Pullman, Incorporated v. Phoenix Steel Corporation

304 A.2d 334, 1973 Del. Super. LEXIS 157
CourtSuperior Court of Delaware
DecidedFebruary 9, 1973
StatusPublished
Cited by32 cases

This text of 304 A.2d 334 (Pullman, Incorporated v. Phoenix Steel Corporation) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pullman, Incorporated v. Phoenix Steel Corporation, 304 A.2d 334, 1973 Del. Super. LEXIS 157 (Del. Ct. App. 1973).

Opinion

OPINION

WRIGHT, Judge.

Defendant, Phoenix Steel Corporation, a Delaware corporation (Phoenix), has moved for summary judgment in this action for declaratory judgment brought by Pullman, Incorporated, also a Delaware corporation (Pullman). The issue is whether or not a State court must apply the United States Arbitration Act, 9 U.S.C. §§ 1-14 (1970), in cases before it involving contracts which touch or concern interstate or foreign commerce.

Summary judgment may be granted only where, considering the facts in a light most favorable to the non-moving party, there is no material issue of fact and the moving party is entitled to judgment as a matter of law. Matas v. Green, 3 Storey 473, 171 A.2d 916 (Del.Super.1961); Superior Court Rules, Civil, R. 56(c), Del.C. Ann.

The essential facts of the case are as follows: In August, 1967, Pullman, through one of its divisions, Swindell-Dressler Co., entered into a written contract with Phoenix by which Pullman was to “design, engineer, furnish and erect” an electric furnace melt shop to be used in the production of steel at Phoenix’s Claymont, Delaware plant. Incorporated by reference into the contract was a separate Technical Proposal previously prepared by Pullman and approved by Phoenix which set forth detailed plans, designs and specifications for the project. As work on the melt shop neared completion, Phoenix, anxious to place the $18.2 million facility into operation as soon as possible, asked for and received Pullman’s permission to start up some of the new equipment. This action by the parties contravened the express terms of the contract, which provided that the melt shop would be turned over to Phoenix after Pullman had finished it. It *336 was during this initial period and afterward that Phoenix claims it discovered many deficiencies in the facility which prevented it from attaining its expected production standards. Pullman and Phoenix attempted to correct the, problems that arose in the operation of the complex facility, but Phoenix continued to express dissatisfaction with the work.

As provided for in the contract, the parties entered into negotiations to iron out their differences. These discussions began in about January, 1969 and continued until August, 1971 without success. Finally, on August 5, 1971, Phoenix notified Pullman in writing that it was invoking the arbitration provisions of the contract, demanded that the dispute be submitted to binding arbitration and named its arbitrator. In response to requests by Pullman, defendant three times granted extensions of time to permit continued negotiations. Finally, on November 12, 1971, the date the third and last extension granted by defendant expired, Pullman filed suit in the Court of Chancery to enjoin Phoenix from proceeding with arbitration. That Court granted a stay pending a determination in the Superior Court whether an executory agreement to arbitrate is valid and enforceable under Delaware law.

The same day it filed the above suit in the Court of Chancery, Pullman brought this action for declaratory relief under the provisions of 10 Del.C. §§ 6S01-03 and Rule 57, Superior Court Rules, Civil, seeking judgment (1) declaring that Pullman is not liable to defendant with respect to any matter arising out of the design and construction of the melt shop; (2) declaring that defendant may not demand arbitration; and (3) staying arbitration proceedings. Phoenix in its answer counterclaimed contending that the arbitration provisions of the contract are valid and enforceable or, in the alternative, that Pullman is liable in damages for breach of the arbitration agreement.

The arbitration provisions of the contract provide:

(1) Any difference or dispute concerning any matter or thing done or omitted to be done by either party shall be given fair consideration by both parties and an earnest effort shall be made by them to reach an equitable settlement.
(2) If such effort, after a reasonable time not exceeding one (1) month, shall fail, then the difference or dispute shall be submitted to an arbitrator acceptable to both parties, who shall be a citizen of the United States residing and doing business in the United States and reasonably familiar professionally with the general field to which this agreement relates. His decision shall be binding on both parties and no appeal shall be taken therefrom.
(3) If within thirty (30) days after either party requests arbitration the parties are unable to agree on a single arbitrator, or at the option of either party on notice to the other, each party shall within fifteen (15) days thereof appoint one (1) arbitrator, and the two (2) arbitrators so selected shall select a third one, qualified as in the next preceding paragraph. If the two (2) arbitrators chosen by the parties do not within thirty (30) days agree upon the choice of the third arbitrator, he shall be named as (sic) the request of the more diligent party by the American Arbitration Association and shall be qualified as provided in the next preceding paragraph. If either party should fail to appoint its arbitrator within the time limited, the arbitration shall proceed before the one (1) chosen, with the same force, effect, and finality as if there were three (3).

The two remaining paragraphs of the arbitration article relate to the vote required to make an award by the arbitrators and the allocation of the costs of arbitration between the two parties.

It seems clear that the defendant’s letter of August 5, 1971 was sufficient notice of its intent to invoke arbitration. Preliminarily, plaintiff asserts that summa *337 ry judgment cannot be granted because there exists a material issue of fact whether Phoenix waived its right to invoke arbitration by waiting more than 18 months in the face of an express provision that arbitration shall be invoked “after a reasonable time not exceeding one (1) month”. This case is distinguishable from Ferguson v. Berbusse, 216 A.2d 876 (Del.Super.1966), where it was held that a delay of 9 and one-half months in asserting a right to arbitration after the defendant filed its answer constituted a waiver by defendant of its right to invoke arbitration; here, defendant demanded arbitration prior to commencement of suit by plaintiff. Whether defendant here waived its right to invoke the arbitration provisions of the contract is a question to be decided by the trier of fact. Nathan Miller, Inc. v. Northern Ins. Co. of New York, 3 Terry 523, 39 A.2d 23 (Del.Super.1944); G.M.S. Realty Corp. v. Girard Fire & Marine Ins. Co., 8 Terry 216, 89 A.2d 857 (Del.Super.1952).

Assuming, without deciding, that defendant did not waive its rights to arbitration under the contract, the Court now turns to the question of whether the United States Arbitration Act is applicable in actions before State courts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penton Business Media Holdings, LLC v. Informa PLC
Court of Chancery of Delaware, 2018
CitiMortgage, Inc. v. Swift.
Superior Court of Delaware, 2015
Smith v. Guest
16 A.3d 920 (Supreme Court of Delaware, 2011)
CIGNA Ins. Co. v. Didimoi Prop. Holdings, NV
110 F. Supp. 2d 259 (D. Delaware, 2000)
Kysor Industrial Corp. v. Margaux, Inc.
674 A.2d 889 (Superior Court of Delaware, 1996)
Humm v. Aetna Casualty & Surety Co.
656 A.2d 712 (Supreme Court of Delaware, 1995)
Figgs v. Bellevue Holding Co.
652 A.2d 1084 (Superior Court of Delaware, 1994)
Patton v. Simone
626 A.2d 844 (Superior Court of Delaware, 1992)
Sinex v. Wallis
611 A.2d 31 (Superior Court of Delaware, 1991)
World Films, Inc. v. Paramount Pictures Corp.
125 P.R. Dec. 352 (Supreme Court of Puerto Rico, 1990)
Staats ex rel. Staats v. Lawrence
576 A.2d 663 (Superior Court of Delaware, 1990)
Wilson v. Dover Skating Center, Ltd.
566 A.2d 1020 (Superior Court of Delaware, 1989)
Trabaudo v. Kenton Ruritan Club, Inc.
517 A.2d 706 (Superior Court of Delaware, 1986)
Olmstead v. General Motors Corp., Inc.
500 A.2d 615 (Superior Court of Delaware, 1985)
Ex Parte Alabama Oxygen Co., Inc.
433 So. 2d 1158 (Supreme Court of Alabama, 1983)
Tennessee River Pulp & Paper Co. v. Eichleay Corp.
637 S.W.2d 853 (Tennessee Supreme Court, 1982)
State Ex Rel. St. Joseph Light & Power Co. v. Donelson
631 S.W.2d 887 (Missouri Court of Appeals, 1982)
Kress Corp. v. Edw. C. Levy Co.
430 N.E.2d 593 (Appellate Court of Illinois, 1981)
MERRILL LYNCH PIERCE, ETC. v. Melamed
405 So. 2d 790 (District Court of Appeal of Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
304 A.2d 334, 1973 Del. Super. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pullman-incorporated-v-phoenix-steel-corporation-delsuperct-1973.