Fite & Warmath Const. Co., Inc. v. Mys Corp.

559 S.W.2d 729, 1977 Ky. LEXIS 559
CourtKentucky Supreme Court
DecidedDecember 9, 1977
StatusPublished
Cited by27 cases

This text of 559 S.W.2d 729 (Fite & Warmath Const. Co., Inc. v. Mys Corp.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fite & Warmath Const. Co., Inc. v. Mys Corp., 559 S.W.2d 729, 1977 Ky. LEXIS 559 (Ky. 1977).

Opinion

REED, Justice.

The decisive issue presented by this appeal is whether the trial court was correct in enforcing a contractual agreement to arbitrate instead of applying what is generally described as the common-law rule, which regards as revocable by either party any agreement between them to arbitrate future disputes.

In November 1969, Fite and Warmath Construction Company, Inc., a Tennessee corporation, entered into a “cost-plus” contract with MYS Corporation, a Kentucky corporation wholly owned by New York residents, in which Fite agreed to serve as general contractor for MYS in the construction of a commercial shopping mall in Hop-kinsville, Kentucky. The contract, executed in New York City, was a printed standard-form agreement between owner and general contractor provided by the American Institute of Architects. It contained detailed provisions concerning the rights and duties of the contracting parties. In addition, it contained an agreement to arbitrate which read:

“7.10 ARBITRATION
“7.10.1 All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, except as set forth in Subpara-graph 2.2.9 with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment as provided by Subpara-graphs 9.7.5 and 9.7.6, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.
“7.10.2 Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Sub-paragraphs 2.2.10 and 2.2.11 where applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred, by the applicable statute of limitations.”

Thereafter, Fite commenced construction and the parties performed under the contract for about one year. On November 19, 1970, precipitated by a series of disputes between them, Fite and MYS entered into a memorandum agreement whereby they mutually agreed to terminate their contract as *732 of 12:00 noon, Monday, November 12, 1970. Besides reciprocal pledges of cooperation to insure an orderly transfer of the project, this memorandum recited that the disputes “shall be decided in accordance with the terms of the original contract,” and that “the interpretation of the contract shall be controlled by the laws of the State of Kentucky applicable to the execution of the original contract.” (emphasis supplied).

On January 8, 1970, after withdrawing from the job site, Fite filed a mechanics and materialman’s lien against the project in the office of the Christian County Clerk.

On April 23, 1971, MYS filed a demand for arbitration with the American Arbitration Association pursuant to section 7.10 of the original contract as reconfirmed in the November 19, 1970, memorandum of agreement terminating the relationship.

In the arbitration demand, MYS alleged 15 separate contractual violations, asserting that Fite had failed to provide qualified supervisory personnel, had awarded subcontracts at higher than market prices, had purchased materials which did not meet trade standards or contract terms, had employed more workmen than were necessary, had permitted unauthorized changes from plans, and had caused unnecessary delays.

On May 6, 1971, Fite filed suit in the circuit court against MYS to enforce its lien (KRS 376.010, et seq.) in the amount of $1,084,246.58 and for general damages in amount of $3,800,000. On May 10, 1971, Fite filed its answer with the arbitration association in which it asserted that there was no necessity to arbitrate because of its pending suit in the state court; it also stated that any award by arbitrators would not be binding upon the state court.

After other procedural skirmishes were completed, the circuit court ruled that the arbitration agreement was enforceable and stayed the state court proceedings until arbitration was completed.

After extensive proceedings in which Fite and MYS fully participated, the arbitration tribunal rendered its award on December 9, 1973. This award was in favor of MYS against Fite in the sum of $326,141.42, plus interest at 6 per cent per annum from April 28, 1971. Despite Fite’s various objections to the award, including the complaint that it did not contain separate findings of fact, the circuit court entered the arbitration award as the judgment of the court. Fite appeals. We affirm the judgment of the circuit court for the reasons later stated.

I.

The trial judge held that the United States Arbitration Act of 1925 1 applied. Section 2 of this Act declares in pertinent part that a written provision for arbitration in “any contract evidencing a transaction involving commerce” shall be valid and irrevocable and enforceable except upon such grounds as exist at law or in equity for the revocation of any contract.

From undisputed evidentiary material, the trial judge made the following significant factual findings:

Fite is a Tennessee corporation with its principal place of business in Tennessee. MYS is a Kentucky corporation with its principal place of business in New York, New York. The supervising architects are residents of New York. The construction loan which financed the project was made by the Manufacturers Hanover Trust Company of New York, New York. Eighty-eight per cent of the subcontractors engaged in the construction project were nonresidents of Kentucky and many of the employees crossed the Kentucky-Tennessee border daily to perform work on the mall. The majority of the tenants of the mall are corporations incorporated under the laws of a state other than Kentucky and maintaining their respective principal places of business in a state other than Kentucky.

After reciting these factual findings, the trial judge stated: “The court finds as a matter of fact at the time the parties entered into the contract on November 11, 1969, in New York, New York, both parties contemplated a transaction involving inter *733 state commerce within the meaning of the Federal Arbitration Act, Title 9, U.S.C. Sections 1 and 2.” Fite argues that the Supreme Court of the United States has recognized that the U. S. Arbitration Act is not applicable in state courts. It relies as authority upon the cases of Prima Paint Corporation v. Flood & Conklin Mfg. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitsui Sumitomo Ins. USA, Inc. v. Denham-Blythe Co.
375 F. Supp. 3d 788 (E.D. Kentucky, 2019)
Ernst & Young, LLP v. Clark
323 S.W.3d 682 (Kentucky Supreme Court, 2010)
Garrison v. PALMAS DEL MAR HOMEOWNERS ASS'N, INC.
538 F. Supp. 2d 468 (D. Puerto Rico, 2008)
Weis Builders, Inc. v. Complete Contracting, Inc.
247 S.W.3d 542 (Court of Appeals of Kentucky, 2008)
State Farm Mutual Automobile Insurance Co. v. Marley
151 S.W.3d 33 (Kentucky Supreme Court, 2004)
Louisville Peterbilt, Inc. v. Cox
132 S.W.3d 850 (Kentucky Supreme Court, 2004)
Saneil v. Robards
289 F. Supp. 2d 855 (W.D. Kentucky, 2003)
Buck Run Baptist Church, Inc. v. Cumberland Surety Insurance Co.
983 S.W.2d 501 (Kentucky Supreme Court, 1998)
Valley Construction Co. v. Perry Host Management Co.
796 S.W.2d 365 (Court of Appeals of Kentucky, 1990)
RIVERFRONT PROP. LTD. v. Max Factor III
460 So. 2d 948 (District Court of Appeal of Florida, 1984)
Kodak Mining Co. v. Carrs Fork Corp.
669 S.W.2d 917 (Kentucky Supreme Court, 1984)
Atlantic Painting & Contracting Inc. v. Nashville Bridge Co.
670 S.W.2d 841 (Kentucky Supreme Court, 1984)
Ex Parte Alabama Oxygen Co., Inc.
433 So. 2d 1158 (Supreme Court of Alabama, 1983)
Keating v. Superior Court
645 P.2d 1192 (California Supreme Court, 1982)
MERRILL LYNCH PIERCE, ETC. v. Melamed
405 So. 2d 790 (District Court of Appeal of Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
559 S.W.2d 729, 1977 Ky. LEXIS 559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fite-warmath-const-co-inc-v-mys-corp-ky-1977.