Buck Run Baptist Church, Inc. v. Cumberland Surety Insurance Co.

983 S.W.2d 501, 1998 Ky. LEXIS 160, 1998 WL 897028
CourtKentucky Supreme Court
DecidedDecember 17, 1998
Docket97-SC-979-DG
StatusPublished
Cited by15 cases

This text of 983 S.W.2d 501 (Buck Run Baptist Church, Inc. v. Cumberland Surety Insurance Co.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buck Run Baptist Church, Inc. v. Cumberland Surety Insurance Co., 983 S.W.2d 501, 1998 Ky. LEXIS 160, 1998 WL 897028 (Ky. 1998).

Opinion

WINTERSHEIMER, Justice.

This appeal is from a decision of the Court of Appeals reversing an order staying arbitration by the circuit court. The underlying dispute is between Buck Run Baptist Church, Inc. and Cumberland Surety Insurance Company, Inc. on a performance bond issued by Cumberland which guarantees performance of the general contractor on the construction of a new sanctuary and educational building for the church.

The principal issue is whether Buck Run can be required to arbitrate with Cumberland Surety under contractual provisions between the church and its general contractor to which Cumberland Surety issued a performance bond for the satisfactory completion of the construction project. Buck Run argues that the dispute is not subject to arbitration because the performance bond is an insurance contract rendering any dispute arising thereunder exempt from arbitration pursuant to KRS 417.050. Other questions raised will be considered in this Opinion.

In 1993, Buck Run Baptist Church entered into a standard agreement between owner and contractor pursuant to a standard form *503 issued by the American Institute of Architects with Z & J Construction, Inc., a Kentucky corporation, for the construction of a new worship center and educational building for the church in rural Franklin County, Kentucky. Pursuant to the terms of the contract, Buck Run and Z & J agreed that all controversies and claims arising out of the contract or from any breach thereof would be subject to binding arbitration. At the same time, Cumberland Surety issued a Payment and Performance Bond in the amount of $1,472,400, which provided that the contract between Buck Run and Z & J was made a part of the bond, the same as though it was set forth herein.

In the Fall of 1993, there were concerns about the performance of the contract, and on July 21, 1994, the project architect notified Buck Run that sufficient cause existed to terminate the contractor. Pursuant to the terms of the bond, Cumberland retained another contractor to complete the project; however, a dispute arose as to the performance of the new contractor and Buck Run refused to pay the remainder due on the contract. Cumberland made a demand for arbitration and later filed a declaratory judgment action seeking to compel Buck Run to arbitrate claiming that the church had wrongfully refused to pay the remaining contract balance of $66,522.54. Buck Run responded that the project had not been completed and that the dispute with Cumberland was not subject to arbitration because KRS 417.050 provided that disputes arising from insurance contracts are not subject to arbitration. The circuit court determined that the claims were not subject to arbitration because of the exemption. The Court of Appeals reversed the circuit court and in a split decision, determined that arbitration was the proper remedy. This Court granted discretionary review.

This dispute involves the completion of certain requirements of a construction contract, the entitlement of Cumberland Surety to the balance due under the construction contract and other damages. The proposed arbitration proceeding does not involve an insurance contract which is exempt from compulsory arbitration under the terms of KRS 417.050, and consequently, the Court of Appeals was correct when it determined that the trial court was in error by finding that the term “insurance contracts” as set forth in KRS 417.050 was intended to include the surety bond issued by Cumberland in this case. Cf. Valley Construction Co. v. Perry Host Management Co., Ky.App., 796 S.W.2d 365 (1990). There was no disagreement between the parties as to their respective rights, duties and obligations under the payment and performance bond. Cumberland discharged its surety obligation under the bond by causing to have performed the Z & J original construction contract. The present dispute arises from a disagreement as to whether Cumberland completed its construction project consistent with the original contract terms and conditions.

The Cumberland Surety performance bond clearly and specifically incorporated by reference the construction contract between Buck Run and Z & J. Therefore, the Court of Appeals was correct in its determination that if the arbitration provisions of that contract are otherwise enforceable, they are binding on Buck Run. Cumberland, in effect, stood in the shoes of Z & J and became the contractor on the project. Consequently, Cumberland is entitled to enforce the construction contract arbitration agreement. This dispute involves a construction contract, and not the applicability of an insurance exemption to the statute.

Home Lumber Co. v. Appalachian Regional Hospitals, Inc., Ky.App., 722 S.W.2d 912 (1987), held that a prime construction contract which required arbitration could be incorporated by reference into a purchase order contract with a material supplier. However, a majority of the Court of Appeals panel in that case believed that there was a, question of fact and remanded the ease for a factual determination of that question. In this ease, the language of the performance bond clearly incorporates by reference the contract between Buck Run and Z & J. Therefore, Home Lumber Co., supra, is clearly distinguishable.

Such a decision is consistent with the well reasoned authorities from other jurisdictions which have considered the question. *504 See Commercial Union Insurance Co. v. Gilbane Building Co., 992 F.2d 386 (1st Cir. 1993). Kentucky has favored the enforcement of private arbitration contracts. Cf. Kodak Mining Co. v. Carrs Fork Corp., Ky., 669 S.W.2d 917 (1984); Fite & Warmath Constr. Co. v. MYS Corp., Ky. 559 S.W.2d 729 (1977). In MYS Corp., supra, this Court observed that there is a significant difference between an adhesion contract in which the parties have disparate bargaining power and a contract which voluntarily has been entered into by sophisticated and knowledgeable businessmen concerning a financial transaction of considerable magnitude. Here the church had the advice of a professional architect who in fact recommended that it terminate the original construction contract. As noted in MYS Corp., the parties should not be free to repudiate promises to arbitrate.

There is a significant difference between types of insurance contracts contemplated by KRS

Related

University of Kentucky v. Peter Regard
Kentucky Supreme Court, 2023
Mitsui Sumitomo Ins. USA, Inc. v. Denham-Blythe Co.
375 F. Supp. 3d 788 (E.D. Kentucky, 2019)
John Daugherty v. American Express Company
485 F. App'x 746 (Sixth Circuit, 2012)
In re: Steven Brockman v.
Sixth Circuit, 2011
Valued Services of Kentucky, LLC v. Watkins
309 S.W.3d 256 (Court of Appeals of Kentucky, 2009)
Estate Of Kenneth Stewart Riddle
421 F.3d 400 (Sixth Circuit, 2005)
National Home Insurance v. King
291 F. Supp. 2d 518 (E.D. Kentucky, 2003)
Sifuentes v. State
29 S.W.3d 238 (Court of Appeals of Texas, 2000)
Gomes v. State
9 S.W.3d 373 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
983 S.W.2d 501, 1998 Ky. LEXIS 160, 1998 WL 897028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buck-run-baptist-church-inc-v-cumberland-surety-insurance-co-ky-1998.