Pathman Construction Co. v. Knox County Hospital Ass'n

326 N.E.2d 844, 164 Ind. App. 121, 1975 Ind. App. LEXIS 1121
CourtIndiana Court of Appeals
DecidedMay 5, 1975
Docket1-474A60
StatusPublished
Cited by29 cases

This text of 326 N.E.2d 844 (Pathman Construction Co. v. Knox County Hospital Ass'n) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pathman Construction Co. v. Knox County Hospital Ass'n, 326 N.E.2d 844, 164 Ind. App. 121, 1975 Ind. App. LEXIS 1121 (Ind. Ct. App. 1975).

Opinion

Lowdermilk, J.

This is an appeal from a judgment declaring an arbitration provision null and void, and enjoining any further action to enforce said provision.

*123 The pertinent facts establish that on August 14, 1968, plaintiffs-appellees, Knox County Hospital Association and the Governing Board of Knox County Hospital (hereinafter collectively referred to as “Hospital” unless otherwise indicated respectively as “Association” or “Board”), and defendants-appellants, Pathman Construction Company (Company), an Illinois corporation, entered into a construction contract for the building and remodelling of the Good Samaritan Hospital in Vincennes, Indiana, which contract was for $3,767,000.

Subsequently, on April 5, 1972, the contract was assigned to Pathman Construction Corporation of Indiana (Pathman). Numerous subcontractors were employed and among these were included several out-of-state companies and some out-of-state employees. The dollar value of the out-of-state contracts totalled over $700,000 and included such items as cabinets and such major components as structural steel and windows to be included in the hospital.

The contract between the parties included an arbitration clause which, in pertinent part, is as follows:

“7. Arbitration.— (a) It is mutually agreed that all disputes arising in connection with this contract shall be submitted to arbitration in accordance with the provisions of the current Standard Form of Arbitration Procedure of the American Institute of Architects and that all findings of fact by the arbitrators under this agreement shall be conclusive and binding on both parties. It is further mutually agreed that the decision of the arbitrators shall be a prior condition to any right of legal action which either party to the contract may have against the other.
(b) The work under this contract shall not be stopped or delayed in any way during the arbitration proceedings except by written mutual consent of both parties to the contract, and such mutual consent shall stipulate whether extension of the time for completion of the contract will be authorized by such stoppage or delay.
(c) Demand for arbitration in connection with any dispute shall be filed in writing with the Architect and with the other party to the contract. Any demand for arbitration shall be made within thirty days after the dispute has arisen *124 if practicable, but, in any event, no demand for arbitration shall be made after the date of final payment except in the case of a dispute arising in connection with any guarantee provisions of the Contract Documents.
(d) The arbitrators hereunder shall have authority to award to the party whose contentions are approved as being in conformity with contract requirements such sums as they, or a majority of them, consider is proper to compensate the injured party for any loss in connection with the proceedings ; and, if they find that the arbitration proceedings were demanded without reasonable cause, they may in addition award the injured party damages for delay, unless precluded by agreement between the contracting parties before arbitration. . . .”

In 1972 various disputes arose between the parties and Hospital filed a demand for arbitration under Paragraph 7 (c) of the contract, with regard to the removal and patching of certain walls, the lack of temporary heat, unlevel floors and water leakage. Thereafter, Pathman demanded arbitration with regard to certain other disputes. The problems were submitted for arbitration and an award was made April 9,1973.

In October of 1973 further problems between the parties developed and Pathman then demanded arbitration pursuant to the contract. At this time Hospital filed its complaint, asking that the arbitration provision in the contract be declared void, and seeking a temporary restraining order, a preliminary injunction, and a permanent injunction prohibiting Pathman from attempting to use said arbitration provision. A temporary restraining order was issued October 19, 1973, and on November 6, 1973, the trial court held that the restraining order would remain in force throughout the trial.

Trial of the matter was concluded on December 11,1973, and on January 4, 1974, the trial court made its entry and judgment, declaring the arbitration provision null and void and enjoining Pathman from any further action to enforce said provision. In making this judgment the trial court specifically found that “. . . plaintiffs lacked the capacity to enter into such an agreement when the contract was executed in 1968 ..

*125 This appeal follows the trial court’s overruling of Pathman’s motion to correct errors.

In this appeal Pathman raises three separate arguments.

1. That Hospital has waived the right to question the arbitration clause because of its participation in the previous arbitration proceedings.

Pathman further argues that Hospital is not entitled to the equitable relief of injunction because it enters the court with unclean hands.

2. That the Indiana Rules of Procedure, Trial Rule 38(E) nullifies prior law declaring agreements to arbitrate void by stating:

“(E) Arbitration. Nothing in these rules shall deny the parties the right by contract or agreement to submit or to agree to submit controversies to arbitration made before or after commencement of an action thereon or deny the courts power to specifically enforce such agreements.”

In this same argument Pathman contends that the Uniform Arbitration Act, passed in Indiana in 1969 (IC 1971, 34-4-2-1 to 34-4-2-22 (Burns Code Ed.)) indicates an intent to revoke any prior case law declaring arbitration of future disputes contrary to public policy.

Finally, Pathman argues in this respect that since arbitration is merely remedial and procedural, any acts relating thereto should be retroactive.

3. That the contract between the parties involves interstate commerce and is subject to the United States Arbitration Act, found at 9 U.S.C.A. § 1, et seq. Pathman contends this is a body of federal substantive law which pre-empts the field of arbitration under the circumstances here involved.

I.

We first deal with Pathman’s arguments that TR. 38(E) and/or the Indiana Uniform Arbitration Act of 1969 serve to validate the arbitration clause.

*126 We would agree with Pathman that there are at least two situations where an act may have retroactive effect. First, where it is necessary to carry out the purpose of the law, and, second, where a remedy alone is provided, and no new rights are given or existing ones removed. See Herrick v. Sayler (7th Cir. 1957), 245 F.2d 171; Malone v. Conner (1963), 135 Ind. App. 167, 189 N.E.2d 590.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MPACT Construction Group, LLC v. Superior Concrete Constructors, Inc.
785 N.E.2d 632 (Indiana Court of Appeals, 2003)
Crawfordsville Apartment Co. v. Key Trust Co. of Florida
692 N.E.2d 478 (Indiana Court of Appeals, 1998)
Brown v. KFC National Management Co.
921 P.2d 146 (Hawaii Supreme Court, 1996)
Elzinga & Volkers, Inc. v. LSSC CORP.
838 F. Supp. 1306 (N.D. Indiana, 1993)
Timms v. Rosenblum
713 F. Supp. 948 (E.D. Virginia, 1989)
Lucas v. American Family Mutual Insurance Co.
403 N.W.2d 646 (Supreme Court of Minnesota, 1987)
Bailey v. Menzie
505 N.E.2d 126 (Indiana Court of Appeals, 1987)
Ex Parte Alabama Oxygen Co., Inc.
433 So. 2d 1158 (Supreme Court of Alabama, 1983)
Keating v. Superior Court
645 P.2d 1192 (California Supreme Court, 1982)
R. J. Palmer Construction Co. v. Wichita Band Instrument Co.
642 P.2d 127 (Court of Appeals of Kansas, 1982)
Kress Corp. v. Edw. C. Levy Co.
430 N.E.2d 593 (Appellate Court of Illinois, 1981)
Devlin v. Shearson Hayden Stone, Inc.
21 Pa. D. & C.3d 213 (Delaware County Court of Common Pleas, 1981)
Burke County Public Schools Board of Education v. Shaver Partnership
279 S.E.2d 816 (Supreme Court of North Carolina, 1981)
Hecla Mining Co. v. Bunker Hill Co.
617 P.2d 861 (Idaho Supreme Court, 1980)
Kendrick Memorial Hospital, Inc. v. Totten
408 N.E.2d 130 (Indiana Court of Appeals, 1980)
Board of County Commissioners v. Stephans
408 A.2d 1017 (Court of Appeals of Maryland, 1980)
Utopia Coach Corp. v. Weatherwax
379 N.E.2d 518 (Indiana Court of Appeals, 1978)
Fite & Warmath Const. Co., Inc. v. Mys Corp.
559 S.W.2d 729 (Kentucky Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
326 N.E.2d 844, 164 Ind. App. 121, 1975 Ind. App. LEXIS 1121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pathman-construction-co-v-knox-county-hospital-assn-indctapp-1975.