Great American Insurance v. United States

492 F.2d 821, 20 Cont. Cas. Fed. 83,149, 203 Ct. Cl. 592, 1974 U.S. Ct. Cl. LEXIS 95
CourtUnited States Court of Claims
DecidedFebruary 20, 1974
DocketNo. 151-72
StatusPublished
Cited by23 cases

This text of 492 F.2d 821 (Great American Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great American Insurance v. United States, 492 F.2d 821, 20 Cont. Cas. Fed. 83,149, 203 Ct. Cl. 592, 1974 U.S. Ct. Cl. LEXIS 95 (cc 1974).

Opinion

Cowen, Chief Judge,

delivered the opinion of the court:

In this case, we are once again asked to determine the lights of several parties to priority in the balance due under a Government contract. On June 24,1970, the United States, through the Department of the Navy, contracted with T. G. Williamson, doing business as Williamson Construction Company, for the replacement of exterior siding on Johnson Housing (MEMQ), Naval Air Station Memphis, Millington, Tennessee. Plaintiff, Great American Insurance Company, executed both performance and payment bonds for the contract pursuant to the Miller Act, 49 Stat. 793 (1935), as amended, 40 U.S.C. §§ 270a-270e (1970). On October 19,1970, the contractor assigned to Boulevard State Bank all moneys due or to become due under the contract, and on the same day, the assignee bank gave notice of the assignment to plaintiff and defendant.1

In this action, plaintiff seeks reimbursement from the Government for payments made to laborers and materialmen [596]*596under the terms of the surety’s payment bond. The defendant asserts a right to $10,200 of the contract balance on the basis of a change order dated August 16,1971, which assessed that amount against the contractor as liquidated damages for delay in completing the contract. Defendant further contends that in the event this court determines that any amount paid by defendant to the assignee bank was in fact erroneously paid, then defendant is entitled to a judgment against both the assignee and the contractor to the extent the surety is awarded a recovery herein. The Government has impleaded the contractor and the assignee bank as third-party defendants in this suit, and they contest their liability to the defendant.

The case is before the court on the parties’ cross-motions for summary judgment, and there are no factual issues except those relating to the Government’s right to judgment against the contractor.

The total contract price for the construction project was $102,564. During the performance of the contract, the defendant made two progress payments to the Boulevard State Bank. The first payment was made on December 3, 1970, in the amount of $42,660 (excluding retainages), and the second progress payment was on January 6,1971, in the amount of $31,160 (excluding retainages).

On March 26, 1971, the final housing units in the project were accepted by defendant as complete. Following completion of the contract, on May 10, 1971, Great American advised the defendant in writing that it had notice of unpaid claims of subcontractors in excess of $31,000, which amount exceeded the unpaid contract balance then being held by the Government ($28,718). Great American then requested that the surety’s name be 'added as joint payee in any future payments to the contractor or that all future payments be withheld. Also, on May 10, 1971, the contractor requested that a “final payment” be made on the contract in the amount of $28,718.

The Government officer responsible for administering the contract took the position that payment could be withheld at the request of the surety only if the surety presented evidence of actual payment of the contractor’s obligations, [597]*597together with a court order or a written agreement signed by all parties. On May 19, 1971, the Government made a payment designated on the voucher as “Third Partial Payment” in the amount of $7,108 (excluding retainages) to the assignee bank.

On June 29, 1971, the contractor filed a petition in bankruptcy, and on July 1,1971, he was adjudicated a bankrupt. The contractor alleges that notice of the bankruptcy was given to the United States by mailing notice on or about July 1,1971, to the District Director of Internal Revenue, at Wichita, Kansas, and to the United States Attorney in Topeka, Kansas.

During the pendency of the bankruptcy, Williamson applied to the District Court for the District of Kansas for an order restraining the plaintiff from pursuing the prosecution of pending suits against the bankrupt. Williamson’s application referred to two suits brought in the Western District of Tennessee by the subcontractors, Willey Painting Corporation and Crump Lime & Cement Company, against the surety under the payment bond. In these actions, the surety asserted a claim for a judgment over and against Williamson for the amount of any judgment entered against the surety in favor of the subcontractors.

By order of September 14,1971, the referee in bankruptcy refused to enjoin the prosecution of the suits in the Western District of Tennessee, because he found that the surety’s suit was necessary to enable the surety to pursue the contract retainages under the contract between the bankrupt and the United States. The referee further found that the subject matter of the litigation in Tennessee did not constitute an asset of the bankrupt’s estate, and the referee also ordered the trustee to abandon any claim to any retainage funds held by the United States under the contract in question. On March 3, 1972, T. G. Williamson received a discharge in bankruptcy by order of the District Court for the District of Kansas.

It is established that during September 1971, the plaintiff surety discharged all claims made against it by reason of its payment bond. In so doing, the surety paid out $32,772.49, which exceeds the surety’s total claims in this action.

[598]*598There are three distinct contract funds in issue: (1) the $7,108 payment made to the assignee bank on May 19,1971; (2) $10,200 claimed and retained by the Government as liquidated damages pursuant to the change order of August 16, 1971; and (3) a contract retainage in the amount of $11,400, which the Government admittedly holds as a stakeholder.

I

The principal issues raised by this case concern the $7,108 payment made to the assignee bank, and the liability of the contractor or the assignee bank to the defendant for its erroneous payment of that amount. We have repeatedly held that the surety who satisfies the contractor’s obligations to pay laborers and materialmen under the payment bond has an equitable interest, superior to the interest of the contractor’s assignee or the contractor’s trustee in bankruptcy, in the unpaid contract balance held by the Government as a stakeholder. See, e.g., Argonaut Insurance Co. v. United States, 193 Ct. Cl. 483, 496, 434 F. 2d 1362, 1369 (1970); National Surety Corp. v. United States, 132 Ct. Cl. 724, 728-29, 133 F. Supp. 381, 384, cert. denied, 350 U.S. 902 (1955) ; Continental Casualty Co. v. United States, 145 Ct. Cl. 99, 169 F. Supp. 945 (1959) .2 On May 10,1971, when plaintiff notified defendant of the unpaid claims of laborers and materialmen and asserted a claim to the unpaid contract balance, the defendant still held a total of $28,718, including the $7,108 in question. At that time, the Government asserted no claim to the $7,108 so that the Government held that amount as a stakeholder with full knowledge that both the surety and the assignee claimed a right to the money. Eelying primarily on our decisions in Fireman's Fumd Insurance Co. v. United States, 190 Ct. Cl. 804, 421 F. 2d 706 (1970); Home Indemnity Co. v. United States, 180 Ct. Cl. 173, 376 F. 2d 890 (1967); Newark Insurance Co. v. United States, 144 Ct. Cl. 655, 169 F. Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National American Insurance v. United States
498 F.3d 1301 (Federal Circuit, 2007)
Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
American Renovation & Construction Co. v. United States
65 Fed. Cl. 254 (Federal Claims, 2005)
LaSalle Talman Bank, F.S.B. v. United States
45 Fed. Cl. 64 (Federal Claims, 1999)
International Fidelity Insurance v. United States
42 Cont. Cas. Fed. 77,368 (Federal Claims, 1998)
National Surety Corporation v. United States
118 F.3d 1542 (Federal Circuit, 1997)
Transamerica Premier Insurance v. United States
32 Fed. Cl. 308 (Federal Claims, 1994)
International Fidelity Insurance v. United States
37 Cont. Cas. Fed. 76,277 (Court of Claims, 1992)
Fireman's Fund Insurance Company v. The United States
909 F.2d 495 (Federal Circuit, 1990)
Ransom v. United States
35 Cont. Cas. Fed. 75,674 (Court of Claims, 1989)
United States Fidelity & Guaranty Co. v. United States
35 Cont. Cas. Fed. 75,637 (Court of Claims, 1989)
Reliance Insurance v. United States
15 Cl. Ct. 62 (Court of Claims, 1988)
Sentry Insurance A Mutual Co. v. United States
34 Cont. Cas. Fed. 75,257 (Court of Claims, 1987)
Balboa Insurance Company v. The United States
775 F.2d 1158 (Federal Circuit, 1985)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
American Fidelity Fire Insurance
578 F.2d 1389 (Court of Claims, 1978)
American Fidelity Fire Insurance v. United States
513 F.2d 1375 (Court of Claims, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
492 F.2d 821, 20 Cont. Cas. Fed. 83,149, 203 Ct. Cl. 592, 1974 U.S. Ct. Cl. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-american-insurance-v-united-states-cc-1974.