Fidelity & Casualty Co. of New York v. First National Exchange Bank

193 S.E.2d 678, 213 Va. 531, 1973 Va. LEXIS 177
CourtSupreme Court of Virginia
DecidedJanuary 15, 1973
DocketRecord 7877 and 7878
StatusPublished
Cited by8 cases

This text of 193 S.E.2d 678 (Fidelity & Casualty Co. of New York v. First National Exchange Bank) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Casualty Co. of New York v. First National Exchange Bank, 193 S.E.2d 678, 213 Va. 531, 1973 Va. LEXIS 177 (Va. 1973).

Opinion

Cochran, J.,

delivered the opinion of the court.

The final order entered June 2, 1971, from which these appeals were granted, denied relief to The First National Exchange Bank of Virginia (Bank) on its bill to enforce a mechanic’s lien under Code § 43-1 et seq. (Record No. 7878), and denied relief to The Fidelity and Casualty Company of New York (Fidelity) on its cross-bill to recover certain monies received by the Bank (Record No. 7877).

The controversy, arising from the financial collapse of Virginia Prestressed Concrete Corporation (Prestressed) and its wholly owned subsidiary, Atlas Erectors, Incorporated (Atlas), was submitted to the trial court under a stipulation that comprised narrative statements of facts and voluminous exhibits.

Woodward & Lothrop, Incorporated, owner, entered into a contract dated November 2, 1964, with Chas. H. Tompkins Company (Tompkins), contractor, for construction of a warehouse building in Fairfax County. By a subcontract entered into November 23, 1964, between Tompkins and Prestressed, it was agreed that Prestressed would “furnish all labor, material, equipment and plant and services necessary to complete in place the ‘Precast and PrecastPrestressed Concrete Building Frame’ ” specified in the prime contract, for the sum of $761,279.00. By amendment to the subcontract, also dated November 23, 1964, it was provided that obligations imposed upon Prestressed under the prime contract would not arise until execution of the prime contract. The amendment, proposed and prepared by Prestressed, also modified the terms of payment by leaving $94,975.00 for erection work subject to a 10% retainage on progress payments, but making $666,304.00 for materials fabricated and supplied on the job site subject only to one-half of 1% discount on progress payments. It was stipulated that the main purpose of the *533 amendment was to avoid retainage on the fabrication portion of the subcontract.

Fidelity issued payment and performance bonds dated November 23, 1964, in the penalty of $666,304.00, naming Prestressed as principal, Fidelity as surety and Tompkins as obligee, for fabrication and supply of materials. It issued payment and performance bonds in the penalty of $94,975.00 on the same date, with Atlas as principal, Fidelity as surety and Tompkins as obligee, covering erection of materials on the job site. Fidelity required Prestressed and Atlas to execute indemnity agreements assigning their rights under the subcontract, conditioned upon default. 1

By subcontract dated December 30, 1964, Prestressed sub-subcontracted to John Howard Steel Erectors, Inc. (Howard) the bulk of the erection work, with a few exclusions, for $89,000.00. Prior to June, 1965, Howard became financially distressed and Prestressed, by agreement dated June 10, 1965, re-subcontracted the work undertaken by Howard to Neal Lawrence, Inc. on a cost plus percentage basis. By subcontract dated June 10, 1965, Prestressed sub-subcontracted to Tonstad Caulking Company the caulking of wall panels at the job site for $5,390.00. Also in June, 1965, following a request by Fidelity to examine all subcontract assignments, Prestressed and Atlas, without advising Fidelity, executed a subcontract dated back to December 30, 1964, under which Prestressed purported to sub-subcontract to Atlas the entire hauling of materials and erection thereof on the job site for $94,975.00. Nevertheless, except for some minor tasks, Atlas actually performed no erection or caulking work on the project.

Prestressed’s employee, DuPuy, serving as project manager, was responsible for delivery of materials and proper erection thereof on the job site. Prestressed, with the knowledge of Tompkins, entered *534 into agreements with several other companies for production of a substantial portion of the concrete materials which it was required to supply under its subcontract with Tompkins.

For many years the Bank had financed Prestressed. Several loans were secured by deeds of trust on Prestressed’s real estate, plant and equipment. Since 1958 the Bank had also made operating loans to Prestressed for the performance of contracts made by Prestressed with others. These loans were secured by assignments of the respective contracts to the Bank without notice to third parties. Between January 11, 1965, and June 3, 1965, the Bank advanced to Prestressed the aggregate sum of $395,000.00, evidenced by 16 promissory notes, to finance the Tompkins-Prestressed subcontract. For each advance Prestressed executed its note and an assignment to the Bank of the entire amount of the subcontract proceeds in the sum of $761,279.00.

The last progress payment under the subcontract was made by Tompkins to Prestressed by check dated June 10, 1965, in the sum of $206,525.12. It was received by the Bank on Saturday, June 12, 1965, without notice to Fidelity, with which the Bank had been conferring about the financial problems of Prestressed. The Bank applied $108,610.28 to Prestressed’s notes arising from the TompkinsPrestressed subcontract, leaving a balance of $64,781.21 payable to the Bank, and deposited the remainder to Prestressed’s account. The Bank required Prestressed to pay out of the deposit the aggregate amount of $86,330.80 to two suppliers.

On June 18, 1965, all work at the job site under the TompkinsPrestressed subcontract was suspended. A few days later Prestressed and Atlas filed voluntary petitions in bankruptcy.

The Bank cooperated with Tompkins to effect completion of performance of the Prestressed subcontract. The Bank assisted in having Prestressed’s plant leased to Southern Block and Pipe Company and in causing finished materials to be released for delivery on the job site. It advanced money for a week’s payroll, for which it was subsequently reimbursed in the Prestressed bankruptcy proceedings. Erection of materials was completed by other companies on order of Tompkins. Upon completion of the job there remained in Tompkins’s hands a balance of $84,658.14 of the Tompkins-Prestressed subcontract proceeds.

On September 7, 1965, the Bank, as assignee of Prestressed and in its own right, filed a mechanic’s lien to secure its claim to these proceeds, but Tompkins paid the money to Fidelity as surety for Prestressed. Fidelity paid numerous mechanics’ liens filed against Pre *535 stressed in the aggregate amount of $88,360.68, and one filed against Atlas in the amount of $14,595.38. Only the claim against Atlas was litigated to judgment. In addition two other non-lienor claimants against Prestressed were paid by Fidelity.

The Bank commenced a suit to enforce its lien on March 4, 1966, seeking $84,602.02 of the subcontract balance allocated to fabrication and materials, as security for payment of Prestressed’s indebtedness of $64,781.21, plus per diem interest of $10.80 from August 10, 1965, and attorney fees of $9,717.18. The owner, Tompkins and Fidelity, named as defendants, filed a demurrer challenging the Bank’s right to claim a mechanic’s Hen either as assignee or in its own right. This demurrer was overruled by the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cdm Enterprises v. Manufactured Housing Bd.
530 S.E.2d 441 (Court of Appeals of Virginia, 2000)
Harrisonburg Plaza, Inc. v. Saam, Inc.
50 Va. Cir. 520 (Rockingham County Circuit Court, 1999)
Pollard & Bagby, Inc. v. Pierce Arrow, L.L.C.
521 S.E.2d 761 (Supreme Court of Virginia, 1999)
Smith v. Sink
442 S.E.2d 646 (Supreme Court of Virginia, 1994)
Historic Green Springs, Inc. v. Brandy Farm, Ltd.
32 Va. Cir. 98 (Louisa County Circuit Court, 1993)
Hutto v. Bic Corp.
800 F. Supp. 1367 (E.D. Virginia, 1992)
Waskey v. Lewis
294 S.E.2d 879 (Supreme Court of Virginia, 1982)
Charett v. Charett
256 S.E.2d 238 (Court of Appeals of North Carolina, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
193 S.E.2d 678, 213 Va. 531, 1973 Va. LEXIS 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-casualty-co-of-new-york-v-first-national-exchange-bank-va-1973.