Atsa of California, Inc., Plaintiff/cross-Claimant/appellant v. Continental Insurance Co., Etc. v. Cairo General Contracting Co., Cross-Defendant/appellee. Hamed Abulhassan, Counter-Defendant/appellant v. Cairo General Contracting Co., Cross-Defendant/appellee

702 F.2d 172, 1983 U.S. App. LEXIS 29523
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 21, 1983
Docket81-6017
StatusPublished
Cited by55 cases

This text of 702 F.2d 172 (Atsa of California, Inc., Plaintiff/cross-Claimant/appellant v. Continental Insurance Co., Etc. v. Cairo General Contracting Co., Cross-Defendant/appellee. Hamed Abulhassan, Counter-Defendant/appellant v. Cairo General Contracting Co., Cross-Defendant/appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atsa of California, Inc., Plaintiff/cross-Claimant/appellant v. Continental Insurance Co., Etc. v. Cairo General Contracting Co., Cross-Defendant/appellee. Hamed Abulhassan, Counter-Defendant/appellant v. Cairo General Contracting Co., Cross-Defendant/appellee, 702 F.2d 172, 1983 U.S. App. LEXIS 29523 (9th Cir. 1983).

Opinion

702 F.2d 172

ATSA OF CALIFORNIA, INC., Plaintiff/Cross-Claimant/Appellant,
v.
CONTINENTAL INSURANCE CO., etc., Defendant,
v.
CAIRO GENERAL CONTRACTING CO., Cross-Defendant/Appellee.
Hamed ABULHASSAN, Counter-Defendant/Appellant,
v.
CAIRO GENERAL CONTRACTING CO., Cross-Defendant/Appellee.

Nos. 81-6017, 81-6026.

United States Court of Appeals,
Ninth Circuit.

Submitted Dec. 27, 1982.
Decided March 21, 1983.

Alan M. Mund, Fulop & Hardee, Beverly Hills, Cal., for plaintiff/cross-claimant/appellant.

Stephen T. Owens, Graham & James, Los Angeles, Cal., Robert E. Currie, Latham & Watkins, Newport Beach, Cal., for cross-defendant/appellee.

Appeal from the United States District Court for the Central District of California.

Before ANDERSON and PREGERSON, Circuit Judges, and SOLOMON,* District Judge.

PREGERSON, Circuit Judge:

ATSA of California, Inc. ("ATSA"), and Hamed Abulhassan, an officer of ATSA, appeal the district court's order staying all proceedings and directing all parties to submit to arbitration in accordance with the written contract between ATSA and Cairo General Contracting Co. ("Cairo").1 The stay order is appealable under 28 U.S.C. Sec. 1292(a)(1) in accordance with the Enelow-Ettelson rule.2 Wren v. Sletten Construction Co., 654 F.2d 529, 532-33 (9th Cir.1981).

BACKGROUND

In April 1978, ATSA, a California corporation, and Cairo, an Egyptian corporation, entered into a written agreement under which ATSA would prefabricate and turn over to Cairo a factory for manufacturing building panels and Cairo would pay ATSA $4.1 million.

In January 1979, ATSA shipped the components of the prefabricated factory to the Port of Alexandria, Egypt. In connection with the shipment, ATSA purchased marine insurance from Continental Insurance Company of New York ("Continental") specifying that any loss would be payable to ATSA. ATSA then endorsed in blank and transferred to Cairo Continental's certificate of insurance. During the voyage the insured shipment sustained damage.

ATSA asserts that, in October 1979, Cairo and ATSA orally agreed that ATSA would repair the damaged items in return for an assignment of Cairo's interest in the insurance proceeds.

In May 1980, while Continental was processing the insurance claim, Cairo and Abulhassan executed a written contract providing that Abulhassan would represent Cairo in negotiations with Continental in return for a percentage of any settlement paid by Continental. In November 1980, Continental issued a settlement check for $1.75 million payable to ATSA and Cairo jointly. Cairo refused to endorse the check and turn it over to ATSA, asserting that the prefabricated factory ATSA delivered to Cairo was unacceptable.

In January 1981, ATSA filed suit against Continental, alleging that Continental had breached the marine insurance contract by refusing to pay ATSA the insurance proceeds. In March, Continental answered and counterclaimed, interpleading the proceeds of the policy. The district court dismissed Continental and ordered Cairo joined as a defendant. In June, ATSA filed a cross-claim against Cairo alleging five causes of action. Cairo filed its answer in August and pleaded the arbitration clause in its contract with ATSA as an affirmative defense. Cairo also filed counterclaims against ATSA. Cairo drew Abulhassan into the case in August 1981 as a counterdefendant in its counterclaim. Abulhassan then filed cross-claims against Cairo.

On November 16, 1981, the district court stayed all proceedings pending a final arbitral award. It ordered ATSA and Cairo each to name a "neutral, disinterested" arbitrator and directed all parties, including Abulhassan, to submit to arbitration "in accordance with the Rules for the International Court of Arbitration promulgated by the International Chamber of Commerce." The court denied Abulhassan's request to appoint an arbitrator.

ANALYSIS

I. Validity of the Arbitration Clause

ATSA argues that arbitration should not be compelled because the arbitration clause in its agreement with Cairo does not designate either the governing law or the forum for arbitration. ATSA's argument has no merit.

The validity of an arbitration agreement affecting commerce is determined by federal law. Becker Autoradio U.S.A., Inc. v. Becker Autoradiowerk GmbH, 585 F.2d 39, 43 (3d Cir.1978); Coenen v. R.W. Pressprich & Co., 453 F.2d 1209, 1211 (2d Cir.), cert. denied, 406 U.S. 949, 92 S.Ct. 2045, 32 L.Ed.2d 337 (1972); cf. Textile Workers Union v. Lincoln Mills, 353 U.S. 448, 456-57, 77 S.Ct. 912, 917-18, 1 L.Ed.2d 972 (1957). Under federal law, when parties agree to submit disputes to arbitration, it is presumed that the arbitrator will be authorized to determine all issues of law and fact necessary to resolve the dispute. Ormsbee Development Co. v. Grace, 668 F.2d 1140, 1146 (10th Cir.1982); Continental Materials Corp. v. Gaddis Mining Co., 306 F.2d 952, 954 (10th Cir.1962). Thus, the arbitrator has authority to determine the applicable law. Moreover, 9 U.S.C. Sec. 4 authorizes the district court to order that arbitration take place within the district. See Econo-Car International, Inc. v. Antilles Car Rentals, Inc., 499 F.2d 1391 (3d Cir.1974).

II. Waiver of the Right to Arbitration

A. Alleged Failure of Cairo to Name an Arbitrator

ATSA contends that Cairo waived its right to arbitration by refusing to nominate an arbitrator when ATSA first requested arbitration in December 1980. Cairo, on the other hand, contends that ATSA did not make a bona fide effort to invoke the arbitration clause. A dispute about a waiver of arbitration may properly be referred to the arbitrator. World Brilliance Corp. v. Bethlehem Steel Co., 342 F.2d 362 (2d Cir.1965). Therefore, the court did not abuse its discretion when it referred the issue of waiver to arbitration.

B. Cairo's Participation in Pleading and Discovery

ATSA also contends that Cairo waived its right to arbitration when it filed pleadings and engaged in discovery before seeking arbitration. Under the federal policy favoring arbitration, a party does not waive arbitration merely by engaging in action inconsistent with an arbitration provision. E.g., Hilti, Inc. v. Oldach, 392 F.2d 368 (1st Cir.1968). Moreover, inconsistent behavior alone is not sufficient; the party opposing the motion to compel arbitration must have suffered prejudice. Shinto Shipping Co. Ltd. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doyle v. UBS Fin. Servs., Inc.
Second Circuit, 2025
Morgan v. Sundance, Inc.
596 U.S. 411 (Supreme Court, 2022)
iPayment
Court of Appeals of North Carolina, 2018
iPayment, Inc. v. Grainger
808 S.E.2d 796 (Court of Appeals of North Carolina, 2018)
George Clinton v. Hendricks & Lewis Pllc
557 F. App'x 665 (Ninth Circuit, 2014)
Raymond James Financial Services, Inc. v. Honea
55 So. 3d 1161 (Supreme Court of Alabama, 2010)
Stern v. Cingular Wireless Corp.
453 F. Supp. 2d 1138 (C.D. California, 2006)
Omar v. Ralphs Grocery Co.
13 Cal. Rptr. 3d 562 (California Court of Appeal, 2004)
Pyramid Travel, Inc. v. Sri Lankan Travel, Inc.
64 F. App'x 70 (Ninth Circuit, 2003)
Cybertek, Inc. v. Bentley Systems, Inc.
182 F. Supp. 2d 864 (D. Nebraska, 2002)
Chloe Z Fishing Co. v. Odyssey Re (London) Ltd.
109 F. Supp. 2d 1236 (S.D. California, 2000)
Creative Telecommunications, Inc. v. Breeden
120 F. Supp. 2d 1225 (D. Hawaii, 1999)
Ids Life Insurance Co. v. Sunamerica, Inc.
103 F.3d 524 (Seventh Circuit, 1997)
IDS Life Insurance v. SunAmerica, Inc.
103 F.3d 524 (Seventh Circuit, 1996)
Petitions of Laitasalo
196 B.R. 913 (S.D. New York, 1996)
Curtis G. Testerman Co. v. Buck
667 A.2d 649 (Court of Appeals of Maryland, 1995)
Zurich Insurance v. Ennia General Insurance
882 F. Supp. 1438 (S.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
702 F.2d 172, 1983 U.S. App. LEXIS 29523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atsa-of-california-inc-plaintiffcross-claimantappellant-v-continental-ca9-1983.