Insite Corp. v. Walsh Constr. Co. P.R. (In Re Insite Corp.)

906 F.3d 138
CourtCourt of Appeals for the First Circuit
DecidedOctober 5, 2018
Docket17-1436P
StatusPublished
Cited by3 cases

This text of 906 F.3d 138 (Insite Corp. v. Walsh Constr. Co. P.R. (In Re Insite Corp.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Insite Corp. v. Walsh Constr. Co. P.R. (In Re Insite Corp.), 906 F.3d 138 (1st Cir. 2018).

Opinion

LIPEZ, Circuit Judge.

*141 The appellant in this case is a bankrupt subcontractor, Insite, which claims that a general contractor, Walsh, improperly withheld payments belonging to its bankruptcy estate. Insite sought to recover the payments by initiating an adversary proceeding against Walsh in bankruptcy court in Puerto Rico. The bankruptcy court found that the withheld payments were not property of Insite's estate, the district court affirmed, and Insite now appeals to us.

Applying the Supreme Court's decision in Pearlman v. Reliance Insurance Co. , 371 U.S. 132 , 141-42, 83 S.Ct. 232 , 9 L.Ed.2d 190 (1962), we have held that, under Puerto Rico law, funds withheld by a general contractor to cure a subcontractor's default and to complete a subcontractor's work do not become property of the subcontractor, and hence are not part of the subcontractor's bankruptcy estate. See Segovia Dev. Corp. v. Constructora Maza, Inc. , 628 F.2d 724 , 729-30 (1st Cir. 1980). The bankruptcy court found that this well-established principle, known as the Pearlman doctrine, prevented Insite from gaining a property interest in the funds withheld by Walsh, and it accordingly granted summary judgment to Walsh.

Because we conclude that Insite had no right under the subcontract with Walsh to any of the funds it claims were withheld, we do not rely on the Pearlman doctrine. In the unusual circumstances of this case, neither that doctrine nor the parties' contract answers the question that determines Insite's right to payment: whether a defaulting subcontractor who has no contractual right to compensation is nonetheless entitled to an equitable recovery if the general contractor has benefited at the subcontractor's expense. In that scenario, the subcontractor's right to recovery, if any, must be determined by other principles of local law. Thus, although we agree with the bankruptcy and district courts that Insite is not due funds under its contract with Walsh, the courts still must consider whether Walsh was benefited by Insite's post-default performance in such a way that Insite has an equitable claim under Puerto Rico law. We therefore vacate the judgment and remand to allow the bankruptcy court to address that issue in the first instance.

I.

A. Factual & Procedural Background

In September 2010, the Department of Veterans Affairs awarded appellee Walsh Construction Company Puerto Rico ("Walsh") a contract to build an addition to a VA facility in San Juan, Puerto Rico. Two months later, Walsh subcontracted with appellant Insite Corporation, Inc. ("Insite") for certain concrete and masonry work. Insite in turn contracted with a number of sub-subcontractors and suppliers (collectively, its "suppliers") and began its work on the job site. The terms of the Walsh-Insite contract entitled the latter to periodic progress payments, subject to certain conditions. Insite regularly applied *142 for, and Walsh regularly satisfied, such payments through the month of November 2011.

More precisely, the last progress payment issued by Walsh corresponded to work performed by Insite through November 21, 2011. Insite would later apply for three other progress payments totaling $591,953: $179,897 for work performed from November 22 to December 26, 2011; $70,750 for work performed from December 27, 2011 through January 22, 2012; and $341,306 for work performed from January 23 through March 7, 2012. Walsh did not approve these payment applications for reasons that we shall explain.

On the morning of December 30, 2011, Walsh hand-delivered Insite a letter titled "Notice of Default," accusing Insite of materially breaching the parties' subcontract by failing to pay its suppliers. Specifically, Walsh asserted that a check issued by Insite to pay a supplier for work performed in October 2011 was rejected for insufficient funds, and that Insite had balances overdue by 60 to 120 days with two other suppliers. Consistent with the terms of the parties' contract, the letter provided Insite 72 hours to remedy its default, and demanded assurance that Insite intended and was able to perform the balance of its contracted work.

That evening, at 5:49 p.m., Insite filed for Chapter 11 bankruptcy. Insite subsequently notified Walsh of this development and assured Walsh that the protection afforded by federal bankruptcy law would allow it to continue executing the subcontract. Walsh responded with a letter contesting the adequacy of Insite's assurance and accusing Insite of failing to timely pay two more suppliers.

Meanwhile, Walsh notified Insite's surety, United Surety & Indemnity Company ("USIC"), that Insite was in default of the subcontract. USIC, however, refused to perform on its bond, asserting that it had no obligation to perform until Walsh formally terminated its subcontract with Insite. Though Walsh had accused Insite of defaulting on the subcontract, it was unable to terminate the agreement before Insite entered bankruptcy. And, once Insite filed for bankruptcy, Walsh could not terminate the contract without the bankruptcy court's approval. See , e.g. , Computer Commc'ns Inc. v. Codex Corp. ( In re Computer Commc'ns ), 824 F.2d 725 , 728 (9th Cir. 1987) (holding that defendant was required to obtain bankruptcy court's permission before terminating contract with debtor). 1

With Walsh unable to terminate Insite, and USIC refusing to perform on its bond, Insite continued to execute at least some work on the job site after it filed for bankruptcy. The value of the work performed by Insite during this time, and in the month preceding its bankruptcy filing, is unclear. Taken at face value, the progress payment applications submitted by Insite for its work from November 22, 2011 to March 7, 2012 suggest that Insite performed $591,953 worth of work for which it was not paid. However, Walsh was not satisfied with Insite's performance during this time. Walsh sent a number of letters to Insite accusing it of repeatedly defaulting on the contract and of failing to timely prosecute its work. Furthermore, to keep Insite's suppliers working on the project, Walsh issued $63,927.15 in jointly payable checks to Insite and its suppliers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
906 F.3d 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/insite-corp-v-walsh-constr-co-pr-in-re-insite-corp-ca1-2018.