Framingham Trust Company v. Gould-National Batteries, Inc., American Casualty Company v. Framingham Trust Company
This text of 427 F.2d 856 (Framingham Trust Company v. Gould-National Batteries, Inc., American Casualty Company v. Framingham Trust Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Sewell & Smith Construction Company (the contractor) agreed to construct a factory addition for Gould-National Batteries, Inc. (the owner) for $133,000. 1 *857 Framingham Trust Company (the bank) agreed to provide the financing on the security of an assignment of the contractor’s present and future accounts receivable, which financing agreement was duly executed and recorded. American Casualty Company (the surety) furnished the performance and payment bonds for the contractor as required by the owner. On default by the contractor, the surety completed the work at an outlay of some $3000, paid some $50,000 to previously unpaid laborers and material-men, and then sought to be reimbursed by the owner out of the unpaid balance owing for the completed work. The bank concedes the surety’s right to the $3000 for completion of the work, but claims that it — not the surety — is entitled to the remainder of the unpaid balance held by the owner at the time of default. The owner, having conceded liability for the unpaid balance, is involved only as the stakeholder. 2
The district court granted summary judgment for the bank, holding that its rights as assignee with a perfected security interest had priority over the subrogation rights of the performing surety. 3 307 F.Supp. 1008 (D.Mass. 1969). We reverse. In National Shawmut Bank of Boston v. New Amsterdam Casualty Co., 411 F.2d 843 (1st Cir. 1969), we held that the surety’s right of subrogation survived the passage of the Uniform Commercial Code in Massachusetts and prevailed over the bank’s security interest in the unpaid balance. 4 In discussing the extent of the surety’s subrogation rights, we stated, at 848, that the performing surety
“is subrogated not only to the right of the government [the owner] to pay laborers and materialmen from funds retained out of progress payments [citing cases], but also to the government’s right to apply to the cost of completion the earned but unpaid progress payments in its hands at the time of default [citing cases].
The bank concedes the second proposition but contests the former. However, that proposition was reaffirmed in American Fire & Casualty Co. v. First National City Bank of New York, 411 F.2d 755, 758 (1st Cir. 1969), cert. de *858 nied, 396 U.S. 1007, 90 S.Ct. 563, 24 L.Ed.2d 499 (1970), wherein we upheld the performing surety’s right to such unpaid progress payments and unpaid balance as reimbursement for its payments to previously unpaid laborers and materialmen. While we think those decisions dispositive of the issue here presented, we add a few brief comments in response to the reasons found persuasive by the district court in reaching a contrary decision.
First, as indicated by our decision in American Fire & Casualty Co., supra, we do not understand the propositions enunciated in National Shawmut Bank to be confined to cases arising under the Miller Act, where the United States is the owner. The government’s well established right to have the laborers and materialmen paid out of the unpaid progress payments or unpaid balance does not arise from any legal obligation to such suppliers but simply from its equitable obligation to those who provide it with labor and materials. United States v. Munsey Trust Co., 332 U.S. 234, 240-241, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947); Henningsen v. United States Fidelity & Guaranty Co., 208 U.S. 404, 410, 28 S.Ct. 389, 52 L.Ed. 547 (1908); National Surety Corp. v. United States, 133 F.Supp. 381, 383-384, 132 Ct.Cl. 724 (1955), cert. denied sub nom., First National Bank in Houston v. United States, 350 U.S. 902, 76 S.Ct. 181, 100 L.Ed. 793 (1955); see Pearlman v. Reliance Insurance Co., 371 U.S. 132, 136-139, 83 S.Ct. 232, 9 L.Ed.2d 190 (1962). We see no reason why that same equitable obligation to the laborers and materialmen should not exist on the part of the non-government owner, who receives the same benefit from those suppliers— construction work and materials — as did the government in the aforementioned cases. 5 Moreover, the non-government owner, like the government, has an interest in seeing its suppliers paid so that the work necessary for completion of the contract can be done with minimum disruption and expense. 6 See also National Surety Corp. v. United States, supra, 133 F.Supp. at 383.
Therefore, since both the government and the non-government owner have the right to pay their suppliers out of the unpaid balance, 7 the performing *859 surety, through subrogation, is entitled to assert that right, and prevail over the secured creditor. National Shawmut Bank, supra, 411 F.2d at 848. The district court suggested, however, that according such right to the surety would circumvent the Massachusetts lien statutes, the materialmen and suppliers having failed to perfect a lien under Massachusetts General Laws, chapter 254, section 4, at the time of default. However, those lien statutes are circumvented just as much — or as little 8 — by according the surety the right to be reimbursed for labor and material costs incurred subsequent to default, which right the district court readily recognized. We fail to see why it should preclude reimbursement to the surety for labor and material costs incurred prior to default when it clearly does not have that effect on reimbursement for such costs incurred after default.
In sum, we cannot escape the conclusion that in both a practical and a legal sense, the payment of previously unpaid laborers and materialmen is a cost of completing the contract.
In No. 7524, the judgment should be reversed and judgment entered for the surety for the entire unpaid balance in the possession of the owner at the time of default, the surety’s cost of completing the contract and paying the previously unpaid laborers and materialmen having exceeded the amount of such unpaid balance. In No. 7523, the judgment should be reversed and the action dismissed.
Reversed and remanded for appropriate action.
.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
427 F.2d 856, 8 U.C.C. Rep. Serv. (West) 228, 1970 U.S. App. LEXIS 8807, Counsel Stack Legal Research, https://law.counselstack.com/opinion/framingham-trust-company-v-gould-national-batteries-inc-american-ca1-1970.