Todd Shipyards Corp. v. Cunard Line, Ltd.

943 F.2d 1056, 1991 WL 163340
CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 27, 1991
DocketNos. 89-16607, 89-16610
StatusPublished
Cited by93 cases

This text of 943 F.2d 1056 (Todd Shipyards Corp. v. Cunard Line, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Todd Shipyards Corp. v. Cunard Line, Ltd., 943 F.2d 1056, 1991 WL 163340 (9th Cir. 1991).

Opinion

BRUNETTI, Circuit Judge:

Cunard Line Limited (“Cunard”) appeals from a district court order confirming an arbitration award in the matter of Todd Shipyards Corporation and Cunard Line Limited, American Arbitration Association (“AAA”), Case No. 13-110-0658-84, and confirming the denial of Cunard’s counterclaim. We have jurisdiction pursuant to 28 U.S.C. § 1291 and affirm.

I. FACTS

In September 1983, Todd Shipyards Corporation (“Todd”) and Cunard entered into a contract for the repair and refit of a passenger cruise ship, the M.Y. Sagafjord. The work was undertaken at Todd’s San Francisco shipyard for a fixed price of $4.5 million. The project was extensive and included repairs to the body and interior of the ship, the upgrade and conversion of existing cabins and common areas, and the addition of a two-level module structure housing twenty cabins and a nightclub. The contract contemplated the work would be completed by December 20, 1983.

Section 1 of the contract between Todd and Cunard states: “Drawings and Specifications pertinent to this Contract are attached hereto as Exhibits A and B respectively, and made a part hereof.” Neither drawings nor specifications were attached, in fact, and as a result the contract was incomplete in various respects. The parties disagree about the nature and extent of issues left open by the contract, and about terms and understandings outside the written agreement.

The arbitration panel declined to make specific findings of fact. Because this court must accept the facts as decided by the arbitration panel, see infra, III. Standard of Review, the description that follows relies on findings implicit in the arbitration award.

a.Plans and Specifications

The contract contemplated these would be part of the agreement. No plans or specifications were attached to the contract, however, and the arbitration panel decided, despite Cunard’s assertion that the parties had agreed to utilize drawings and descriptions contained in two loose-leaf binders, that no such agreement was made. As such, the panel held that in order to determine the intent of the parties with regard to the project, “evidence extrinsic to [the contract] must be used to determine” the nature of the agreement.

b.Construction Engineering and Working Drawings

Todd’s bid for the contract included the cost of retaining engineers to inspect the ship and prepare detailed working drawings for the project. In the course of negotiations Cunard informed Todd it would engage an outside firm, Hapag-Lloyd (“Hapag”), to perform this work and provide these materials to Todd. The contract price was reduced by $235,000 to reflect this deletion from the agreement. Todd asserted, and the panel apparently agreed, Cunard’s failure to provide adequate drawings caused Todd enormous overtime expense.

c.Supply of Construction Materials, Fixtures and Furnishings

The contract reflected Cunard’s desire to provide a variety of construction materials, [1059]*1059fixtures and furnishings, rather than leave the purchase of these materials to Todd. The panel found Cunard breached this part of the agreement by failing to provide various materials and sufficient installation instructions, and by failing to sufficiently pre-customize certain of the fixtures.

d. Open Items

A number of design decisions left open by the agreement were essential to the completion of the project. The panel found that delay with regard to these decisions by Cunard, and Cunard’s “design as you go” approach to the project as a whole led to a large increase in the cost of the project to Todd.

Because of Cunard’s failure to provide specifications, drawings, materials and design support during the project, Todd was not able to complete the repair and conversion of the Sagafjord in the fifty days allotted. More significantly, Todd incurred a large additional expense due to overtime worked in an effort to complete the project despite Cunard’s intransigence. Cunard refused to pay even the fixed contract price ($4.5 million) because Todd failed to complete the entire project within the contract period.

II. PROCEEDINGS BELOW

Todd filed suit against Cunard, and in rem against the Sagafjord, alleging breach of contract, quantum merit, breach of duty of good faith and fair dealing, and fraud. Todd filed a demand for arbitration pursuant to a comprehensive arbitration clause in the contract. The arbitration commenced in March 1985.1

The arbitration was dominated at once by the question whether the written agreement dated September 22, 1983, was the entire contract between the parties. Cunard filed a motion in the District Court of New Jersey seeking determination under 9 U.S.C. § 4 whether it was within the authority of the arbitration panel to decide the scope of the written agreement. The action was transferred to the Northern District of California where Judge Williams held that the arbitration clause contained in the contract contemplated arbitration of “any and every dispute,” which included the question whether the written contract was a complete representation of the parties’ agreement.

In August 1986 the arbitration panel issued an interim ruling on “Contract Composition.” The panel determined: (a) the contract referred to exhibits which purportedly described the nature of the “repairs” contemplated by the agreement; (b) such exhibits were not attached to the contract; (c) the contract did not contain the complete understanding of the parties; (d) extrinsic evidence was necessary to arrive at something approaching the parties’ understanding; and (e) various amendments and additions to the agreement occurred after the parties signed the written contract. As a result of these findings the panel invalidated the contract’s integration section (§ 19) which, as Cunard avers, “emasculated the parties’ fixed price contract.”

After an extensive arbitration over more than two years the panel issued an award in favor of Todd for $11.4 million, including compensatory damages, punitive damages, attorneys’ fees, and costs. The panel also denied Cunard’s counterclaim for Todd’s alleged failure to perform the contract within the period allotted.

Cunard filed a motion in the District Court of New Jersey to vacate the award, while Todd asked the District Court for the Northern District of California to confirm the award. The entire matter was considered by the latter court which confirmed the award in its entirety. See Todd Shipyards Corp. v. Cunard Lines Ltd., 735 F.Supp. 1463 (N.D.Cal.1989).

III. STANDARD OF REVIEW

The Federal Arbitration Act, 9 U.S.C. at § 10, sets out the grounds upon which a federal court may vacate the decision of an arbitration panel. The statute addresses decisions influenced by corrup[1060]*1060tion or undue influence, and cases in which arbitrators exceed their power under the terms of an agreement to arbitrate. Courts have interpreted this section narrowly, in light of Supreme Court authority strictly limiting federal court review of arbitration decisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Bldg. Corp. v. S. Cal. Dist. Council of Laborers
373 F. Supp. 3d 1309 (C.D. California, 2019)
Jon Sanchez v. Robert Elizondo
878 F.3d 1216 (Ninth Circuit, 2018)
Richard Wawock v. Csi Electrical Contractors
649 F. App'x 556 (Ninth Circuit, 2016)
Metzler Contracting Co. LLC v. Stephens
774 F. Supp. 2d 1073 (D. Hawaii, 2011)
Reliastar Life Insurance v. EMC National Life Co.
564 F.3d 81 (Second Circuit, 2009)
White v. Mayflower Transit, LLC
481 F. Supp. 2d 1101 (C.D. California, 2007)
Birmingham News Co. v. Horn
901 So. 2d 27 (Supreme Court of Alabama, 2004)
FREIGHTLINER, LLC v. Teamsters Local 305
336 F. Supp. 2d 1118 (D. Oregon, 2004)
Vernon Vu Luong v. Circuit City Stores, Inc.
356 F.3d 1188 (Ninth Circuit, 2004)
Association of Flight Attendants v. Aloha Airlines, Inc.
158 F. Supp. 2d 1200 (D. Hawaii, 2001)
Strain-Japan R-16 School District v. Landmark System, Inc.
51 S.W.3d 916 (Missouri Court of Appeals, 2001)
Bowen v. Amoco Pipeline Co.
254 F.3d 925 (Tenth Circuit, 2001)
Commonwealth Associates v. Letsos
40 F. Supp. 2d 170 (S.D. New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
943 F.2d 1056, 1991 WL 163340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/todd-shipyards-corp-v-cunard-line-ltd-ca9-1991.