John's Insulation, Inc. v. Hartford Accident & Indemnity Co. (In Re John's Insulation, Inc.)

221 B.R. 683, 1998 Bankr. LEXIS 746, 32 Bankr. Ct. Dec. (CRR) 930, 1998 WL 336625
CourtUnited States Bankruptcy Court, E.D. New York
DecidedJune 23, 1998
Docket8-12-71297
StatusPublished
Cited by7 cases

This text of 221 B.R. 683 (John's Insulation, Inc. v. Hartford Accident & Indemnity Co. (In Re John's Insulation, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John's Insulation, Inc. v. Hartford Accident & Indemnity Co. (In Re John's Insulation, Inc.), 221 B.R. 683, 1998 Bankr. LEXIS 746, 32 Bankr. Ct. Dec. (CRR) 930, 1998 WL 336625 (N.Y. 1998).

Opinion

DECISION ON MOTION TO DISMISS ADVERSARY PROCEEDING FOR FAILURE TO STATE A CLAIM UPON WHICH RELIEF CAN BE GRANTED

JEROME FELLER, Bankruptcy Judge.

Defendant Hartford Accident and Indemnity Co. (“Hartford”) moves to dismiss this adversary proceeding, brought in the Chapter 11 bankruptcy case of John’s Insulation, Inc., for failure to state a claim upon which relief can be granted pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure (“Fed. R. Civ.P.”), made applicable hereto by Rule 7012(b) of the Federal Rules of Bankruptcy Procedure (“Fed. R. Bankr. P.”). The parties agree that New York law governs.

In its complaint, John’s Insulation seeks an affirmative recovery of damages, as well as a disallowance of Hartford’s general unsecured claim. After considering the complaint, the parties’ memoranda either in support of or in opposition to the motion, and our own independent inquiry, we find that the complaint forwards no discernible legal basis for an affirmative claim of relief. 1 Although the complaint advances cognizable defenses to Hartford’s unsecured claim, in the absence of an associated cognizable demand for relief brought pursuant to Fed. R. Bankr.P. 7001, the proper vehicle for such objections is by motion, as provided in Fed. R. Bankr.P. 3007. Accordingly, for the reasons hereafter discussed, the motion is granted and the instant adversary proceeding is dismissed.

I. BACKGROUND

Hartford, as surety, issued a performance bond on behalf of John’s Insulation, a construction company located in Long Island City, Queens, as a prerequisite for the award of a $3.5 million construction contract to provide labor and material for the installation of a heat recovery system for the New York City Department of Sanitation (“City”). The bond ensured completion of construction by binding Hartford to perform in the event of a default by John’s Insulation. In order to obtain the performance bond, John’s Insulation entered into a General Indemnity Agreement (“Indemnity Agreement”) with Hartford, on or about May 20, 1985. 2 The Indemnity Agreement provided Hartford with a contractual right of indemnification should it incur any loss from completing the construction contract, pursuant to the perfor- *686 manee bond, after a default by John’s Insulation.

Ultimately, John’s Insulation was defaulted by the City, which retained a progress payment of approximately $400,000.00 for work completed by John’s Insulation that was “in the pipeline” and awaiting final approval for disbursement. Subsequently, Hartford was called upon to finish the installation work. The City applied the retained progress payment, in addition to the unearned monies remaining under the contract, toward Hartford’s completion of construction, which included employing engineers, lawyers, and replacement contractors. Upon approving the completed work, the City owed a final payment under the contract of $408,403.51.

John’s Insulation, which had since filed a petition for relief under Chapter 11, initiated an adversary proceeding against both the City and Hartford, blocking Hartford’s receipt of the final payment and claiming entitlement to those monies. Hartford, on the other hand, as completing surety, filed a general unsecured claim in the Chapter 11 case based on its indemnification rights, in the amount of $500,113.04. By stipulation entered into between the parties and so ordered by this Court, the $408,403.51 final payment was escrowed in an account jointly held by John’s Insulation and Hartford through their respective attorneys. This initial adversary proceeding ended on the grant of a motion to dismiss without prejudice to the filing of a second adversary proceeding, solely against Hartford, to resolve the competing claims to the escrowed funds.

In its second complaint, the one presently before the Court, John’s Insulation alleges that there were no disputes regarding any of the work that it had performed on the contract, which at the time of default was roughly 86% completed. After the default, the City requested the performance of extra work by the replacement contractors and the use of additional materials, both of which exceeded the specifications of the original contract. At times, the extra work included scrapping and rebuilding portions of the project previously completed by John’s Insulation and approved by the City. However, Hartford faded to demand compensation for these extras. John’s Insulation further alleges that Hartford failed to exercise proper care in reviewing and settling payments to the contractors, consulting engineers, and legal counsel that were hired, resulting in exorbitant and exaggerated payouts.

Relying on these factual allegations, the complaint advances three theories of recovery: breach of contract, negligence, and improper accounting. First, the Indemnity Agreement explicitly and impliedly required Hartford to complete the construction reasonably and in good faith. Hartford’s breach of the Indemnity Agreement is evidenced by the performance of extra work without demanding adequate compensation and by honoring inflated billing requests. Next, Hartford was negligent in not properly overseeing the construction. Similar to the breach of contract claim, it knew or should have known that the extra work was beyond the terms of the contract and that work was being billed at exorbitant rates. Finally, John’s Insulation claims that Hartford improperly accounted for the money it received and expended on the job, which resulted in the assessment of an overcharge on Hartford’s indemnity claim.

As a remedy under the breach of contract and negligence causes of action, John’s Insulation demands that Hartford’s unsecured claim be disallowed. There is no basis for Hartford to seek indemnification because it has already been fully reimbursed for the reasonable costs and expenses of completing the construction. These two causes of action also demand judgment for the $408,403.51 escrowed by the City. John’s Insulation claims that but for Hartford’s negligence and/or breach of the Indemnity Agreement, the escrowed monies would represent a contract surplus. Therefore, the escrowed monies should be awarded free and clear of any claims of indemnity. Finally, John’s Insulation seeks $538,769.00 under the improper accounting cause of action, claiming that it is owed an additional $130,366.00 in excess of the escrow account for monies that Hartford improperly overcharged.

Hartford counters with the instant motion to dismiss for failure to state a claim upon which relief can be granted. Regarding the *687 negligence cause of action, Hartford asserts that absent a violation of a legal duty independent of the contract, New York law does not support such claims. Under the breach of contract claim, neither party questions the fact that John’s Insulation was defaulted on the contract with the City.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
221 B.R. 683, 1998 Bankr. LEXIS 746, 32 Bankr. Ct. Dec. (CRR) 930, 1998 WL 336625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johns-insulation-inc-v-hartford-accident-indemnity-co-in-re-johns-nyeb-1998.