Framingham Trust Co. v. Gould-National Batteries, Inc.

307 F. Supp. 1008, 1969 U.S. Dist. LEXIS 10624
CourtDistrict Court, D. Massachusetts
DecidedDecember 30, 1969
DocketCiv. A. Nos. 67-936, 68-207
StatusPublished
Cited by3 cases

This text of 307 F. Supp. 1008 (Framingham Trust Co. v. Gould-National Batteries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Framingham Trust Co. v. Gould-National Batteries, Inc., 307 F. Supp. 1008, 1969 U.S. Dist. LEXIS 10624 (D. Mass. 1969).

Opinion

OPINION

GARRITY, District Judge.

This is a diversity action brought under the Declaratory Judgments Act, 28 U.S.C. § 2201. The matter is presently before the court on crossmotions for summary judgment. At issue are the rights to unpaid contract balances and retainages in the hands of an owner at the time of default by a contractor. The plaintiff, American Casualty Company (“the Surety”), claims the funds in question under the doctrine of equitable subrogation. The defendant, Framingham Bank and Trust Company (“the Bank”) claims them on the basis of an assignment of contract rights, under the Uniform Commercial Code, Mass.G.L. c. 106, assigned to the Bank by the construction contractor whose performance of the contract was presumably financed by the Bank to a large extent. The defendant Langan is the receiver in bankruptcy of the defaulted contractor, Sew-ell & Smith Construction Company. He has renounced any claim in this case to rights superior to those of either the Surety or the Bank. Defendant Gould-National Batteries, Inc., is the owner of the property under construction and party to the construction contract with Sewell & Smith. Gould-National is also the obligee of the surety bonds. It makes no claim with respect to the funds in question and is a mere stakeholder as to that part remaining in its possession.1 The facts set forth in the [1010]*1010following paragraphs are either undisputed or have been stipulated.

Findings of Fact

1. On December 3, 1965 S.ewell & Smith executed a security agreement with the Bank assigning its accounts and contract rights as security for repayment of money loaned then and thereafter. The financing statements were duly recorded in the office of the clerk of the Town of Framingham on December 28, 1965 and in the office of the Secretary of State on December 29, 1965.

2. On May 23, 1966 Sewell & Smith executed a contract with Gould-National for the construction of an addition to its factory building located in Marlboro, Massachusetts. The contract price was $133,000. The contract, in article 5, and the “General Conditions” of the American Institute of Architects which were incorporated in it by reference, in articles 24 and 25, conditioned Sewell & Smith’s right to payments upon its proving to the extent required by the architect that it had paid for materials and labor connected with the work. Article 22 of the general conditions permitted termination should the contractor fail to make prompt payment to subcontractors or for material or labor. Article 26, entitled “Payments Withheld” provided,

The Architect may withhold or, on account of subsequently discovered evidence, nullify the whole or a part of any certificate to such extent as may be necessary in his reasonable opinion to protect the owner from loss on account of: * * * c) Failure of the Contractor to make payments properly to subcontractors or for material or labor.

Article 32, “Liens”, provided,

Neither the final payment nor any part of the retained percentage shall become due until the Contractor, if required, shall deliver to the owner a complete release of all liens arising out of the contract, or receipts in full in lieu thereof and, if required in either case, an affidavit that so far as he has knowledge or information the releases and receipts include all the labor and material for which a lien could be filed.

Articles 36 and 37 provided that the contract created no contractual relation between any subcontractor and the owner; and that the owner was under no obligation to pay to or see to the payment of any sums to any subcontractor.

3. Also on May 23, 1966 the Surety and Sewell & Smith, as principal, executed both a performance bond and a labor and material payment bond in favor of Gould-National, as obligee, guaranteeing performance of the contract and payment of labor and material claims. These bonds were not recorded in any official registry or office.

4. On or about February 16, 1967 Sewell & Smith gave notice to Gould-National and the Surety of its inability to complete the contract and it formally acknowledged its default. On December 27, 1967 Sewell & Smith was adjudicated a bankrupt.

5. Following Sewell & Smith’s default, Gould-National made demand upon the Surety to complete the job and the Surety complied. The amount expended by the Surety under its performance bond was $3,237.94. The cost .of finishing the work was less than 2.5% of the contract price of $133,000, indicating that at the time of default the actual construction was all but complete. As a result of the decision in National Shawmut Bank of Boston v. New Amsterdam Casualty Company, 1 Cir. 1969, 411 F.2d 843, the bank does not contest the Surety’s right to the $3,237.94 it spent completing the job. However, at the time of its default Sewell & Smith was delinquent in payments to its workers and suppliers to the extent of $53,293.07, which sum the Surety was obliged to pay to the contractor’s laborers and materialmen under its payment bond.

6. The Surety claims $25,691.60, which represents all contract balances [1011]*1011and retainages not paid by Gould-National to the contractor.2 The Bank claims $22,453.66 of that amount as. the assignee of Sewell & Smith’s contract rights. The Bank concedes that the difference, $3,237.94, belongs to the Surety as reimbursement of its costs in completing the contract. From the total sum, Gould-National paid the Surety $19,089.10 on December 7,1967.

7. Both the losses suffered by the Surety and the amount of Sewell & Smith’s indebtedness to the Bank now and at the time of default are in excess of the $25,691.60 contract balances and retainages withheld by Gould-National.

8. The workers and suppliers to whom Sewell & Smith was delinquent took no action to create liens against Gould-National’s property pursuant to Mass.G.L. c. 254, § 4, nor against funds in its hands pursuant to Mass.G.L. c. 254, § 81.

Conclusions of Law

This case presents another facet of the general problem discussed in National Shawmut Bank of Boston v. New Amsterdam Casualty Company, supra, of the relative priority of the claims of an assignee bank with a perfected security interest and a performing surety company to funds due a defaulting construction contractor by the owner of the premises on which the construction contract was being performed. The National Shawmut Bank case held that a surety completing a contract under its performance bond had priority over a bank holding a security interest in the contractor’s accounts receivable by virtue of the surety being subrogated to the right of the Government, as owner in that case, to apply to the cost of completion whatever indebtedness or retain-ages remained in its hands at the time of default.3 The dispute here relates to the surety’s payments under its payment bond of an amount in excess of the sum in the hands of the owner at the time of the contractor’s default, which sum is also less than the amount due the assignee bank.

There are other differences in the case at bar from the situation in the National Shawmut Bank

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
307 F. Supp. 1008, 1969 U.S. Dist. LEXIS 10624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/framingham-trust-co-v-gould-national-batteries-inc-mad-1969.