Tennessee River Pulp & Paper Co. v. Eichleay Corp.

637 S.W.2d 853, 1982 Tenn. LEXIS 428
CourtTennessee Supreme Court
DecidedJuly 6, 1982
StatusPublished
Cited by12 cases

This text of 637 S.W.2d 853 (Tennessee River Pulp & Paper Co. v. Eichleay Corp.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee River Pulp & Paper Co. v. Eichleay Corp., 637 S.W.2d 853, 1982 Tenn. LEXIS 428 (Tenn. 1982).

Opinion

OPINION

BROCK, Justice.

The issue to be addressed is whether a contractual provision to arbitrate future disputes is revocable at will, in accordance with Tennessee common law, or whether it is irrevocable by virtue of the U. S. Arbitration Act, 9 U.S.C. § 1 et seq. (hereinafter the Act).

On July 13, 1977, Eichleay Corporation and Tennessee River Pulp & Paper Company, hereinafter, called Tennessee River, entered into a contract whereby Eichleay, as general contractor, agreed to expand the production facilities of Tennessee River’s plant located in Counce, Tennessee. The contract price was $15,116,700.00 which included $350,000.00 in non-significant changes. Article 38 of the General Conditions of the contract document contained an agreement to arbitrate which provides that:

“A11 claims, disputes and other matters in question arising out of or relating to, this contract or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, then obtaining, unless the parties mutually agree otherwise. This agreement so to arbitrate shall be specifically enforceable under prevailing laws. The award rendered by the arbitrator shall be final, and judgment may be entered upon it in accordance with the applicable law in any court having jurisdiction thereof.” (Emphasis added.)

Article 11 of the contract provides that “this contract shall be construed in accordance with and governed by the laws of the State of Tennessee or political subdivisions thereof.”

The contract provided that work was to begin on the expansion of the production facilities on July 15,1977, and completed on September 15, 1978. On March 23, 1979, the contract was 98% complete and the plaintiff, Tennessee River, learned at this time that the defendant, Eichleay, was making a claim for approximately $4,000,-000.00 in additional expenses. On May 25, 1979, the contract was officially completed.

On October 18, 1979, Tennessee River made a “final payment” to Eichleay under the contract pursuant to a release which provided that certain claims of Eichleay were reserved. After it became apparent that the disputes could not be resolved by amicable agreement, on December 18, 1979, Eichleay filed its written demand for arbitration in accordance with the provisions contained in the contract. On December 26, 1979, Tennessee River gave notice that it had elected to revoke its agreement to arbitrate future disputes. On January 8, 1980, Eichleay responded that it considered revocation not to be effective and cited the United States Arbitration Act, 9 U.S.C. § 2. 1

*855 On January 24, 1980, Tennessee River filed this action in the Chancery Court for Davidson County and obtained a temporary restraining order staying the arbitration proceedings pending judicial determination of its right to revoke the arbitration agreement. Eiehleay filed a motion to dissolve the temporary restraining order and to stay judicial proceedings pending arbitration.

After an oral hearing, the Chancellor issued a memorandum opinion in which he denied the application for a temporary injunction, granted Eichleay’s motion to dissolve the temporary restraining order, and stayed judicial proceedings, holding: (i) the contract in dispute is one “involving commerce” within the meaning of the Act; (ii) that the Act applied to every contract involving interstate commerce; and (iii) that agreements to arbitrate, contained in such contracts, are valid, irrevocable and enforceable.

The Chancellor held that the congressional power to regulate commerce as expressed in the Act was the supreme law of the land and superseded any common law of Tennessee in conflict therewith. An Order was entered in Chancery Court, in accordance with the memorandum opinion, denying plaintiff’s application for temporary injunction.

Plaintiff moved the court to grant an interlocutory appeal pursuant to Rule 9(b) of the Rules of Appellate Procedure and the Chancellor entered an order granting plaintiff’s application. The following issues were certified on appeal:

(1) Whether, in an action in a state court, an agreement to arbitrate contained in a contract involving interstate commerce is binding, enforceable and irrevocable by virtue of the United States Arbitration Act and the supremacy clause of the United States Constitution and
(2) Whether the Court abused its discretion, or otherwise erred, in declining to limit the scope of the issues to be submitted to arbitration, concluding that the scope of arbitrable issues was, initially, a question to be determined by the arbitrators.

The Court of Appeals granted the interlocutory appeal and remanded the cause to the Chancellor for the limited purpose of consideration and disposition of an application for stay of arbitration pending appeal. Application for stay of arbitration was denied on June 10, 1980. The two issues certified by the Chancellor were argued before the Court of Appeals, Western Section, sitting at Nashville and that court reversed the Chancellor’s decree and remanded the matter for further proceedings. We then granted permission to appeal to this Court.

The Chancellor determined that the contract between the parties was one “involving commerce” within the meaning of the Act. The Act provides that “a written provision in any maritime transaction or contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction ... shall be valid, irrevocable and enforceable.” Tennessee River asserts that the expansion project “affects” commerce but claims that these “contacts” with interstate commerce do not “evidence a transaction involving commerce” and are not sufficient to invoke the provisions of the Act.

The extent to which this contract involves commerce is clear. The contract exceeds $15,000,000.00 and is between two Delaware corporations; the plaintiff has its home office in Illinois, whereas, the defendant’s home office is in Pennsylvania. The materials used, the labor employed, and the subcontractors involved, in substantial part, came to the project from outside Tennessee. Eiehleay purchased substantial quantities of materials and supplies from vendors in at least 26 states; and 34 per cent of all materials and supplies purchased by Eiehleay were from out-of-state vendors. There is ample basis in the record to support the conclusion that the contract was one “involving commerce.”

The Court of Appeals, relying upon two landmark arbitration cases, Robert Lawrence Co. v. Devonshire Fabrics, Inc., 271 *856 F,2d 402 (2d Cir. 1959), cert. granted, 362 U.S. 909, 80 S.Ct. 682, 4 L.Ed.2d 618, dismissed under Rule 60, 364 U.S. 801, 81 S.Ct. 27, 5 L.Ed.2d 37 (1960), and Prima Paint Corp. v. Flood and Conklin,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delisa Roose v. Bath Fitter Tennessee, Inc.
Court of Appeals of Tennessee, 2025
Mid-South Maintenance Inc. v. Paychex Inc.
Court of Appeals of Tennessee, 2015
Dale Supply Company v. York International Corp
Court of Appeals of Tennessee, 2003
Sanderson Farms, Inc. v. Gatlin
848 So. 2d 828 (Mississippi Supreme Court, 2003)
Urology Associates v. Cigna Healthcare
Court of Appeals of Tennessee, 2002
J.C. Bradford v. Douglas Kitchen
Court of Appeals of Tennessee, 2002
Sanderson Farms, Inc. v. Roy R. Gatlin
Mississippi Supreme Court, 2000
Frizzell Construction Co. v. Gatlinburg, L.L.C.
9 S.W.3d 79 (Tennessee Supreme Court, 1999)
GAF Corp. v. Werner
485 N.E.2d 977 (New York Court of Appeals, 1985)
Ex Parte Alabama Oxygen Co., Inc.
433 So. 2d 1158 (Supreme Court of Alabama, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
637 S.W.2d 853, 1982 Tenn. LEXIS 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-river-pulp-paper-co-v-eichleay-corp-tenn-1982.