeline Co.
351 S.E.2d 711 (Court of Appeals of Georgia, 1986)
Siplast, Inc. v. Inland Container Corp.
323 S.E.2d 187 (Court of Appeals of Georgia, 1984)
Norton v. Herron
677 P.2d 877 (Alaska Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
210 S.E.2d 34, 133 Ga. App. 83, 1974 Ga. App. LEXIS 976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sasser-co-v-griffin-gactapp-1974.