Atlantic Painting & Contracting Inc. v. Nashville Bridge Co.

670 S.W.2d 841, 1984 Ky. LEXIS 224
CourtKentucky Supreme Court
DecidedMarch 29, 1984
StatusPublished
Cited by25 cases

This text of 670 S.W.2d 841 (Atlantic Painting & Contracting Inc. v. Nashville Bridge Co.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Painting & Contracting Inc. v. Nashville Bridge Co., 670 S.W.2d 841, 1984 Ky. LEXIS 224 (Ky. 1984).

Opinion

LEIBSON, Justice.

On July 1,1969, Nashville Bridge Company contracted with the Commonwealth of Kentucky for the construction of the superstructure of the 1-24 bridge across the Ohio River between McCracken County, Kentucky and Massac County, Illinois. On September 10, 1969, Nashville Bridge subcontracted with Atlantic Painting & Contracting Inc. and Buckeye Painting & Sheeting Co., Inc., a. Joint Venture, for Atlantic/Buckeye to provide painting services for the superstructure to the bridge.

Both the contract and the subcontract were for a fixed price, based on scheduled completion in the fall of 1971. But the work was not completed until approximately three (3) years later. Atlantic/Buckeye claimed damages from escalated costs incurred by reason of the delay in completion.

Atlantic/Buckeye first notified Nashville Bridge that it expected compensation “for the additional expenses due to the escalation on wages, material, insurances e.t.c. (sic.)” by letter of December 11, 1972. Both parties went on to completion of the work with no specific arrangements for the escalated costs due to delay.

On March 21, 1974, Atlantic/Buckeye’s attorney wrote Nashville Bridge that “by reason of the construction delays and the lack of completion sufficient to allow my clients to proceed timely, it has been computed that an additional $56,205.93 must be recognized as an extra charge under this contract.” There being no response Atlantic/Buckeye sent a second letter demanding arbitration. Section 26 of the subcontract between Atlantic/Buckeye and Nashville Bridge provided that “in the event of any dispute not satisfactorily settled” where there was “no provision for settle *843 ment in the Prime Contract, then either party hereto may ... demand an arbitrator.”

Nashville Bridge resisted arbitration of this dispute on grounds that payments under the contract were limited to the amounts specified therein; that the payment demanded was beyond the scope of the contract so not subject to arbitration. After negotiations, the parties agreed to submit to arbitration the following issue, as expressed in a letter describing the submission from the American Arbitration Association:

“Whether, under the contract involved in the matter, is the question of escalated costs of labor and materials resulting from construction delays, subject to arbitration under the terms of the subject contract.”

Thereafter attorneys for both Nashville Bridge and Atlantic/Buckeye submitted briefs with the American Arbitration Association. On April 15, 1975, an arbitrator duly appointed entered an award to the effect that the claim was not “subject to arbitration.”

Whether Atlantic/Buckeye could claim additional costs resulting from delays was a threshold question to be decided before getting into the facts related to proving the claim. But the arbitrator’s decision expressed as a “reason” underlying the award failure to “give notice of the delay as required under the general specifications.” This statement addresses itself to the conduct of the parties as to which no proof had been taken.

Atlantic/Buckeye filed suit in the McCracken Circuit Court on February 27, 1976, demanding judgment against Nashville Bridge for escalated costs from delay, and also for additional amounts for retain-age and extra work.

Shortly before trial Nashville Bridge moved for summary judgment on grounds that the arbitrator’s award was a bar to the circuit court action. This motion squarely presented the sole question on this appeal. But the trial court tried the case on its merits without ruling on the motion for summary judgment. The trial court found for Atlantic/Buckeye on each of its various claims, and for Nashville Bridge on a counterclaim, and assessed damages at a net amount of $139,083.53 against Nashville Bridge.

The trial court found that both parties entered into the contract with intention that it would be completed in the fall of 1971; that when it became clear that the completion date could not be met, by their conduct, if not expressly, they agreed to continue with the work to completion adjusting for delay damages and extra work on an ad hoc basis. The trial court held that the contract between the parties had undergone a “novation due to the delays” and that they had worked together toward a common goal on their own terms established outside the contract. The court found that neither of the parties in the course of dealing with the other explicitly followed all of the terms in the original contract. The trial court pointed to the fact that Nashville Bridge later brought suit and collected substantial delay damages from the Commonwealth of Kentucky for work done during the period beyond the term of its contract, and that its claim against the Commonwealth originally included delay damages for painting, as evidence for the conclusion that “Nashville Bridge obviously expected a new contract except to the extent of conforming to acceptable standards.”

On appeal the Court of Appeals reversed so much of the decision as provided for payment of delay damages and extra work on grounds that “the prior arbitration award was a bar to further litigation.” The Court of Appeals stated correctly that “Neither we nor the circuit court may evaluate the evidence for either party and substitute our judgment for that of the arbitrator if the award is within the scope of the submission and not fraudulent.” (Emphasis added).

On discretionary review the sole question is whether the arbitrator’s award exceeded the scope of the question presented. We *844 must decide exactly what question was submitted for arbitration and what the arbitrator decided.

Appellee relies on the federal Arbitration Act, found in 9 U.S.C. Sections 1-14. Section 2 specifies that “a written provision in ... a contract evidencing a transaction involving (interstate) commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction, ... shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.” The present contract is certainly one in interstate commerce, and this statute applies. However, Kentucky law is no different. Fite and Warmath Constr. Co., Inc. v. MYS Corp., Ky., 559 S.W.2d 729 (1977).

Initially Nashville Bridge took the position that there was no right to delay damages, so there was nothing to arbitrate. On the other hand Atlantic/Buckeye claimed it was entitled to collect delay damages. If so, the arbitration clause, which was broad enough to encompass “any dispute” between the parties, included delay damages. The essence of the arbitrator’s award, when closely read, is to recognize the existence of a right to collect delay damages, so it would be subject to arbitration, but to find that Atlantic/Buckeye was foreclosed from pursuing its claim for delay damages because it failed to give proper notice that additional compensation would be expected before proceeding with work for which such a claim would be made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A Better Way Wholesale Autos, Inc. v. Saint Paul
338 Conn. 651 (Supreme Court of Connecticut, 2021)
Commonwealth v. Gaither
539 S.W.3d 667 (Missouri Court of Appeals, 2018)
Judge v. Superior Court CA2/7
California Court of Appeal, 2016
Extendicare Homes, Inc. v. Whisman
478 S.W.3d 306 (Kentucky Supreme Court, 2015)
Certain Underwriters at Lloyd's London v. Ashland, Inc.
967 A.2d 166 (District of Columbia Court of Appeals, 2009)
St. Fleur v. WPI Cable Systems/Mutron
879 N.E.2d 27 (Massachusetts Supreme Judicial Court, 2008)
Moscatiello v. Hilliard
939 A.2d 325 (Supreme Court of Pennsylvania, 2007)
Jackson v. Tullar
285 S.W.3d 290 (Court of Appeals of Kentucky, 2007)
Gueyffier v. Ann Summers, Ltd.
50 Cal. Rptr. 3d 294 (California Court of Appeal, 2006)
Joseph v. Advest, Inc.
906 A.2d 1205 (Superior Court of Pennsylvania, 2006)
Wells v. Chevy Chase Bank, F.S.B.
768 A.2d 620 (Court of Appeals of Maryland, 2001)
Eurocapital Group Ltd. v. Goldman Sachs & Co.
17 S.W.3d 426 (Court of Appeals of Texas, 2000)
Siegel v. Prudential Ins. Co. of America
79 Cal. Rptr. 2d 726 (California Court of Appeal, 1998)
Manson v. Dain Bosworth Inc.
623 N.W.2d 610 (Court of Appeals of Minnesota, 1998)
Rosenthal v. Great Western Financial Securities Corp.
926 P.2d 1061 (California Supreme Court, 1996)
Polk v. American Casualty Co. of Reading, PA.
816 S.W.2d 178 (Kentucky Supreme Court, 1991)
Tackett v. Campbell Corp.
781 S.W.2d 758 (Court of Appeals of Kentucky, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
670 S.W.2d 841, 1984 Ky. LEXIS 224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-painting-contracting-inc-v-nashville-bridge-co-ky-1984.