Appalachian Regional Healthcare Inc. v. Beyt, Rish, Robbins Group, Architects

963 F.2d 373, 1992 U.S. App. LEXIS 20399, 1992 WL 107014
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 19, 1992
Docket91-6063
StatusUnpublished
Cited by4 cases

This text of 963 F.2d 373 (Appalachian Regional Healthcare Inc. v. Beyt, Rish, Robbins Group, Architects) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Regional Healthcare Inc. v. Beyt, Rish, Robbins Group, Architects, 963 F.2d 373, 1992 U.S. App. LEXIS 20399, 1992 WL 107014 (6th Cir. 1992).

Opinion

963 F.2d 373

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
APPALACHIAN REGIONAL HEALTHCARE INC. Plaintiff-Appellant
v.
BEYT, RISH, ROBBINS GROUP, ARCHITECTS, Defendant-Appellee.

No. 91-6063.

United States Court of Appeals, Sixth Circuit.

May 19, 1992

Before RALPH B. GUY, Jr., and BATCHELDER, Circuit Judges, and SPIEGEL,* District Judge

PER CURIAM.

This suit involves a dispute between the developer of a hospital and an architectural firm over defects in the hospital. For the reasons set out below, we remand the case to the district court to determine whether the arbitrators' decision should be upheld under the limited standard of review for arbitration awards.

The procedural background of this case is complicated. On August 3, 1983, plaintiff-appellant, Appalachian Regional Healthcare Inc. (ARH), a Kentucky corporation, and defendant-appellee, Beyt, Rish, Robbins Group Architects (Beyt, Rish), a partnership with its principal office in Louisiana, entered into a written contract in which defendant agreed to perform architectural services for construction of an ARH hospital. The parties' contract specifies that all disputes under the contract are to be resolved by arbitration,1 that the award of the arbitrators is final, and that judgment may be entered on the award in any court with jurisdiction over the matter.2 The contract requires ARH to submit a written demand for arbitration "within a reasonable time after the claim, dispute or other matter in question has arisen," but at least within the statute of limitations for filing a lawsuit on the matter.3 However, the contract also specifies that the statute of limitations for an act or failure to act will begin to run not later than the date the project is substantially completed or the date the Certificate of Payment has been issued.4 Perhaps most importantly, the contract states that the agreement shall be governed by Kentucky law.5

On March 29, 1990, ARH demanded arbitration of Beyt, Rish and the construction manager because of structural defects with the hospital building. ARH then brought suit in Fayette Circuit Court in Kentucky seeking an order requiring joint arbitration of the disputes among ARH, Beyt, Rish and the construction manager. In that state court proceeding and in all subsequent proceedings, Beyt, Rish argued that plaintiff's demand for arbitration was not timely because it was not brought within the one-year statute of limitations.6 ARH argued that the seven-year statute of limitations, rather than the one-year statute, applied,7 and, in any case, the demand was timely under the one-year statute. The Fayette Circuit Court ruled that the dispute between ARH and Beyt, Rish should proceed to arbitration but refused to order the joint arbitration sought by ARH. The Court held that the statute of limitations issue was for the arbitrators to decide. Defendant Beyt, Rish appealed this decision to the Kentucky Court of Appeals. That appeal is still pending.

On February 16, 1991, the arbitration panel found that ARH's demand was timely under the statute of limitations, but did not specify which statute applied. The arbitration panel rendered an award in favor of ARH for $573,043.

On March 20, 1991, ARH filed a petition in federal district court to confirm the arbitration award rendered in its favor on February 16, 1991. On May 9, 1991, the Kentucky Supreme Court in Perkins v. Northeastern Log Homes, 808 S.W.2d 809 (Ky.1991), struck down the seven-year statute of limitations, Ky.Rev.Stat. § 417.135, which the arbitrators may have relied upon in deciding that the demand for arbitration was timely. On May 20, 1991, Beyt, Rish filed a petition in Fayette Circuit Court and a motion in the federal court action to vacate the arbitrators' award. ARH then filed a motion to dismiss or abate the state court action on the basis of the district court's prior jurisdiction. The Fayette Circuit Court granted the motion, abating Beyt, Rish's action.

Then, on June 28, 1991, defendant Beyt, Rish moved the federal district court to abstain from exercising its jurisdiction because the state courts needed to determine which state statute of limitations should apply. On August 9, 1991, the district court dismissed ARH's petition, holding that the Federal Arbitration Act was the law which governs the case but that abstention was necessary because the statute of limitations question must be decided by the state court.

The issue we must address, then, is whether the district court's abstention and resultant dismissal of the complaint was proper. We find that the district court need not have addressed the abstention issue because under the Federal Arbitration Act, the arbitration award was subject to a limited scope of review and the only question before the district court was whether the arbitrators overstepped their authority in rendering the award. We remand to the district court to review the arbitration award under the standard we set out below.

The threshold question is whether the Federal Arbitration Act (FAA) or Kentucky arbitration law applies to this contract which contains a Kentucky choice-of-law provision. We believe that the district court was correct that the FAA applies to this case, but for the reasons stated below.

The FAA creates a body of federal substantive law "establishing and regulating the duty to honor an agreement to arbitrate." Moses Cone Memorial Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 25 n. 32, 103 S.Ct. 927, 942 n. 32 (1983).8 It applies "to any arbitration agreement within the coverage of the Act." Id. at 24, 103 S.Ct. at 941. Because this contract is one "evidencing a transaction involving commerce," 9 U.S.C. § 2, this contract is covered by the FAA.9 The question, however, is whether the contract's choice-of-law provision trumps the federal arbitration law in favor of Kentucky arbitration law.

The FAA does not preempt the field of arbitration so long as the state law does not require judicial resolution of claims that the parties agreed to arbitrate. Volt Info. Sciences v. Board of Trustees, 489 U.S. 468, 475-76 109 S.Ct. 1248, 1253-54 (1989). In Volt, the Supreme Court held that it would not disturb a California Court of Appeals decision interpreting a choice-of-law provision in a contract to mean that the state's procedural arbitration rules applied to the contract. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
963 F.2d 373, 1992 U.S. App. LEXIS 20399, 1992 WL 107014, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-regional-healthcare-inc-v-beyt-rish-ro-ca6-1992.